Penker Construction Co. v. United States

96 Ct. Cl. 1, 1942 U.S. Ct. Cl. LEXIS 134, 1942 WL 4460
CourtUnited States Court of Claims
DecidedFebruary 2, 1942
DocketNo. 43277
StatusPublished
Cited by14 cases

This text of 96 Ct. Cl. 1 (Penker Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Penker Construction Co. v. United States, 96 Ct. Cl. 1, 1942 U.S. Ct. Cl. LEXIS 134, 1942 WL 4460 (cc 1942).

Opinions

Whitaker, Judge,

delivered the opinion of the court:

The plaintiff sues the defendant for the sum of $259,033.99, setting out 15 causes of action growing out of the execution of a contract between it and the defendant for the erection of 68 buildings, providing 91 officers’ quarters, at Patterson Field, Fairfield, Ohio.

First cause of action

The first cause of action is for an alleged unwarranted deduction of the sum of $6,270.55 on account of a decrease in the amount of excavation which the plaintiff estimated would be necessary.

The plaintiff agreed to erect the buildings for the lump sum of $1,018,300.00, which included the excavation shown. The Government, however, says that it is entitled to deduct the above-mentioned sum from this lump sum price by [35]*35reason, of tbe provision of item XIII of plaintiff’s bid, which provides in part:

Item XIII. “ Unit Prices.”—
The Contractor shall submit “Unit Prices” in the following schedule for all items listed below.
Those “Unit Prices” will be used in making deductions from or additions to the contract amount, provided any deviation from the drawings and specifications decreases or increases the work indicated or required.
“Unit Prices” shall include the furnishing of all labor and material, complete in place, unless otherwise noted herein.
(a) Earth Excavation, One Dollar ($1.00) per cu. yd.
* if! # «Í Jfc

The plaintiff replied that this provision is inapplicable because there had been no deviation from the work indicated or required by the drawings and specifications.

The plans showed the finished grade, but did not show the natural grade, or the elevation of the buildings above this grade, but paragraph S. C. 6, page 7a of the specifications required the contractor to visit the site to determine “the relation of finished grades of the buildings to existing grades and the natural surface of the ground.” The testimony shows that from a visit to the site and from the plans ■a contractor was able to determine the amount of excavation “indicated” by the drawings and specifications.

This contractor did visit the site and examined the plans preparatory to putting in its bid. From this it estimated that a certain amount of excavation would be necessary. But because it was not known just what the elevation of the buildings would be, and because, therefore, it could not determine exactly the amount of excavation that would be necessary, it made its estimate sufficiently high to cover contingencies. Its estimate was based on the amount of excavation “indicated.” The proof does not show there has been any deviation therefrom. This estimate it included in its figures to arrive at the lump sum for doing all the work.

But the defendant suspected that its estimate for doing this work was more than it had actually cost it, and de[36]*36manded its work sheets to determine this fact. When it turned out it had not cost as much as had been estimated, the defendant asserted the right to deduct the excess.

There is no justification for this. The plaintiff’s contract was to do the work called for by the contract for a certain sum, irrespective of cost, and it was defendant’s duty to pay the sum stipulated, irrespective of cost. This sum was subject to decrease or increase only in the event there was a “deviation from the drawings and specifications,” decreasing or increasing the work indicated. Here there was no deviation from'the amóúhPof work indicated. Although 'the natural grade was not shown on the plans, the required visit to the site supplied this data and from the two the amount of excavation indicated could be and was determined. The exact amount that would be necessary could not be determined because the elevation of the buildings had not been fixed, but while the plans and specifications did not show exactly the amount to be “required,” they did “indicate” that amount. The proof shows they indicated the amount necessary within a foot or so, and there is no proof there was any deviation therefrom. There is, therefore, no justification for any deduction from the lump sum bid. That it did not cost plaintiff as much as it had estimated certainly offers no justification for such a deduction.

