P. H. McLaughlin & Co. v. United States

37 Ct. Cl. 150, 1902 U.S. Ct. Cl. LEXIS 129, 1900 WL 1498
CourtUnited States Court of Claims
DecidedFebruary 17, 1902
DocketNo. 18941
StatusPublished
Cited by10 cases

This text of 37 Ct. Cl. 150 (P. H. McLaughlin & Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
P. H. McLaughlin & Co. v. United States, 37 Ct. Cl. 150, 1902 U.S. Ct. Cl. LEXIS 129, 1900 WL 1498 (cc 1902).

Opinion

Howry, u.,

delivered the opinion of the court:

Authority was conferred by an act approved March 3,1887, upon the Secretary of the Navy to have constructed a new Naval Observatory on Georgetown Heights, in the city of Washington, D. C.

Pursuant to that authority, the Secretary invited proposals for the construction and erection, by contract, of nine buildings. The specifications with plans (except certain details of work and materials relating to the construction of floors, piers for instruments, and equatorial domes) were to be had on application, and proposals were to be made in accordance with forms to be furnished. It was required that each proposal should be accompanied by a satisfactory guaranty that the bidder would, within twenty days after the receipt of notice of acceptance, execute the required contract and give a bond, with satisfactory surety, conditioned for the faithful performance of the contract within eighteen months after it was made.

A bid by plaintiffs for this work was accepted June 29,1888, but the contract between the parties was- not actually executed until October 2,1888. It does not appear whether any unusual preparation for the undertaking was made by plaintiffs between those dates.

The building lines not having been designated until November 2, 1888, active work on the buildings was not begun until that time. Because of delay in the execution of the contract and the omission of the engineers to designate building lines, the contractors applied for and obtained an extension of time for the completion of the work to October 1, 1890. Three extensions of time to complete were subsequently granted on the application of the contractors.

With an extension of time to their credit of nearly two months, plaintiffs abandoned the work September 3, 1891, before it was finished, and thereupon the contract was by proper authority declared forfeited.

After forfeiture the buildings were completed under a new contract. The cost of completion was charged to plaintiffs, and an account was rendered to them showing the debits and credits to which each party to this action was entitled under the original contract with the authorized additions. A balance appearing in plaintiffs’ favor, the amount of it was paid [184]*184to them on the order of the Secretary of the Navy. Subsequently plaintiffs suggested an error of $2,864.80, with a view of having the same corrected. The Secretary declined to I’efund the amount asked, whereupon the plaintiffs brought this action.

The claims, tabulated from the amended petition, are as follows:

1. Delay until October 2,1888, in the execution of the contract. $4,500. 00

2. To extra expenses incurred, on account of enforced delays of the work by the Government, April 22, 1890, to September 8, 1891, for enforced idleness for said period of watchmen, drivers to teams, a foreman and engineer, blacksmith and helper, a clerk, timekeeper, office boy, teams and feed of horses, cost of maintaining separate office for assistant Government architect, making a total of §13,714.50; lossoftime and opportunity to each member of the firm for eighteen months, at $200 per month, $10,800; profits lost, which might have been made if other contracts could have been taken during these eighteen months, $6,150; amount paid general laborers, not above enumerated, $10,000; total of these items. 40,673.50

3. Materials furnished and work done by the contractors on the buildings and appurtenances on account of mismanagement and delays of defendants, which cost the contractors $374,-059.96, upon which a commission of 20 per cent profit is claimed. 74,811. 99

4. Materials furnished and work done extra to the contract ... 29,371. 35

5. Materials at the site at the time of forfeiture, and appropriated by defendants. 24,478. 35

6. Exclusion of Davis, one of the contractors, without just cause, from the management and direction of the work for a year and a half during the life of the contract (necessitating the employment of an extra foreman at $5 per day). 27,250.00

7. Failure to pay the full amount of 90 per cent of the value of the work at the times specified by the contract, but withheld, to the embarrassment of the contractors in arranging payment for materials and labor, compelling them to borrow-money and to pay interest. 2,588. 77

8. An improper charge against the contractors on account of salary of the assistant architect of said buildings and traveling expenses of the architect... 2,564.80

These demands are so inconsistent witb an apparent adjustment of the matter after the completion of the work, and are so earnestly urged as just, the items will be considered upon their merits irrespective of the supposed settlement.

[185]*185Respecting delay in the execution of the contract, it is argued for the plaintiifs that the advertisement and specifications were complete when submitted for bids, and that the acceptance of the proposals for doing the work constituted a. contract without the formalities of a subsequent written agreement; and although it is conceded that the Secretary of the Navy was bound by law to make a formal contract, nevertheless it is insisted that it was his duty not to delay doing so to' the damage of the bidders.

The defense is rested upon the ground that plaintiffs did not complete the execution of the bond conditioned for the faithful performance of the work until a few days before the contract was formally executed; and, secondly, that the matter of delay was subsequently submitted to the Secretary of the Navy with a view of securing an extension of time only, which was granted.

The statutes relating to public contracts, some directory, but others mandatory, are not interposed by way of defense to this branch of the case (secs. 3744-3747); but section 3744 of the Revised Statutes provides that “it shall be the duty of the Secretary of War, of the Secretary of the Navj-, and of the Secretary of the Interior to cause and require every contract made by them severally on behalf of the Government, or by their officers under them appointed to make such contracts, to be reduced to writing- and signed by the contracting parties ivith their names at the end thereof. ” This statute is mandatory. (Clark v. United States, 95 U. S. R., 539; South Boston Iron Company v. United States, 118 U. S. R., 37.) Operative as a statute of frauds, it makes contracts not reduced to writing and signed by the contracting parties void.

The preliminary advertisements, specifications, and proposals and acceptance of proposals must be viewed as becoming a part of the statutory contract when a contract was executed as required by statute, but until then only the negotiations necessary to the execution of a formal contract. The exception noted in the books that a parol contract wholly or partly executed on one side entitles the party performing to recover the fair value of his property or services as upon an implied contract for a quantum meruit has no application here.

Independent of the statute, while the contractors were no [186]*186doubt waiting on the Secretaiy, thej1- were quietly doing so and presumably engaged in business profitable to themselves, although it does appear that the contractors declined to accept other contracts.

They made no effort, however, to complete the preliminaries.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

S&E Contractors, Inc. v. United States
406 U.S. 1 (Supreme Court, 1972)
Oltedale v. United States
39 F. Supp. 998 (D. Rhode Island, 1941)
Penn Bridge Co. v. United States
59 Ct. Cl. 892 (Court of Claims, 1924)
Brinck v. United States
53 Ct. Cl. 170 (Court of Claims, 1918)
Otero v. United States
48 Ct. Cl. 216 (Court of Claims, 1913)
Plumley v. United States
226 U.S. 545 (Supreme Court, 1913)
United States v. New York & P. R. S. S. Co.
197 F. 995 (S.D. New York, 1912)
Plumley v. United States
43 Ct. Cl. 266 (Court of Claims, 1908)
Lewman v. United States
41 Ct. Cl. 470 (Court of Claims, 1906)