ASFA International Construction Industry and Trade, Inc.

CourtArmed Services Board of Contract Appeals
DecidedSeptember 2, 2014
DocketASBCA No. 57880
StatusPublished

This text of ASFA International Construction Industry and Trade, Inc. (ASFA International Construction Industry and Trade, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ASFA International Construction Industry and Trade, Inc., (asbca 2014).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) ASF A International Construction Industry ) ASBCA No. 57880 and Trade, Inc. ) ) Under Contract No. FA5685-05-C-0004 )

APPEARANCE FOR THE APPELLANT: D. Lee Toedter, Esq. Attorney at Law & Contract Consultant Orange Beach, AL

APPEARANCES FOR THE GOVERNMENT: Col Robert J. Preston II, USAF Acting Air Force Chief Trial Attorney W. Michael Rose, Esq. Senior Trial Attorney Gregory A. Harding, Esq. Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE MELNICK ON BOARD JURISDICTION AND APPELLANT'S MOTION FOR SUMMARY JUDGMENT

This appeal arises from ASF A International Construction Industry and Trade, Inc.'s (ASFA's or appellant's) timely appeal of a contracting officer's (CO's) final decision (COFD) assessing liquidated damages for late completion of the construction of three environmental facilities at Incirlik Air Base, a Turkish Air Force installation, in Adana, Turkey. ASF A now moves for summary judgment asserting that the government improperly assessed liquidated damages because the government waived the scheduled completion dates for each facility. The Board raised the issue of its jurisdiction, sua sponte.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

1. The 39th Air Base Wing of the Department of the Air Force (Air Force or government) awarded Contract No. FA5685-05-C-0004 (contract) to ASFA 1 on 11 May 2005 to complete construction of three partially constructed environmental facilities - a hazardous materials storage (HAZMAT) facility, a hazardous waste

1 The contract was originally awarded to ASF A Insaat Pazarlama (1st R4, tabs 4, 6); however, by novation under Modification No. A00002, the contractor's name was changed to ASFA International Construction Industry & Trade (1st R4, tab 6).

f storage facility (storage), and a pesticide management facility (pesticide)- at Incirlik Air Base in Adana, Turkey (1st R4, 2 tab 4 at 2-5, 15-19 of 31 3). Contract line item number (CLIN) 0001 was for the construction of the pesticide facility, CLIN 0002 was for the construction of the storage facility, and CLIN 0003 was for the construction of the HAZMAT facility (1st R4, tab 4 at 4-5of31).

2. The contract included the following pertinent Federal Acquisition Regulation (FAR) clauses by reference: 52.233-1, DISPUTES (JUL 2002); 52.232-5, PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (SEPT 2002); and 52.249-10, DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984) (1st R4, tab 4 at 12-13 of 31 ). The contract also included the following pertinent FAR clauses in full text: 52.211-10, COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984); and 52.211-12, LIQUIDATED DAMAGES -CONSTRUCTION (SEPT 2000) (1st R4, tab 4 at 13-14 of 31 ).

3. FAR clause 52.232-5, PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (SEPT 2002) provides the following, in part:

(b) Progress payments. The Government shall make progress payments monthly as the work proceeds, or at more frequent intervals as determined by the Contracting Officer, on estimates of work accomplished which meets the standards of quality established under the contract, as approved by the Contracting Officer.

4. Under contract clause FAR 52.211-10, COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984), the storage facility was to be completed no later than 131 calendar days from the date of the notice to proceed (NTP); the pesticide facility was to be completed no later than 152 calendar days from the date of the NTP;

2 The government submitted its Rule 4 files in six separate hard copy submittals. The first submittal was for ASBCA No. 57773, which is ASFA's related appeal. The second submittal was for this appeal. ASBCA No. 57773 and this appeal were consolidated (ASBCA No. 57880, Bd. notice of docketing

2 and the HAZMAT facility was to be completed no later than 218 calendar days from the date of the NTP (1st R4, tab 4 at 13-14 of 31; gov't opp'n at 11, ~ 15; app. reply at 7,~15).

5. The Liquidated Damages clause states the following, in part:

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $276.87 for the first day and $255. 72 for each calendar day of delay until the work is completed or accepted. The above amounts will be assessed separately for each project in which the work is delayed until the work is completed or accepted (i.e., CLIN 0001, CLIN 0002, CLIN 0003).

(1st R4, tab 4 at 14 of 31)

6. By memorandum dated 28 June 2005, the government issued a NTP to ASF A to begin performance under the contract stating the following, in part:

1. Pursuant to the terms and conditions of Contract Number F A5685-05-C-0004, you are hereby notified to proceed with the work. Performance shall commence within 10 calendar days after receipt of this notice. This is your Notice to Proceed to start actual performance on the contract. Entire work required by the contract shall be completed not later than 218 calendar days after receipt of this Notice to Proceed.

ASFA acknowledged receipt of the NTP on the same day. (1st R4, tab 14)

7. After issuance of the NTP, the contract's scheduled completion dates for the three facilities were the following:

3 Facility Contract Completion Date Pesticide 27 November 2005 4 Storage 6 November 2005 HAZMAT 1 February 2006

(Gov't opp'n at 11, ~ 15; app. reply at 7, ~ 15)

8. ASFA failed to complete construction of the storage and pesticide facilities by the contract completion dates (gov't opp'n at 11, ~ 16; app. reply at 7, ~ 16). The storage facility was 12 percent complete by the contract completion date. The pesticide facility was 21 percent complete by the contract completion date. (Gov't opp'n at 15-16, ~~ 30, 31; app. reply at 11, ~~ 30, 31)

9. By email dated 9 March 2006, CO Cummins, following up on an earlier meeting between the parties, stated that "it is at the [CO's] discretion whether or not to assess liquidated damages. At this time, I have not made a CO decision whether to assess or not assess liquidated damages .... " (Gov't opp'n, CO Cummins decl., attach. 1 at 1 of 10) In addition, CO Cummins also attached a spreadsheet for informational purposes "so [ASFA is] fully aware of the liquidated damages (LD) figures I have calculated for each of the above projects at this time as well as my methodology for arriving at these LD figures" (id.). The spreadsheet purported to project liquidated damages through 31 May 2006 for each facility (id. at 3-9of10).

10. CO Cummins' 9 March 2006 email also requested letters from ASFA communicating the planned end dates for each facility, the number of additional days requested to complete construction for each facility, and justification for the requested additional days (gov't opp 'n, CO Cummins decl., attach. 1 at 3-9 of 10).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Scott v. Harris
550 U.S. 372 (Supreme Court, 2007)
M. Maropakis Carpentry, Inc. v. United States
609 F.3d 1323 (Federal Circuit, 2010)
Arctic Slope Native Association, Ltd. v. Sebelius
583 F.3d 785 (Federal Circuit, 2009)
Jewell M. Hart v. The United States
910 F.2d 815 (Federal Circuit, 1990)
Dj Manufacturing Corporation v. United States
86 F.3d 1130 (Federal Circuit, 1996)
Am-Pro Protective Agency, Inc. v. United States
281 F.3d 1234 (Federal Circuit, 2002)
Olson Plumbing & Heating Co. v. United States
602 F.2d 950 (Court of Claims, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
ASFA International Construction Industry and Trade, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/asfa-international-construction-industry-and-trade-asbca-2014.