Barlow v. United States

35 Ct. Cl. 514, 1900 U.S. Ct. Cl. LEXIS 96, 1900 WL 1476
CourtUnited States Court of Claims
DecidedMay 21, 1900
DocketNo. 20798
StatusPublished
Cited by14 cases

This text of 35 Ct. Cl. 514 (Barlow v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Barlow v. United States, 35 Ct. Cl. 514, 1900 U.S. Ct. Cl. LEXIS 96, 1900 WL 1476 (cc 1900).

Opinion

Nott, Ch. J.,

delivered the opinion of the court:

The contract in this case, bearing date the 29th of October, 1892, provides “ that if at any time it should be found advantageous or necessary to make any change or modification in the aforesaid plans and specifications, such changes or modifications must be agreed upon in writing.” The parties acted under this provision no less than eleven times. There are eleven supplemental contracts, in one of which the trivial sum of $17 is the total consideration.-

The defendants now contend that the claimants can not recover upon some of their causes of action because this provision of the contract was not complied with. It is manifest, however, that neither of the parties to the contract considered the provision as applicable to most of the matters now in issue. The Chief of the Bureau of Yards and Docks certainly did not. He did not seek to make any change or modification in the “aforesaid plans and specifications” which would involve additional expense. On the contrary, he regarded everything that was done under his direction and requirements as an obligation resting' upon the contractors under the original contract. The one party maintained that the contractors were bound by the contract; the other party maintained that they were doing extra work or furnishing better material under requirements which were not contained in the contract.

The contract also provides that “ no omission in the plans or specifications of any detail, object, or provision necessary to carry this contract into full and complete effect, in accordance with the true intent and meaning hereof, shall operate to the disadvantage of the United States, but the same shall be satisfactorily supplied, performed, and observed by the contractors. And all claims for extra compensation by reason of, or for, or on account of, such extra performance are hereby,'in -consideration of the premises, expressly waived.”

To the court it seems plain that this provision applies only to “omissions,” to matters of “detail,” and only to such “omissions,” and “matters of detail” as shall be “necesscury to carry the contract into full and complete effect, in accordance with the true intent and meaning thereof.” It cannot be held, in the opinion of the court, that the things which [544]*544the Chief of the Bureau compelled the contractors to do were “omissions” on “matters of detail,” or “necessary” to carry the contract into effect. On the contrary, they were clearly changes or additions which the Chief of the Bureau had or had not the right to require within the true intent and meaning of other provisions of the contract.

The contract also pi’o vides “ that if any doubts or disputes arise as to the meaning or requirements of anything in this contract, or if any discrepancy occurs between the aforesaid plans and specifications and this contract, the matter shall be at once inferred for the consideration and decision of the Chief of the Bureau of Yards and Docks, and his decision thereon shall be final, subject, however, to the right of the contractors to appeal from such decision to the Secretary of the Navy, who, in case of such appeal, shall be furnished by the contractors with a full and complete statement of the grounds of their appeal, in writing, and shall thereupon take such action in the premises as, in his judgment, the rights and interests of the respective parties to this contract shall require, and the parties of the first part hereby bind themselves and their heirs and assigns, and their personal and legal representative, to abide by his, the said Secretary’s, decision in the premises.”

But here it must be noted that this fourteenth provision of the contract is grounded upon “doubts and disputes,” which are to be at once referred for the consideration of the Chief of the Bureau, whose decision is to be final unless appealed from to the Secretary. The doubts and disputes are manifestly those which might arise between the contractors and the engineer in charge. In other words, the contract provided that before the provision should become practically binding, it would be necessary that the engineer in charge, the Chief of the Bureau, and the Secretary of the Navy should all decide against the contractors, and that two of the three should be disinterested. As regards some of the matters in controversy there was no “doubt” or “dispute” on the part of the engineer in charge — his decision was on the side of the contractors — the controversy was begun by the Chief of the Bureau.

