Loral Corporation v. The United States

434 F.2d 1328, 193 Ct. Cl. 473, 1970 U.S. Ct. Cl. LEXIS 69
CourtUnited States Court of Claims
DecidedDecember 11, 1970
Docket253-69
StatusPublished
Cited by13 cases

This text of 434 F.2d 1328 (Loral Corporation v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Loral Corporation v. The United States, 434 F.2d 1328, 193 Ct. Cl. 473, 1970 U.S. Ct. Cl. LEXIS 69 (cc 1970).

Opinion

*1329 ON PLAINTIFF’S AND DEFENDANT’S MOTIONS FOR SUMMARY JUDGMENT

LARAMORE, Judge.

This case represents the third attempt by plaintiff to secure compensation in addition to that provided for under certain contracts with the defendant. The first case, Loral Electronics Corp. v. United States, 387 F.2d 975, 181 Ct.Cl. 822 (1967), hereafter referred to as Loral I, presents most of the facts upon which this claim arises, with certain exceptions to be indicated hereafter. In that case, Loral Electronics Corp. (now known as Loral Corporation) was successful in its attempt to overturn a decision by the Armed Services Board of Contract Appeals (Loral Electronics Corp., 1964 BCA If 4439) and in so doing it was found by this court that plaintiff was entitled to reimbursement from the defendant, under certain cost-plus-fixed-fee contracts, for rental payments for the use of a building in which the contracts in question were being performed. Loral I, swpra.

Following the Loral I decision, plaintiff sought to amend and supplement its pleadings in that ease so as to include more than the five Navy contracts specifically referred to in Loral I. The court, per curiam, denied plaintiff the right to supplement the pleadings in Loral I and the reasons for said denial are found at Loral Electronics Corp. v. United States, 409 F.2d 578, 187 Ct.Cl. 499 (1969), hereafter referred to as Loral II.

Briefly stated, the court found in Loral II that the Loral I decision related only to the five contracts that were specifically referred to in the petition in this court which were the same five that were before the ASBCA. The court went on to point out that “ * * * plaintiff could have brought new and independent suits on these other contracts to which it now points.” (Loral II, supra, 409 F.2d at 580-581, 187 Ct.Cl. at 503.) Pursuant to the suggestion noted above, plaintiff now brings this action to recover on numerous contracts entered into with the government between 1962, when Loral I was started, and 1967, the date Loral I was decided. These contracts differ from those to which the court directed its opinion in Loral I in that the contracts upon which this case is built are negotiated fixed-price contracts. Another difference of minor significance is that in Loral I the contracts involved were all performed in the Bronx section of New York City at 825 Bronx River Avenue, while in this case the numerous contracts were performed not only at the aforementioned location, but also at 1440 Story Avenue, which is also in the Bronx. The facts of this case further show that the plaintiff occupied both buildings under leases which included, in both cases, options to purchase the premises at the end of the lease term.

These options, which were discussed in Loral I, caused the defendant to treat plaintiff as the equitable owner of both buildings and as a consequence defendant refused to accept plaintiff’s rental expense as an item of reimbursable cost in the cost-plus-fixed-fee contracts. In Loral I, this court decided that, as applied to the five cost-plus contracts, the government’s position was incorrect and, therefore, rental expense, as opposed to “cost of ownership” should be allowed. (See, Loral I, 387 F.2d at 977, 181 Ct.Cl. at 826, (1967).)

However, because this case presents the question under significantly different facts, we cannot find that the government must reimburse the plaintiff for rental expenses incurred in the performance of the fixed-price contracts here in question. This decision is based on the initial premise that this court will decide each case as it is presented and only within the confines of the facts as developed. Therefore, we will not pass on issues that are not presented by the facts of the case. This position was aptly stated in Loral II, 409 F.2d at 580, 187 Ct. Cl. at 502-503:

In the opinion [Loral 7] we referred expressly to the five Navy cost-plus contracts which we were considering, *1330 pointing out that the court was “concerned in the present case” with those specific agreements. 181 Ct.Cl. at 824, 825, 829, 387 F.2d at 976, 979. It is indisputable that we adjudicated only those five contracts (though of course our opinion would be a precedent for administrative or judicial resolution of similar issues under similar agreements). Without amendment, the petition will not support any judgment relating to contracts other than those five, [footnotes omitted.]

Therefore, in this case we need not take Loral 7 as a precedent for the holding here because this case does not present “similar issues under similar agreements.” This case must stand or fall upon its own merits and what we decided in Loral I in relation to the five cost-plus contracts has no application to the fixed-price contracts here in question.

The plain and simple reason this court does not feel it is bound by Loral I is that the contracts in issue in this case present a wholly different situation than the one considered in Loral 7. In Loral I, the contracts were the type that are subject to negotiation throughout their existence (see, ASPR § 3.405-5, and Loral I, 387 F.2d at 976, 181 Ct.Cl. at 824) and since an impasse was reached in negotiations for allowable costs the parties could utilize the “Disputes” clause to resolve their differences (see, Loral I, supra). However, in this case the type of contracts in question are firm fixed-price contracts and once the price was agreed upon, that price remains fixed and it is not subject to further negotiation, unless otherwise provided in the contract. ASPR § 3.404-1 and § 3.404-2. In this case, plaintiff did not “otherwise provide” for adjustment of the fixed price, nor did the plaintiff preserve any objections to the Navy auditors’ characterization of the building overhead. Therefore, at the risk of being repetitious, we must again point out that the factual differences in this case from Loral I as to the contracts involved necessitate the conclusion that plaintiff cannot rely on our decision in Loral I to support his recovery here.

Furthermore, even assuming that the Navy auditors disallowed the rental expense when plaintiff was in the preparation of the bids on the firm fixed-price contracts, the government submits several affidavits by contracting officers indicating that in the final stages of each contract plaintiff never discussed its objection to the characterization of the building overhead. This is significant to the court in that it points out that plaintiff did not endeavor to preserve its objections for final determination in relation to the fixed-price contracts.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Advance Bank v. United States
52 Fed. Cl. 286 (Federal Claims, 2002)
Teledyne, Inc. v. United States
50 Fed. Cl. 155 (Federal Claims, 2001)
Louisiana-Pacific Corp. v. United States
656 F.2d 650 (Court of Claims, 1981)
Johnson, Drake & Piper, Inc. v. United States
531 F.2d 1037 (Court of Claims, 1976)
Hellermann v. Romney
409 F. Supp. 352 (E.D. Wisconsin, 1976)
Eriez Magnetics Corp. v. United States
209 Ct. Cl. 673 (Court of Claims, 1976)
Highway Products, Inc. v. United States
530 F.2d 911 (Court of Claims, 1976)
Nelson v. United States
341 F. Supp. 1353 (D. Montana, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
434 F.2d 1328, 193 Ct. Cl. 473, 1970 U.S. Ct. Cl. LEXIS 69, Counsel Stack Legal Research, https://law.counselstack.com/opinion/loral-corporation-v-the-united-states-cc-1970.