Atlantic Dredging Co. v. United States

35 Ct. Cl. 463, 1900 U.S. Ct. Cl. LEXIS 110, 1900 WL 1472
CourtUnited States Court of Claims
DecidedMay 14, 1900
DocketNo. 14680
StatusPublished
Cited by6 cases

This text of 35 Ct. Cl. 463 (Atlantic Dredging Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Atlantic Dredging Co. v. United States, 35 Ct. Cl. 463, 1900 U.S. Ct. Cl. LEXIS 110, 1900 WL 1472 (cc 1900).

Opinion

WeldoN, J.,

delivered the opinion of the court:

On the 23d day of September, A. D. 1879, the claimant and defendants entered into an agreement, the substance of which is that the claimant agreed to perform certain dredging for the defendants in the Lubec Narrows in the State of Maine, consisting of four excavations, amounting in the aggregate to 142,720 cubic yards, more or less, for which the claimant was to receive different prices, according to the location. The contract advertisement and specifications are made a part of the petition as “A. D. Co., Exhibit No. 1.” It is alleged that the defendants had by examination ascertained, as they thought, the character of the material in the different excavations, especialty D and C, which comprise the larger portion of the excavation, and that upon such knowledge the contract provides as to the character of the material embraced in such excavation, as hereafter shown; that the claimant ■ entered upon the performance of the work within the time with sufficient force; that in the prosecution of the work it was found that D and E did not consist as in said contract provided of “sandy mud and a little gravel,” but upon the contrary consisted of stiff and tenacious clay extremely difficult to remove. It is further averred that upon finding that to be the character of the material the parties attempted to make a new agreement, but failed to do so; that thereupon the claimant abandoned further work upon said shoal in consequence of such materia] being so different from that alleged, and that because of such breach of contract on the part of the defendants the claimant suffered and was subjected to great loss by being prevented from making gains in the performance of such work.

[477]*477It is further alleged that for work actually performed on the different parts of said contract there is due the claimant the sum of $1,217, which being added to the profits which the claimant would have made, and the expenditure to which it was subjected in preparation for the work, amounts to the sum of $35,465/88.

The main controversy arises on that portion of the contract embraced in the fourth classification of work between points D and E, the claimant contending, that as to that work, there is a warranty as to the character of the material to be excavated in the specifications, as follows: “The material composed in shoals between D and E consists chiefly of sandy mud and a little gravel, the estimated quantity of which to be averaged amounts to 125,000 mdre or less cubic yards, measured in scow.” The findings show that the shoals between D and E differed very materially from “sandy mud and a little gravel ” and that such excavation was worth much more than “sandy mud and a little gravel.”

The legal theory upon which the claimant seeks to recover is that there is an express warranty in the agreement as to the quality of the excavation, that such warranty was violated by the great difference in the material in fact and the material contracted for, and because of such violation it is entitled to recover profits and compensation for its outlay in preparing for the execution and performance of the work.

It is contended by defendants that as a matter of fact the claimant did not rely on the specifications as to the character of the material, but made examinations for itself; and conceding that the terms of the specifications measure the liability of the defendants, they do not express or imply a warranty of the kind of material composing the excavation provided for in the agreement. In support of this contention counsel for the United States quotes the language of the Supreme Court in the case of Simpson & Co. v. The United States (172 U. S., 372) and this court in the same case (31 C. Cls. K., 217).

It is said by the Supreme Court: “ If it had been their intention to only undertake to build a dock for the price stipulated, provided a guaranty was afforded them by the United States that the soil upon which the dock was to be constructed was [478]*478to be of a particular nature, conforming to a plan then existing, a purpose so important, so vital, would necessarily have found direct and positive expression in the bid and specifications, and would not have been left to bo evolved by a forced and latitudinarian construction of the word ‘ available,’ used only in the nature of a recital in the specifications and not in the contract. The fact that the bidders knew that a test of the soil in the yard had been made, and drew the contract providing that the dock should be located on a site to be designated by the United States, without any express stipulation that there was a warranty in their favor that the ground selected should be of a defined character, precludes the conception that the terms of the contract imposed such obligation on the Government in the absence of a full and clear expression to that effect, or at least an unavailable implication.”

In the opinion of this court it is said: “We fail to see how the character of the soil entered into the contract. No representations were made as to it (the profile shown in the findings of fact did not amount to a representation upon which the plaintiffs might rely); the Government did not guarantee the character of the soil underlying the site, but freely gave the plaintiffs what information it had, and the parties contracted in no way as to the foundation of the site.”

In the Simpson case the contract simply provided that the dry dock was to be built in certain navy-yards, “ upon available sites to be provided by the Government,” and under that clause of the agreement it was held by this court, and affirmed bj' the Supreme Court, that there was no warranty as the subsoil or guaranty against quicksand, or any other matter which might cause an extraordinary expense to the contractor.

The substance of the decision is, that no liability attached to the United States because the terms of the contract had no reference to the character of the material to be excavated in the performance of the agreement.

The Supreme Court in substance says: If it had been the purpose to particularize the material to be excavated, such a purpose would have found expression in the bid and specifications and would not have depended upon the “latitudinarian construction of the word ‘ available ’ in the nature of a recital in the specification.” The Simpson case differs very [479]*479much from the case at bar in this, to wit: In that case the contract of warranty as contended for by the claimant depended upon the use of the expression “upon a site that was available,” without any designation of the character or quality of the material to be excavated; in this case there is a specific description of the kind of material which is to be removed, to wit, to consist chiefly of “ sandy mud and a little gravel.”

In the Simpson case the alleged warranty related to the surface indications of an available site open to the inspection and view of the claimant, but in this case the alleged warranty is as to the composition of the material composing the shoals which by the terms of the agreement were to be dredged. The one stated an available site as to space and environment; the other relates to the character and quality of • the material, which is shown by the findings to have been very important, inasmuch as when the true character of the shoal was known a contract was let at nearly double the price for which the claimant was to do the work. One related to the surface or site; the other refers to composition hidden from the view.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Volk v. United States
56 Ct. Cl. 395 (Court of Claims, 1921)
Atlantic Dredging Co. v. United States
53 Ct. Cl. 490 (Court of Claims, 1918)
Lewman v. United States
41 Ct. Cl. 470 (Court of Claims, 1906)
Houser v. United States
39 Ct. Cl. 508 (Court of Claims, 1904)
Groton Bridge & Manufacturing Co. v. Alabama & Vicksburg Railway Co.
80 Miss. 162 (Mississippi Supreme Court, 1902)

Cite This Page — Counsel Stack

Bluebook (online)
35 Ct. Cl. 463, 1900 U.S. Ct. Cl. LEXIS 110, 1900 WL 1472, Counsel Stack Legal Research, https://law.counselstack.com/opinion/atlantic-dredging-co-v-united-states-cc-1900.