Ferris v. United States

28 Ct. Cl. 332, 1893 U.S. Ct. Cl. LEXIS 65, 1800 WL 1937
CourtUnited States Court of Claims
DecidedApril 27, 1893
DocketNo. 12813
StatusPublished
Cited by13 cases

This text of 28 Ct. Cl. 332 (Ferris v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ferris v. United States, 28 Ct. Cl. 332, 1893 U.S. Ct. Cl. LEXIS 65, 1800 WL 1937 (cc 1893).

Opinion

Weldon, J.,

delivered tbe opinion of tbe court:

Tbe plaintiff on tbe 15th of December, 1881, filed a petition in which be claimed tbe sum of $10,000 as compensation for work performed by him in dredging tbe Delaware River, under a contract dated on tbe 28th day of January, 1880; alleging, that because of tbe work being different from tbe specifications, and tbe assurance of tbe engineer in charge of the work [338]*338that be would be paid for the increased value of the labor, that claimant is entitled to. recover said sum from the defendants.

On the 22d day of January, 1886, he filed an amended petition, in which he alleges, that as the contract into which he-entered as aforesaid provided for the excavation of 180,000 cubic yards, more or less, of material, he made arrangements tO' perform that amount of work, and he further avers—

’ “ That there being no convenient land above high-water mark upon which-the said material could be landed, and the defendant failing to provide a dike or bulkhead behind which the said material could be deposited, your petitioner was required by the officers of the defendant in charge of said work to construct a dike for that purpose; and that in obedience to the requirements of said officers, and upon the supposition that he would be required to excavate, remove, and deposit the amount of material specified in said contract, to' wit, 180,000 cubic yards, he purchased the necessary land, and constructed a dike capable of holding 180,000 cubic yards of said material, at a cost to himself of the sum of eight thousand dollars. And your petitioner further avers that by reason of the said premises he is entitled to have and recover from the said defendant the sum of eight thousand dollars in addition to said sum of $10,000.”

The original and amended petitions make two distinct claims for compensation, first the increased cost because of the difference in the character of the material in fact, and the character as set forth in the specifications; second, compensation for the damages or costs incident to the construction of a dike and the purchase of land to be used as a dumping ground for the débris of the excavation.

Upon the first branch of the case, the facts set forth in the. eighth finding are applicable—

“ Relying upon the promises of the engineer in charge, to' whom the matter had been referred by Col. Macomb, that he should be compensated for the difference in the character of the work, the'claimant continued the prosecution of the same up to the 19th day of July, 1880, when he was notified verbally of the suspension of the work. He had then excavated and removed from the channel of the Delaware River, near Petty’s Island, 33,232 cubic yards of said material, for which he was-paid by the United States, the sum of thirty-five cents per cubic yard, as provided by said written contract, making the sum of $11,631.20; and .after the suspension of the work when claimant called on Col. Macomb for a settlement in full he was [339]*339referred by tbat officer to Gen. Wrigbt, and Gen. Wright's answer to the demand was ‘I can do nothing for you.’ Your only recourse is an act of Congress or the Court of Claims.’”

By this finding it will be seen that the claimant removed 33,232 cubic yards of excavation for which he has been paid at the rate of 35 cents, the contract price; and finding xn shows, that the reasonable value of the removal of the material as it. in fact existed was the sum of 55 cents. The difference-between the value of the removal of the hind of material that, was removed, and the contract price is the sum of $6,646.40;: and if the contention of the complainant be sound in law, upon that branch of the case, he is entitled to recover the sum of' $6,646.40. Whatever of obligation as a contract expressed which rests on the United States grows out of, and is dependent upon, what was said between the engineer in charge of the.* work and the claimant at the time it was discovered, that the-material in the excavation differed very essentially from the-specifications of the agreement. If the engineer in charge had authority to bind the defendants by his assurance that additional compensation would be paid, such assurance makes the defendants responsible, and upon that part of the case claimant has a right to recover.

The contract under which the work was performed provides :

“If, at any time during the prosecution of the work, it be-found advantageous or necessary to make any change or modification in the project, and this change or modification should involve such change in the specifications as to character and quantity, whether of labor or material, as would either increase- or diminish the cost of the work, then such change or modification must be agreed upon in writing by the contracting parties, the agreement setting forth fully the reasons for such change, and giving clearly the quantities and prices of both material and labor thus substituted for those named in the original contract, and before taking effect must be approved by the-Secretary of War: Provided, That no payments shall be made-unless such supplemental or modified agreement was signed and approved before the obligation arising from such modification was incurred.
“ hfo claim whatever shall at any time be made upon the United States by the party or parties of the second part for or on account of any extra work or material performed or finished, or alleged to have been performed or furnished, under or by virtue of this contract, and not expressly bargained for and specifically included therein, unless such extra work or-[340]*340materials shall have been expressly required in writing by the party of the first part or his successor, the prices and quantities thereof having been first agreed upon by the contracting-parties and approved by the Chief of Engineers.
“Payments shall be made to the said G. H. Ferris when the work contracted for shall have been delivered and accepted, reserving ten (10) per. cent from each payment until the whole work shall have been so delivered and accepted.”

The findings do not show that Col. McComb during the progress of the work had any knowledge of the understanding or agreement between the engineer in charge and the claimant as to the increased compensation; nor do they show that either the Secretary of War or the Chief of Engineers consented or agreed in any way that the claimant should be paid beyond the 35 cents provided in the contract. The agreement stipulates that no claim shall be made against the United States “for or on account of extra work or material performed or furnished or alleged to be performed or furnished under or by virtue of said contract. ” This court said in the ease of Ford (17 C. Cls. R., 75);

“In applying the law of agency to the transactions of the Government, it has not been the purpose of the Supreme Court, nor of this, to shackle or curtail the lawful and reasonable powers of the executive. Both courts have sought with great unanimity of decision to uphold the necessary discretion of the heads of the executive departments, and other responsible officers of the Government, but at the same time so to apply the law that subordinate and irresponsible agents should not bring upon the Government an unauthorized indebtedness through the medium of implied contracts.”

The case of Hawkins (12 C. Cls.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brunner v. United States
70 Fed. Cl. 623 (Federal Claims, 2006)
Beuttas v. United States
77 F. Supp. 933 (Court of Claims, 1948)
W. H. Armstrong & Co. v. United States
98 Ct. Cl. 519 (Court of Claims, 1943)
Walter C. Reediger, Inc. v. United States
94 Ct. Cl. 120 (Court of Claims, 1941)
Houser v. United States
39 Ct. Cl. 508 (Court of Claims, 1904)
Sprague v. United States
37 Ct. Cl. 447 (Court of Claims, 1902)
P. H. McLaughlin & Co. v. United States
37 Ct. Cl. 150 (Court of Claims, 1902)
Atlantic Dredging Co. v. United States
35 Ct. Cl. 463 (Court of Claims, 1900)
James E. Simpson & Co. v. United States
31 Ct. Cl. 217 (Court of Claims, 1896)

Cite This Page — Counsel Stack

Bluebook (online)
28 Ct. Cl. 332, 1893 U.S. Ct. Cl. LEXIS 65, 1800 WL 1937, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ferris-v-united-states-cc-1893.