On this cause of action the plaintiff is entitled to recover, unless the defendant is right in its contention that we have no jurisdiction to render judgment by virtue of the provisions of article 15 of the contract quoted in finding 5, which provides that—

* * * all other disputes concerning questions arising under this contract shall be decided by the contracting officer * * *.

If this provision be given the broad scope contended for by the defendant, this court would have no jurisdiction of any controversy between parties arising out of a contract in any event, save only in a case where the contracting officer’s actions had been arbitrary, capricious, or so grossly erroneous as to imply bad faith. It would leave to the decision of the contracting officer the settlement of all rights of the parties. It would allow him to determine whether [37]*37or not either party had breached the contract in any respect and to determine the amount due the plaintiff thereunder. If the defendant had unreasonably delayed the contractor in the performance of his work and put him to additional expense on account thereof, or had otherwise caused him damage, his right to recover therefor would depend upon the decision of the contracting officer. If this decisison was against him, his only recourse would be an appeal to the head of the department.

We cannot believe that this was the intention of the parties. Especially. can we not believe this when we take into consideration that the person to determine the rights of the parties was the agent of one of the contracting parties. This court in Barlow v. United States, 35 C. Cls. 514, at pages 544-545, said of such a contract:

If the full intent and effect be given to this provision which the defendants now ascribe to it, the contractors might as well have written an agreement on half of a sheet of paper, binding themselves to perform whatever work and furnish whatever material the Chief of the Bureau might require, and accept therefor whatever remuneration _ the Secretary of the Treasury might be pleased to give them.

It is well settled that provisions preventing resort to the courts to settle the rights of the parties are to be strictly construed against excluding this right. This remedy will not be denied unless the language of the contract makes such a conclusion inescapable. Mercantile Trust Co. v. Hensey, 205 U. S. 298; Central Trust Co. v. Louisville, St. Louis & T. R. Co. 70 Fed. 282; Zimmerman v. Marymor, et al. 290 Pa. 299; and other cases cited in 54 A. L. R. 1255. This rule should be applied especially in this case because the contract was drawn by the defendant and it provided that its officer should be the final arbiter, and because the contractor had no option but to take the contract as written, or lose the work. Callahan Construction Co. v. United States, 91 C. Cls. 538, 611.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

American Line Builders, Inc. v. United States
38 Cont. Cas. Fed. 76,406 (Court of Claims, 1992)
Discount Co. v. United States
554 F.2d 435 (Court of Claims, 1977)
Truong Xuan Truc v. United States
22 Cont. Cas. Fed. 80,065 (Court of Claims, 1976)
River Construction Corp. v. United States
159 Ct. Cl. 254 (Court of Claims, 1962)
Oliver-Finnie Company v. United States
279 F.2d 498 (Court of Claims, 1960)
Oliver-Finnie Co. v. United States
150 Ct. Cl. 189 (Court of Claims, 1960)
Binghamton Construction Co. v. United States
107 F. Supp. 712 (Court of Claims, 1952)
Great Lakes Dredge & Dock Co. v. United States
96 F. Supp. 923 (Court of Claims, 1951)
John Arborio, Inc. v. United States
76 F. Supp. 113 (Court of Claims, 1948)
Addison Miller, Inc. v. United States
70 F. Supp. 893 (Court of Claims, 1947)
Union Paving Co. v. United States
107 Ct. Cl. 405 (Court of Claims, 1946)
McShain v. United States
65 F. Supp. 589 (Court of Claims, 1946)
S. J. Groves & Sons Co. v. Warren
135 F.2d 264 (D.C. Circuit, 1943)

Cite This Page — Counsel Stack

Bluebook (online)
96 Ct. Cl. 1, 1942 U.S. Ct. Cl. LEXIS 134, 1942 WL 4460, Counsel Stack Legal Research, https://law.counselstack.com/opinion/penker-construction-co-v-united-states-cc-1942.