Lane Construction Corp. v. Department of Highways

17 Ct. Cl. 73
CourtWest Virginia Court of Claims
DecidedJanuary 15, 1988
DocketCC-82-164
StatusPublished
Cited by2 cases

This text of 17 Ct. Cl. 73 (Lane Construction Corp. v. Department of Highways) is published on Counsel Stack Legal Research, covering West Virginia Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lane Construction Corp. v. Department of Highways, 17 Ct. Cl. 73 (W. Va. Super. Ct. 1988).

Opinion

GRACEY, JUDGE:

Claimant, The Lane Construction Corporation, herein presented a claim against the respondent, the West Virginia Department of Highways, for damages in connection with construction of 6.963 miles of the Highland Scenic Highway, also known as West Virginia Route 150, in Pocahontas County. The alleged damages are generally itemized as follows:

1977 Fill Bench Delay $814,580.19

1979 Slide Delay 102,577.22

1980 Costs 1,062,187.70

[74]*741980 Escalation for Paving 10,116.30

$2,079,461.41-

The contract was advertised for bids as a "Federal Aid Project HSH-l(l)." Claimant submitted the lowest bid, in the amount of $11,467,571.20 and was awarded the contract on May 14, 1977. The project was through the Monongahela National Forest, heavily wooded, rugged terrain, all high in the mountains. It ran from its westerly end, about two miles east of the Williams River, at Station 822, to its easterly end at Station 1189 + 59 at Route 219. To the south was the Edray Fish Hatchery. To the north was the headwaters of the Elk River. The climate conditions were variable and severe, much rain and cold, limiting the length of a construction season. The environmental considerations posed limitations. Timber cut in clearing the right of way was required to be hauled out of the project area, not wasted. Under Section 642.3.2 of the contract Supplemental Specifications, limitations as to the area of clearing and grubbing and excavations were clearly spelled out.

"... To provide a positive guide in this are no more than 750,000 square feet each of erodible soil will be exposed as a result of (1) clearing and grubbing and (2) excavation, embankment, borrow or waste for a maximum cumulative total of 1,500,000 square feet without the approval of the Engineer. Approval to proceed beyond this point will be contingent upon (1) the Engineer's satisfaction, based on performance, as to the Contractor's ability to proceed with his operation and yet maintain pollution control at the level contemplated by this special provision, and (2) Seeding and Mulching of disturbed areas at the Contractor's expense."

The Claimant's Contractor's Proposal, and the resulting contract, called for completion of the project by June 30, 1980. At the pre-construction conference, held on May 3, 1977, the claimant presented its intended schedule for construction. The claimant anticipated completing the project in 1979. Upon cross examination, Byron F. Wetmore, claimant's Executive Vice President, conceded that "... we thought we would have to have relief on that 1,500,000 square feet." The contemplated schedule called for commencement of this work on the project, nearly seven miles, by the end of July, 1977. "We realized there was a restriction in the specification and hoped we could overcome it." What made him think he could overcome such a restriction? "We've had it before and have overcome it." He also admitted that he had learned "... that some of the people that had constructed some of the earlier work had gone broke trying to finish work that took them two or three years longer than they anticipated to do it."

The claimant's intended construction schedule also showed project excavation work to begin June 1, 1977, and the construction work continuing through a 1977 construction season ending November 15. By Stipulation, the parties agreed that project excavation work began June 27, and Wetmore conceded that claimant closed down the job, for the winter, on about October 16th or 17th. "The weather was of such magnitude at that time that we could not work after [75]*75October 15." Thus, the 1977 construction season was somewhat shorter than the claimant had planned.

Generally, this project was a cut and fill type operation. The respondent had provided the plans showing the levels at which rock might be found. Claimant was required to excavate to the rock level, then fill, over the rock, with select rock material for drainage, and with earth and rock back to the desired grade. Most of these fill benches were in the easterly half of the project. Also, the respondent had indicated the rock quarry location as being just easterly from a forest road which could provide contractor access to the project at about Station 982, early the mid-point of the project. For several reasons, the claimant elected to begin construction at that mid-point. Weight limitations denied use of Route 39 as access to the westerly end of the project. Claimant would need rock, in the fill bench operations, and the rock quarry was shown as being at Stations 980-988, not conveniently accessible had the excavation work been started at Route 219, the easterly end of the project. As it turned out, that rock quarry was not satisfactory, and rock had to be hauled from another quarry further east. The claimant's plan was to do the more difficult easterly half of the project first. Then, as paving was progressing westerly from Route 219, the excavation and grading work would be progressing from that mid-point westerly, to the westerly end of the project, readied for paving when the paving reached that mid-point.

Not long after the excavation work began, the claimant began to find that the rock was not at the elevations shown on the plans, and in some cases, the rock was not a hard, firm rock base, but soft shale. The first such experience was one where the rock was at a higher elevation than shown. Subsequent excavation areas proved rock at lower elevations than shown. There were about six such areas. In each case, when the indicated elevation was reached, and rock was not found, a few more feet were excavated at respondent's direction. Mr. Wetmore conceded that it is not uncommon to run into such circumstances in the field. However, he added, "The normal reaction is that usually it is done on a continuing basis as differences are found. Normally, decisions are made quickly as to where the elevations are to be established and the redesigns are done, if you will, on a piecemeal basis sometimes, which allows the work to be progressed."

Respondent's alleged delay in making decisions and giving the claimant redesigns is the basis for claimant's 1977 Fill Bench Delay claim in the total amount of $814,580.19. Of this total, $709,473.65 appears to be for idled equipment. $72,800.00 is for stockpiling fill bench materials, for having to move such materials twice instead of once. $9,219.00 is for salaried idle supervisory personnel. $32,306.54 is for higher labor cost for work done in the 1978 and 1979 seasons instead of, as planned, in the 1977 season. The evidence was conflicting as to the length of the delays with reference to the problem areas. Mike O'Neil respondent's geologist, was notified on August 4 and came to the sight on August 8. On August 19, respondent began bore drilling under his direction. There was conflicting evidence as to whether the several sites were bore in a progressive order of priority requested by claimant, but it was apparent that the presence of the drilling rig caused problems for the claimant. According to O'Neil, as a solution and redesign was accomplished, in a few days in most instances, the claimant was furnished with [76]*76a temporary redesign and, within a day or so thereafter, was formally furnished with the redesign plan.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Venable Const. Co. v. United States
114 F. 763 (U.S. Circuit Court for the Northern District of Georgia, 1902)
Ferris v. United States
28 Ct. Cl. 332 (Court of Claims, 1893)

Cite This Page — Counsel Stack

Bluebook (online)
17 Ct. Cl. 73, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lane-construction-corp-v-department-of-highways-wvctcl-1988.