Red Bobtail Transportation

CourtArmed Services Board of Contract Appeals
DecidedMay 23, 2024
Docket63771
StatusPublished

This text of Red Bobtail Transportation (Red Bobtail Transportation) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Red Bobtail Transportation, (asbca 2024).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) Red Bobtail Transportation ) ASBCA No. 63771 ) Under Contract No. HTC711-14-D-R028 )

APPEARANCE FOR THE APPELLANT: Michael D. Maloney, Esq. Williams Mullen PC Tysons Corner, VA

APPEARANCES FOR THE GOVERNMENT: Caryl A. Potter, III, Esq. Air Force Deputy Chief Trial Attorney Geoffrey R. Townsend, Esq. Patricia W. Walter, Esq. Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE EYESTER PURSUANT TO BOARD RULE 12.2

Red Bobtail Transportation (RBT) appeals a contracting officer’s final decision (COFD) denying its breach of contract, good faith and fair dealing, and prompt payment claim for $798.22. 1 According to RBT, the United States Transportation Command (USTRANSCOM or government) improperly deducted amounts from invoices for services RBT performed. USTRANSCOM argues the claim lacks a certification and is untimely filed, and also disputes all of RBT’s contentions.

RBT elected to pursue this appeal pursuant to the Board’s Rule 12.2, Small Claims (Expedited) procedure. Accordingly, this decision shall have no precedential value, and in the absence of fraud shall be final and conclusive and may not be appealed or set aside. 41 U.S.C. § 7106(b)(4)-(5). RBT also pursued this appeal pursuant to Board Rule 11, in which the decision rests upon written

1 Originally, the claim was for a total of $8,522.35 plus interest (compl. ¶ 1). In its brief, RBT states that after conducting discovery, it realized of the 19 invoices it originally challenged, only two are timely (AGA0103 and AGB0093). RBT therefore withdrew challenges to the remaining 17 invoices. (App. br. at 2 n.1) The total RBT argues is due is $292.88 for AGA0103 and $505.34 for AGB0093, plus interest (id. at 4). After becoming aware of the reduced claim amount, each party still submitted the Rule 12.2 briefs. evidence without courtroom testimony. Based on the following, we grant RBT’s appeal in part and deny it in part.

FINDINGS OF FACT (FOF)

1. USTRANSCOM awarded fixed-priced, multiple award indefinite quantity Contract No. HTC711-14-D-R028 to RBT, effective January 3, 2014, for National Afghan trucking services for three suites of services: bulk fuels (suite 1), dry cargo (suite II), and heavy cargo (suite III) (R4, tab 1 at 1, 4, 12; tab 2 at 19, 21, 24). The period of performance included a one-year base period, 2 one-year option periods, and a 6-month option to extend services period (R4, tab 1 at 4-6). The contract incorporated by reference RBT’s proposal and included as attachments a Schedule B, Unit Price Schedule (3 JAN 14) and a performance work statement (PWS) (15 MAR 13), none of which were included in the record (id. at 9, 55).

2. The contract incorporated by reference Federal Acquisition Regulation (FAR) 52.212-4, CONTRACT TERMS AND CONDITIONS—COMMERCIAL ITEMS (FEB 2012) (R4, tab 1 at 9). In addition, the contract included FAR 52.216-18, ORDERING (OCT 1995), which states that all delivery and task orders issued are subject to the terms and conditions of the contract (id. at 11).

3. As relevant here, USTRANSCOM exercised a 3-month option to extend the contract and issue a delivery order to RBT through March 16, 2017 (app. supp. R4, tabs 1, 2). The parties agree that the PWS effective February 1, 2016 is applicable here because the disputed invoices are for deliveries in January and February 2017 (app. br. at 6; gov’t br. at 1-2). 2 There is nothing in the record showing the modification which incorporated this revised PWS and whether it was signed by RBT.

