Am-Pro Protective Agency, Inc. v. United States

281 F.3d 1234, 51 Fed. Cl. 1234, 2002 U.S. App. LEXIS 3047, 2002 WL 272719
CourtCourt of Appeals for the Federal Circuit
DecidedFebruary 26, 2002
Docket01-5077
StatusPublished
Cited by217 cases

This text of 281 F.3d 1234 (Am-Pro Protective Agency, Inc. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Am-Pro Protective Agency, Inc. v. United States, 281 F.3d 1234, 51 Fed. Cl. 1234, 2002 U.S. App. LEXIS 3047, 2002 WL 272719 (Fed. Cir. 2002).

Opinion

MICHEL, Circuit Judge.

Plaintiff-Appellant Am-Pro Protective Agency, Inc. (“Am-Pro”) appeals from a judgment of the United States Court of Federal Claims dismissing, as untimely, the contract action that Am-Pro brought against the government and holding, in the alternative, that the government was entitled to summary judgment based on a previously executed release. See Am-Pro Protective Agency v. United States, No. 98-940C, slip op. (Feb. 2, 2001). At the same time, the trial court rejected Am-Pro’s assertion that it had executed this release under duress, meaning (according to Am-Pro) that neither the release nor the applicable limitations period barred its contract claim.

Because the only evidence Am-Pro relies on in opposition to summary judgment — an uncorroborated affidavit executed six years after the government’s alleged wrongdoing occurred — cannot create a genuine issue and meet the high evidentiary burden of proof needed to overcome the presumption that government officials act properly and in good faith, we reject Am-Pro’s argument that it was entitled to a trial. We therefore affirm the grant of summary judgment in favor of the government. Accordingly, we need not review the dismissal under RCFC 12(b)(1).

Background

On June 21, 1989, Am-Pro was awarded Contract No. 1038 963119 to provide guard services for the Department of State’s facilities in the Washington, DC, area and at the United States Mission to the United Nations in New York City, New York. This dispute first arose in 1991, when Am-Pro suggested that the government owed it additional compensation for hours it was paying its employees to work during “breaker hours.” “Breaker hours,” as defined by Am-Pro, were the hours for lunch breaks and the two fifteen-minute breaks that Am-Pro was required to provide each guard under the contract. During these times, Am-Pro had to either have another guard fill in for the guard on break or else have that guard work through his break. Am-Pro asserted that it had not been compensated either for the cost of paying another employee to stand guard while the employee assigned to a post' was taking one of these required breaks or for the extra cost of paying overtime to these guards who worked through their breaks.

On January 9, 1992, Am-Pro representatives and counsel met to discuss the “breaker issue” with the Contracting Officer (“CO”) and other Department of State representatives. At this meeting, the CO notified Am-Pro that she would have to consider the pending breaker issue when deciding whether to exercise options on the contract. According to Am-Pro, however, the CO framed this consideration as a threat, allegedly stating that if Am-Pro chose to file a formal claim, she would promptly disapprove it and that, if Am-Pro thereafter appealed her decision, the CO would cancel and re-solicit the existing contract. See Brown Affidavit at 119 (May 20,1998).

*1237 By letter to Am-Pro dated April 8, 1992, the CO reiterated her concern about whether Am-Pro’s price for the contract was known, given its claim for additional compensation under the contract. The CO maintained that the intent of the parties at the time of contract formation was that Am-Pro would provide “breakers” within the contract price for the first 18 months of performance, and that “the principle that breakers are not separately compensable was firmly established by contract performance.” Consequently, the CO indicated that she would have to consider the government’s future potential liability when deciding whether to exercise future options on the contract.