If the full intent and effect be given to this provision which [545]*545tbe defendants now ascribe to it, the contractors might as well ■ have written an agreement on half of a sheet of paper, bind-, ing themselves to perform whatever work and furnish whatever material the Chief of the Bureau might require, and accept therefor whatever remuneration the .Secretary of the Treasury might be pleased to give them.

In Douglas’s Case (2 C. Cls. B., 347) this court said “there are agreements to abide by the decision of a third person, reciprocally obligatory upon both the parties, which are always to be upheld — as an agreement that wagons to be manufactured shall be examined and approved by a certain inspector (Albert Droion’s Case, 1 C. Cls. B., 307), or that the title to an estate to be conveyed shall be approved by the Attorney-General {H&rchamts1 Exchange Company's Case, lb. B., 332), but a decision under this contract by the referee, made after the contract has expired, and when the rights of the parties had become settled and fixed thereunder, can not preclude them from appealing to a court of j ustice. ” In Hurts v. Litchfield (39 N. Y. R.), where a contract provided that “in case any question arises under such contract in relation to the work, both as to value of work added or. deducted, the same shall be adjusted by the architect,” the Court of Appeals held that the provision was not binding, being against the policy of the common law, and having a tendency to exclude the jurisdiction of the courts, provided with ampler means to entertain and decide legal controversies.” The court also said that such stipulations “do not deprive the party of his action, either at law or in equity, to enforce his rights.” Many cases are cited, English and American. The Court of Appeals recognized as valid such stipulations as have always been upheld in this court, cases “where an agreement makes the procurement of an architect’s certificate a condition precedent to any right of action; then,” says the court, “the rule is as claimed by the defendant in this case, but such is not the agreement between these parties.”

In the many cases in which it has been held that where a contract provides that the architect or the engineer in charge shall determine the quantity or the fitness of the material or the sufficiency of the work his decision is ordinarily final it has been the reference of a matter of fact to the arbitrament [546]*546of a person peculiarly fitted by his own knowledge concerning- the subject of dispute to determine a simple fact. But since the decision of the Supreme Court in Glarlds Case (6 Wall. R., 543) it has never been supposed that even the engineer’s system of measurement was conclusive of the contract- or’s rights. (Collins and Farwell, 34 C. Cls. R., 294.) In the cases of all building contracts there are matters to be determined as the work progresses. Some one must pass upon the fitness of the material, the sufficiency of the workmanship, the amount of work performed, etc.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Binghamton Construction Co. v. United States
107 F. Supp. 712 (Court of Claims, 1952)
Beuttas v. United States
60 F. Supp. 771 (Court of Claims, 1944)
Smith v. United States
96 Ct. Cl. 326 (Court of Claims, 1942)
Penker Construction Co. v. United States
96 Ct. Cl. 1 (Court of Claims, 1942)
Oltedale v. United States
39 F. Supp. 998 (D. Rhode Island, 1941)
E. M. Gilbert Engineering Corp. v. United States
82 Ct. Cl. 616 (Court of Claims, 1936)
Emery v. United States
13 F.2d 658 (D. Connecticut, 1926)
Penn Bridge Co. v. United States
59 Ct. Cl. 892 (Court of Claims, 1924)
Lake Michigan Water Co. v. United States Fidelity & Guaranty Co.
123 N.E. 703 (Indiana Court of Appeals, 1919)
Brinck v. United States
53 Ct. Cl. 170 (Court of Claims, 1918)
Gearing v. United States
48 Ct. Cl. 12 (Court of Claims, 1912)
Savage Construction Co. v. United States
47 Ct. Cl. 298 (Court of Claims, 1912)
Venable Const. Co. v. United States
114 F. 763 (U.S. Circuit Court for the Northern District of Georgia, 1902)

Cite This Page — Counsel Stack

Bluebook (online)
35 Ct. Cl. 514, 1900 U.S. Ct. Cl. LEXIS 96, 1900 WL 1476, Counsel Stack Legal Research, https://law.counselstack.com/opinion/barlow-v-united-states-cc-1900.