4. The relevant PWS detailed the “common mission requirements and standards that apply to each suite of transportation service.” To start, the government would issue a transportation movement request (TMR) for a mission for a single asset which specified the terms and shipment data. (App. supp. R4, tab 3 at 33) The terms included the required spot date (RSD), required load date (RLD), required delivery date (RDD), and adjusted RDD (ARDD). The RSD is the date the asset is required at the origin location and is two days prior to the RLD. The RLD is the date the asset is required to be ready to upload the cargo. The RDD is the required date of delivery by the contractor and is met when the asset is at the entry control point waiting area of the destination location. Finally, the ARDD is the shift in delivery date based on actual load date; the adjusted RDD cannot be sooner than

2 The parties filed only one brief each and the Board’s Order dated April 10, 2024 explained that the briefs should be akin to reply and sur-reply briefs or used to expand upon specific disputed facts or legal points. 2 the original RDD. All missions ordered were to be paid based on the number of mission units (MUs), which were in 25 kilometer increments, between the origin and destination on the TMR. (App. supp. R4, tab 3 at 34) Almost all missions required security support and, in some cases, RBT was required to provide the security using the Afghan Public Protection Force (APPF) (id. at 43-44). RBT was responsible for meeting all RSDs, RLDs and RDDs (id. at 36).

5. The initial contract did not contain a section on deductions for missions completed a day late, which is the issue in this appeal (see R4, tab 5 at 3-10 (COFD)). Rather, it set forth performance objectives and stated the performance thresholds for the RLD and RDD were 90 percent on time (PWS at 30, available at https://sam.gov/opp/837518d0a84a30a765535dd0f3e20638/view). The government would use these performance objectives to assess contractor performance and if a contractor failed to meet the minimum performance objectives, it could result in less future task orders or other remedies (id. at 29-30).

6. The February 2017 revised PWS was different. This PWS stated that a failed/partial pay mission included a completed mission where the contractor failed to meet the RSD, RLD or RDD (app. supp. R4, tab 3 at 40). The PWS set forth a point system to partially compensate contractors for failed/partial pay missions as follows:

For each mission, missing RSD, RLD, or RDD (RDD when not exclusively caused by APPF) constitutes as one point each (each point earned is a 25% full pay reduction) resulting in a possible maximum of 75% full pay deduction for missing all three (RSD, RLD, and RDD). However, in the event the missed RDD was exclusively caused by APPF, in lieu of the 25% full pay reduction for missing the RDD provided above, the reduction for missing the RDD will be applied in the following manner:

Cargo delivered one day beyond the RDD - the contractor’s rate will be reduced by AFN 3,190.00 per invoiced escorted mission unit. This reduction will be applied before any percentage reductions.

Cargo delivered two or more days beyond the RDD – the contractor’s rate will be reduced by AFN 6,380.00 per escorted mission unit. This reduction will be applied before any percentage reductions.

3 In the event the contractor missed the RDD for a combination of reasons, of which one includes APPF, the AFN 3,190.00 or AFN 6,380.00 stated above no longer applies and the contractor shall receive a one point reduction (25%) for missing the RDD. It is the contractor’s responsibility to prove to the Government’s satisfaction that delays were caused solely by APPF and that delay was directly related to missing the RDD. If the contractor is unable to clearly demonstrate with adequate documentation that APPF was solely at fault for missing the RDD, a one point reduction (25% of the full pay) applies for missing the RDD.

For example: Missing RSD, but meeting RLD and RDD equals 1 point. Missing RSD and RDD (not exclusively caused by APPF), but meeting RLD equals 2 points or a 50% full pay reduction).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Placeway Construction Corporation v. The United States
920 F.2d 903 (Federal Circuit, 1990)
Dj Manufacturing Corporation v. United States
86 F.3d 1130 (Federal Circuit, 1996)
K-Con Building Systems, Inc. v. United States
778 F.3d 1000 (Federal Circuit, 2015)
Kellogg Brown & Root Services, Inc. v. Murphy
823 F.3d 622 (Federal Circuit, 2016)
Electric Boat Corporation v. Secretary of the Navy
958 F.3d 1372 (Federal Circuit, 2020)

Cite This Page — Counsel Stack

Bluebook (online)
Red Bobtail Transportation, Counsel Stack Legal Research, https://law.counselstack.com/opinion/red-bobtail-transportation-asbca-2024.