Driscoll v. United States

34 Ct. Cl. 508, 1899 U.S. Ct. Cl. LEXIS 14, 1800 WL 2167
CourtUnited States Court of Claims
DecidedOctober 23, 1899
DocketNo. 20930
StatusPublished
Cited by8 cases

This text of 34 Ct. Cl. 508 (Driscoll v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Driscoll v. United States, 34 Ct. Cl. 508, 1899 U.S. Ct. Cl. LEXIS 14, 1800 WL 2167 (cc 1899).

Opinion

Peelle, J.,

delivered the opinion of the court:

December 11,1893, the claimant entered into, the contract set out in the findings, whereby he agreed that for the consid[520]*520eration of $29,490 be would furnish all the labor and materials and perform all tbe work required for the erection and completion of the extension to the custom-house and post-office building at New Haven, Conn., including changes in the present building as in said contract provided, which work was to be completed within seven months from said date.

During the progress of the work sundry supplemental contracts were entered into for certain extra work aggregating $1,950, which work was performed by the claimant and for which, together with all other work required by the terms of said contracts, he has been paid except as to the sum of $157.25, which was withheld from him as damages sustained on the theory that part of the time of the delay in completing said work was due to the fault of the claimant.

In addition to the extra work for which the claimant has been paid, he was required by the local agent, as set forth in the findings, to perform certain additional work, not provided for by the terms of the contract, for the payment of which he seeks a recovery on quantum meruit.

The claimant, without any fault on his part, was delayed by the acts of the defendants in the completion of said work until June 29, 1895, or eleven months and eighteen days beyond the time of the contract period, of which one month and eighteen days were necessarily required in the performance of the extra work aforesaid. For this delay he seeks to recover damages.

The defense in respect of the $157.25, which was withheld under the forfeiture clause of the contract as the amount of damages sustained, on the theory that a part of the delay was the fault of the claimant, is met by the findings of fact in the claimant’s favor and need not be further considered.

In the advertisement for proposals general instructions were given to bidders, among which, under the head of “measurements,” was the following:

“ The successful bidder, at the proper time, to be determined by him, must make all measurements necessary for the proper-prosecution of the work called for by the drawings and specifications; and, during the prosecution of the work, he must make all necessary remeasurements to prevent misfittings in said work; and he will be responsible therefor.”

That paragraph enjoined upon the successful bidder the duty [521]*521and responsibility not only of making “ all measurements necessary for the proper prosecution of the work called for by the drawings and specifications,” but also to make, during the progress of the work, “ all necessary remeasurements to prevent inisfittings in said work.”

The advertisement and general instructions forming a part thereof were incorporated into the contract, and it was therefore clearly the claimant’s duty, dictated by common prudence as well, to make or cause to be made for his own guidance, in the proper prosecution of the work, the necessary measurements and remeasurements called for by the drawings and specifications;” and if the duty and responsibility thus devolved upon him were neglected, by reason .of which he suffered loss, the defendants can not, either in law or in equity, be held liable therefor.

In other words, if in the prosecution of the work the claimant, in making measurements, relied upon one set of drawings alone and was thereby misled, to his injury, the fault was his own, as by the terms of his contract the necessary measurements were based on drawings and specifications; and there is no controversy but that by comparing the drawings or. the drawings with the specifications the proper basis for making the necessary measurements could have been readily ascertained ; but, if not, it was clearly the duty of the claimant, before proceeding further in that respect, to so inform the defendants, to the end that the proper basis might be furnished him.

In the Simpson Case (310. Cls. ft., 217) a contract was entered into to build a dry dock upon an available site to be provided by the Government'. Before entering into the contract the Government had caused soundings or borings to be made by its engineer officers which disclosed no special difficulty. The contractors entered into the contract without making any examination as to the character of the underlying soil. During the progress of excavation a stratum of quicksand was struck, which greatly increased the cost of the work, and the claimants sought to recover damages therefor on the ground that the Government, by agreeing to provide an available site, had thereby guaranteed the character of the underlying soil as indicated by the borings so made, and that in making.their bid and contract they had relied thereon, but the ruling of the [522]*522court was adverse to their contention, and on appeal (172 U. S., 372) the decision was affirmed, the court, among other things, saying:

“ The fact that the bidders knew that a test of the soil in the yard had been made and drew the contract providing that the dock should be located on a site to be designated by the United States without any express stipulation that there was a warranty in their favor that the ground selected should be of a defined character, precludes the conception that the terms of the contract imposed such obligation on the Government in the absence of a full and clear expression to that effect, or at least an unavoidable implication.”

A similar question to the one under consideration was recently passed upon in the case of Burgywn (ante, p. 348). Iu that case the specifications under the head of “ General instruction for bidders” provided:

“ It is understood and agreed that the quantities given are approximate only, and it must be understood that no claim shall be made against the United States on account of any excess or deficiency, absolute or relative, in the same. Bidders are expected to examine the drawings and are invited to make the estimate of quantities for themselves.”

Still another specification under the head of “Details of the work ” correctly gave the basis or area within which the dredging was to be done, but in making computation therefrom the engineer officer stated the quantities of material to be excavated largely in excess of the true amount. The claimant sought a recovery on the theory that in making his bid he had relied upon the specifications, and that in respect of the numerical quantities of material stated they were erroneous, “ by reason of which to entitle the claimant to the compensation provided for in the contract, it became necessary for him to move his dredging machines over more extensive areas than those stated in the specifications, thereby increasing the cost of the work to his damage.”

But the ruling was adverse to the claimant, the court saying:

“All the factors for the computation were c'orrectly given and were open to. bidders, and they were expected and invited to make computations for themselves.
“ They were by the terms of the specifications cautioned to satisfy themselves of the character of the material and of the conditions of the work.’
“To uphold the claimant in his contention in the face of the [523]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Harvey Ward Locke v. United States
283 F.2d 521 (Court of Claims, 1960)
John Thomson Press, & Manufacturing Co v. United States
57 Ct. Cl. 200 (Court of Claims, 1922)
Bray v. United States
46 Ct. Cl. 132 (Court of Claims, 1911)
Lewman v. United States
41 Ct. Cl. 470 (Court of Claims, 1906)
Sprague v. United States
37 Ct. Cl. 447 (Court of Claims, 1902)
P. H. McLaughlin & Co. v. United States
37 Ct. Cl. 150 (Court of Claims, 1902)
Venable Const. Co. v. United States
114 F. 763 (U.S. Circuit Court for the Northern District of Georgia, 1902)
Barlow v. United States
35 Ct. Cl. 514 (Court of Claims, 1900)

Cite This Page — Counsel Stack

Bluebook (online)
34 Ct. Cl. 508, 1899 U.S. Ct. Cl. LEXIS 14, 1800 WL 2167, Counsel Stack Legal Research, https://law.counselstack.com/opinion/driscoll-v-united-states-cc-1899.