Johnson, Drake & Piper, Inc. v. United States

531 F.2d 1037, 22 Cont. Cas. Fed. 80,141, 209 Ct. Cl. 313, 1976 U.S. Ct. Cl. LEXIS 77
CourtUnited States Court of Claims
DecidedMarch 17, 1976
DocketNo. 121-73
StatusPublished
Cited by74 cases

This text of 531 F.2d 1037 (Johnson, Drake & Piper, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Johnson, Drake & Piper, Inc. v. United States, 531 F.2d 1037, 22 Cont. Cas. Fed. 80,141, 209 Ct. Cl. 313, 1976 U.S. Ct. Cl. LEXIS 77 (cc 1976).

Opinion

Per Curiam :

This case comes before the court on plaintiff’s request, filed June 4, 1975, for review by the court of the recommended decision, filed March 4, 1975, by Trial Judge David Schwartz, pursuant to Rule 166 (c) on plaintiff’s motion and defendant’s cross-motion for summary judgment, having been submitted on the briefs and oral argument of counsel. Upon consideration thereof, since the court agrees with the trial judge’s recommended decision (with the addition of footnote No. 8 by the court), as hereinafter set forth, it hereby affirms and adopts the same, as modified, as the basis for its judgment in this case. Therefore, it is concluded that plaintiff is not entitled to recover, plaintiff’s motion for summary judgment is denied, defendant’s cross-motion for summary judgment is granted and plaintiff’s petition is dismissed.

OPINION OE TRIAL JUDGE

Schwartz, Trial Judge;

Plaintiff sues to reverse a decision of the Armed Services Board of Contract Appeals in which claims under a contract were held barred by a written release. Cross-motions for summary judgment present issues, to be decided in accordance with the standards of the Wunderlich Act (41 U.S.C. §§321, 322 (1970)), of the validity of the release as against a plea of duress and of the applicability of the release to the claims presented. By agreement these were the only issues below and they are the only issues to be decided here.

Plaintiff, a joint venture composed of three construction firms, Johnson, Dirake & Piper, Inc., Bums & Roe Western [316]*316Hemisphere Corporation and Merritt-Chapman & Scott Corporation, held a contract dated May 7, 1962 for 177 items of repair and renovation, at a cost of $1.9 million, of some 300 buildings at Thule Air Base in Greenland. Shortly before December 31, 1962, the contract completion date of all but three of the contract items, the parties negotiated a supplementary agreement which was added to the contract as Modification No. 6, containing among other things an extension of time for several of the contract items and a release of claims existing as of December 31,1962.

The work was completed on the following March 31. Several months later, plaintiff presented to the contracting-officer 29 claims for extras and changes, of which 12 were settled and incorporated into the contract by supplementary agreements (also “Modifications”) and 17, making claim for $1.5 million, were denied as barred by the release. On appeal, the Armed Services Board of Contract Appeals, one member dissenting in part, held 16 of the 17 claims barred by the release. The 17th claim, held unaffected by the release, was remanded for consideration on the merits, and is not involved in the present proceeding.

The plaintiff’s contentions to be discussed herein are that the release is invalid for having been obtained by duress, and that if valid, it should be construed to apply only to types of claims other than those presented and in any event not to 11 of the 16 claims in suit, which are said to have arisen in 1963, after the effective date of the release. Additional contentions, not requiring discussion, are that the release is void for illegality as an encroachment on the remedy provided by the Disputes clause and that an exception in the release should be construed as excepting all claims.

It is here held that the Board correctly decided all the issues against the plaintiff. Because the Board’s decision is found to be correct in all respects, there is no need to distinguish between the varying degrees of finality which under the Wunderlich Act, supra, are to be accorded the Board’s decisions of issues of fact and of law.

The setting for the entire case — release and claims and contentions — is the long Arctic winter and the correspondingly short season in which construction work can be done outdoors. Progress of the work according to schedule was of [317]*317special importance in the contract, for the early onset of cold weather in Greenland would prevent outside work after the third week in ‘September. Work began in late May 1962. There is no doubt that plaintiff suffered delays of various kinds, although responsibility for the delays has not been fixed. From July to November the plaintiff complained of delays said to be the Government’s fault or otherwise excusable, and the Government, in no wise agreeing, complained of plaintiff’s failure to keep to schedule.