On May 29, 1992, Am-Pro submitted a certified claim to the CO seeking recovery of $2,593,389 for breaker hours from the date of the contract’s inception to April 15, 1992. In September 1992, the CO denied this claim in its entirety, finding that the contract was a fixed-price contract and that all the costs of contract performance were therefore included in Am-Pro’s original bid price. The relevant contract terms stated “This is a Fixed Price and Time and Materials Contract.... The initial 120 day period of the contract will be a Fixed Price arrangement. After the initial 120 day period, the contract will become Time and Materials.” Am-Pro nevertheless asserted that the contract was a time and materials contract. The CO further explained that “[i]n actual performance and in accord with section B of the contract, the contract is firm, fixed-price with a composite billing rate that utilizes time and materials terms to ensure performance and payment.” The CO also found that “Am-Pro’s cost proposal eontain[ed] several elements which provide for compensation for providing supervisor and guard breaks.” Am-Pro did not appeal the CO’s decision.

The parties met again on November 3, 1992. Am-Pro alleges that, at this meeting, the CO “repeated her threat of canceling the Contract if Am-Pro continued to have its Contract rights protected by appealing her interpretation of the Contract.” Brown Decl. at 1F12. Further, Am-Pro alleges, the CO threatened to “adversely impact [its] ability to contract with other agencies of government....” Id. The CO denies the accuracy of these three allegations. See Cain Deck at f 10.

In a letter dated November 5, 1992, Am-Pro notified the CO that it had asked its attorneys to prepare a letter expressing “its willingness to terminate all claims past and present” regarding the breakers’ issue. By letter dated November 10, 1992, Am-Pro confirmed that it had “withdrawn” the claim that was subject to the September 1, 1992, final decision of the CO. And it agreed that it would not appeal the CO’s final decision or submit any future claim for costs attributable to the “breaker” issue, thereby effectively releasing the government from any future claims for breaker hours. Under this release, the CO agreed that Am-Pro would not be excluded from any other competition for further Department of State security services contracts. 1 Nothing in the letters by Am-Pro (and presumably, its attorneys) alludes to the threats that allegedly occurred in the January 1992 and November 1992 meetings with the government.

At the end of the contract option period, the Department of State entered into another contract with Am-Pro for the provision of guard services through 1997. In *1238 May 1998, nearly six years after the government allegedly threatened Am-Pro with cancellation, Am-Pro submitted a certified claim for $3,832,695.22. Attached to this claim was Am-Pro’s original May 1992 claim for $2,593,389. Alleging that the letters dated November 5, 1992, and November 10, 1992, were written under duress and that the release was therefore invalid, Am-Pro sought compensation for the cost of the breaker hours allegedly incurred from 1989 to 1994.

Shortly thereafter, a new CO was assigned. On July 20, 1998, the new CO notified Am-Pro that he refused to consider its claim because Am-Pro had indeed released that claim in the November 10, 1992, letter and also because the claim was barred by Am-Pro’s failure to timely appeal the first CO’s decision. On December 29, 1998, Am-Pro sued the government in the Court of Federal Claims, challenging the new CO’s decision and seeking payment in the amount of $3,832,695.22.

The Court of Federal Claims dismissed Am-Pro’s complaint for lack of jurisdiction.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Keys v. McDonough
Federal Circuit, 2023
Lockheed Martin Aeronautics Company
Armed Services Board of Contract Appeals, 2022
Exceed Resources, Inc.
Armed Services Board of Contract Appeals, 2020
U.S. Coating Specialties & Supplies, LLC
Armed Services Board of Contract Appeals, 2020
Aerospace Facilities Group, Inc.
Armed Services Board of Contract Appeals, 2020
Fields v. United States
Federal Claims, 2020
Advanced Powder Solutions, Inc.
Armed Services Board of Contract Appeals, 2019
Peraton, Inc v. United States
Federal Claims, 2019
Lulus Ostrich Ranch
Armed Services Board of Contract Appeals, 2019
Nexagen Networks, Inc.
Armed Services Board of Contract Appeals, 2019

Cite This Page — Counsel Stack

Bluebook (online)
281 F.3d 1234, 51 Fed. Cl. 1234, 2002 U.S. App. LEXIS 3047, 2002 WL 272719, Counsel Stack Legal Research, https://law.counselstack.com/opinion/am-pro-protective-agency-inc-v-united-states-cafc-2002.