John Arborio, Inc. v. United States

76 F. Supp. 113, 110 Ct. Cl. 432, 1948 U.S. Ct. Cl. LEXIS 34
CourtUnited States Court of Claims
DecidedMarch 1, 1948
DocketNo. 46868
StatusPublished
Cited by3 cases

This text of 76 F. Supp. 113 (John Arborio, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
John Arborio, Inc. v. United States, 76 F. Supp. 113, 110 Ct. Cl. 432, 1948 U.S. Ct. Cl. LEXIS 34 (cc 1948).

Opinions

Howell, Judge,

delivered the opinion of the court:

Plaintiff brings this suit to recover for alleged underpayment on two items of work involved in its performance of a contract for the construction of Stewart Field Auxiliary Airport, site No. 1, Montgomery, Orange County, New York. It is sought to recover the difference between the ditching price of $1.20 per cubic yard and the borrow or common excavation price of 45 cents or 35 cents per cubic yard for some 70,605 cubic yards of material falling between the ditch lines of the east ditch projected from final field grade upward to original field grade.

Plaintiff also sues to recover the difference between $3.40 per cubic yard and $1.50 per cubic yard for some 85,827 cubic yards of ledge rock removed from the contract by Change Order No. 1 and Supplemental Agreement No. 1, and later restored in the contract by Supplemental Agreement No. 2 at a price of $1.50 per cubic yard.

There are, therefore, two principal questions involved— the first in connection with the ditch excavation which can be stated as follows: Should the disputed yardage be paid for as borrow or common excavation under a reasonable interpretation of the contract provisions, specifications and revised drawings made in the light of the manner in which the work was performed. The second is in connection with the rock excavation and involves the question as to whether Supplemental Agreement No. 2 or any other agreement of the contract was entered into by the plaintiff under duress and whether the price of $1.50 per cubic yard agreed upon in Supplemental Agreement No. 2 was correctly applied by the contracting officer to the total yardage of 85,827 cubic yards of ledge rock excavated.

[447]*447The ditch excavation yardage in controversy was in connection with the east ditch. This ditch was not dug at the location shown on the original contract drawings but was redesigned to parallel the road running east of the airport after the intervening ground had been acquired. This intervening ground became a source of borrow material for raising lower parts of the airport.

Payment for the so-called north ditch and for the French drain was made from original grade to the invert of the ditches. Since the north ditch, when dug, was outside of the field and the French drain, when dug, was in an area to be later raised, there was no other possible method of payment and such action constituted no precedent for payment on the east ditch which was later designed in an area to be reduced in grade and not shown on any drawings exhibited in this case.

Proof does not show whether the east ditch was dug before or after the lowering of the grade in that area. It does show, however, that the contracting officer did not consider it necessary to construct this ditch prior to grading, nor direct the contractor so to do. If the east ditch was constructed in advance of the grading, it was done by plaintiff’s choice. Moreover, the portion of the ditch above finished grade was of no benefit to the Government and served merely the purpose of temporary drainage during construction.

Specification 3-03c is as follows:

Excavation, New Drainage Ditches shall be measured by the cubic yard in place from surveys made before and after excavation for the ditches. The contract price per cubic yard for ditch excavation shall cover the cost of the materials, labor and equipment and doing all work necessary to excavate the new ditches, including the proper disposal of all materials as specified or directed by the Contracting Officer.

Specification 5-02a provided as follows:

General. — Embankment may be placed on frozen ground, if approved by the Contracting Officer. During, or after, thaws, there shall be additional rolling so that a compact layer is formed in the embankment. Prior to placing embankments, the Contractor shall excavate and maintain during his filling operation such [448]*448temporary ditches and drains as are necessary to maintain the embankment and contiguous areas in a reasonably dry condition. No special payment for such work will be made. If desired by the Contractor, he may at his option construct the ditches required under Item 3 of the specifications, to serve the above purpose. In this event, however, payment will be made only after completion of the embankments and after ditches are cleaned and graded in accordance with provisions of Section III of these specifications.

In view of these provisions and the manner in which the , work was performed, a decision was necessary regarding proper payment for the yardage between the ditch lines of the east ditch above finished grade. The authority as well as the responsibility for making such decision are found in Specification 1-35 as follows:

Interpretation of specifications. — The Contracting Officer shall decide all questions which may arise as to the performance, quantity, quality, acceptability fitness, and rate of progress of the several kinds of work to be done or materials to be furnished under this contract. He shall decide all questions which may arise as to the interpretation of the specifications and of drawings used and as to the fulfillment of this contract on the part of the contractor, and as to defects in the contractor’s work.

It was the duty of the contracting officer to approve payments to the plaintiff based upon estimates made and approved by him. Article 16 (a) of the contract is as follows:

Article 16. Payments to contractors. — (a) Unless otherwise provided in the specifications, partial payments will be made as the work progresses at the end of each calendar month, or as soon thereafter as practicable, on estimates made and approved by the contracting officer. In preparing estimates the material delivered on the site and preparatory work done may be taken into consideration.

Therefore, in order to make the first partial payment for work already performed, it became necessary for- the contracting officer to exercise the discretion conferred upon him by these sections and decide how the excavation for ditches and trenches should be measured. Accordingly, on July 17, 1942, Colonel Charles D. Eeidpath, who was the contracting officer from June 17 to October 30, 1942, made his decision [449]*449and issued instructions relative to the measurement of the excavation for ditches and trenches, being Item 4 of the contract, as follows:

Excavation — at price of $1.20 per cubic yard — will be considered as the volume below finished grade of field where ditch occurs. All excavation above that line will be paid for at unit price of common excavation.

Colonel Eeidpath was the first contracting officer and was present not only when the work was begun but most of the time when the work was actually being performed. His view as to the classification of ditch yardage from the east ditch was based upon his on-the-job personal observations as well as his interpretation of the contract specifications and revised drawings made in the light of the manner in which the work was performed. That this decision was a fair and reasonable interpretation is substantiated by the fact that it was later concurred in by Major R. L. Donnelly, a succeeding contracting officer, by the Board of Contract Appeals, War Department, by the authorized representative of the Secretary of War, as well as by the Commissioner of this Court.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Louisiana-Pacific Corp. v. United States
656 F.2d 650 (Court of Claims, 1981)
Johnson, Drake & Piper, Inc. v. United States
531 F.2d 1037 (Court of Claims, 1976)
Loral Corporation v. The United States
434 F.2d 1328 (Court of Claims, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
76 F. Supp. 113, 110 Ct. Cl. 432, 1948 U.S. Ct. Cl. LEXIS 34, Counsel Stack Legal Research, https://law.counselstack.com/opinion/john-arborio-inc-v-united-states-cc-1948.