As late as October 19 plaintiff maintained that despite the delays it was on or close to schedule. On November 20, however, acknowledging that the completion date of December 31 could not be met, and giving a variety of excuses for the delay, plaintiff formally requested an extension of time to February 28, 1963 for some contract items and to August 30, 1963 for others. Upon this, the contracting officer, the division engineer of the Corps of Engineers located in New York City, paid a three-day inspection visit to the site in Greenland and there became convinced that all the excuses were invalid and that plaintiff should be terminated for default. On his return, a meeting was convened on December 10, 1963 of representatives of plaintiff and of the Corps of Engineers at which the contracting officer stated his view that a default termination was warranted and invited plaintiff to present its reasons why it should not be terminated for default. Among those present for the plaintiff were the project manager, five vice-presidents of the three participating firms and two lawyers. Present for the Government were the contracting officer, several branch chiefs and a lawyer. The alleged duress is said to have taken place at this meeting.

The meeting was opened by the contracting officer who stated his above-mentioned views, and plaintiff’s representatives then stated in detail the reasons why they felt the delays were excusable and they should receive the extensions of time desired. After a general discussion, the contracting officer in a detailed statement, during whidh he referred to documents, rejected the reasons which had been offered by plaintiff and adhered to his decision to terminate the contract for default.

Thereupon, in the course of the discussion, the plaintiff’s representatives expressed a willingness to do whatever was [318]*318necessary to be allowed to complete the work and not be terminated for default. The contracting officer changed his mind because he felt that plaintiffs were “good guys” whose companies had good reputations and should not be required to suffer the harm to their reputation from a termination for default. He would give the desired extension on conditions. The conditions were that plaintiff subcontract certain of the items to another contractor; that plaintiff undertake not to bid on the work at Thule in the following year, 1963; that certain items be deleted from the contract; and, finally, that plaintiff sign a general release.

The vice-presidents and the others representing plaintiff discussed the matter among themselves and agreed that they would accept the combination of extensions and conditions. Their reason was their companies had performed 160 million dollars worth of Government contracts and they could not accept the harm to their reputation and to the future business relations with the Government which might follow from a termination for default. The parties thereupon worked out a written, agreement, incorporated into the contract as Modification No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

A4 Construction Company, Inc
Armed Services Board of Contract Appeals, 2025
Kandahar Mahali Transit & Forwarding LTD.
Armed Services Board of Contract Appeals, 2024
Oxy USA, Inc. v. United States
Federal Claims, 2022
Doe v. United States
Federal Claims, 2021
Sand Point Services, LLC
Armed Services Board of Contract Appeals, 2019
Ingham Regional Medical Center v. United States
126 Fed. Cl. 1 (Federal Claims, 2016)
Two Shields v. United States
119 Fed. Cl. 762 (Federal Claims, 2015)
Salter v. United States
119 Fed. Cl. 359 (Federal Claims, 2014)
Pew Forest Products v. United States
105 Fed. Cl. 59 (Federal Claims, 2012)
Metcalf Construction Co. v. United States
102 Fed. Cl. 334 (Federal Claims, 2011)
Raytheon Co. v. United States
96 Fed. Cl. 549 (Federal Claims, 2011)
Robinson v. United States
95 Fed. Cl. 480 (Federal Claims, 2011)
Villacres v. Abm Industries Inc.
189 Cal. App. 4th 562 (California Court of Appeal, 2010)
IMS Engineers-Architects, P.C. v. United States
92 Fed. Cl. 52 (Federal Claims, 2010)
Aboo v. United States
86 Fed. Cl. 618 (Federal Claims, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
531 F.2d 1037, 22 Cont. Cas. Fed. 80,141, 209 Ct. Cl. 313, 1976 U.S. Ct. Cl. LEXIS 77, Counsel Stack Legal Research, https://law.counselstack.com/opinion/johnson-drake-piper-inc-v-united-states-cc-1976.