Davis, J.,

delivered tbe opinion of tbe court:

This action is brought to recover damages for alleged breaches of two contracts, each for the construction of a part of the breakwater of the Harbor of Eefuge at Sand Beach, in Michigan, on Lake Huron.

The case was ably and fully argued. The court has also had the advantage of subsequent written briefs and arguments on both sides, and we now feel entire confidence in the correctness of the results which we have reached upon the complicated questions raised in the arguments.

The first contract was dated December 2,1874, and the causes of damage are twelve in number, as set forth in the claimant’s reargument:

1. For preparing 980 feet lineal of bottom, at $3.00. $2,940 00

2. For sinking bulkhead crib No. 1. 600 00

3. For wastage of timber on ties, 34,944 feet b. m., at $15.00.\. 524 16

4. For building 23 crib bottoms, at $50. 1,150 00

5. For stone furnished to level bottom, 145 cords stone, at $6.90.:. 1,000 50

6. For loss of stone washed out by storms, 353 cords stone, at $6.90. 2,435 70

7. For waste of timber by sloping superstructure, 59,666 feet b. m., at $24.50 . 1,461 81

8. For liewing sides of superstructure, 2,523 lineal feet, at 50c. 1,261' 50

9. For labor in putting on wainscoting or sheathing, 141,120 feet b. m., at $4.00. 564 48

10. For labor in putting on plating, 280 lineal feet, , at $1.00. 280 00

11. For additional cost of superstructure over crib-work, 250,000 feet b. m., at $3.00. 750 00

12. For delay and expenses, 60 days, at $100 . 6, 000 00

18,968 15

The second contract was dated June 21,1875, and the causes of damage are four in number, as set forth in the claimant’s reargument:

1. For labor in framing tie-timbers, 533,748 feetb. m., at $4.50.$2,401 86

2. For breaking of crib No. 34. 640 10

3. For do. crib No. 37 ... 3, 609 00

4. For keeping up general expenses 13 days, at $100. 1, 300 00

7,950 96

[530]*530Many of the subjects of contention between the parties are settled in the findings of fact. The court has found that the contract of December 2, 1874, provided for the construction of 1,000 feet, more or less, of crib-work and superstructure on the shore arm of the breakwater, and that, when it became apparent that the appropriation for the year would not be exhausted by that work, the parties, by a liberal construction of the words “more or less,’ extended that contract so as to cover the construction of 500 additional feet on the same arm. These findings sweep away the issues growing out of a supposed transfer of the work from the sea arm to the shore arm of the breakwater, and dispose of claims 1, 4, 5, 8, 9, 10, and 11, under the first contract.

It is also found that the delay in the completion of the work under the first contract was not due to the acts of the defendants or their agents. This makes it incumbent on the court to refuse to allow the twelfth item of the claimant’s demand under the first contract, viz, for delay and expenses, 60 days, at $100 a day.

In the sixth claim under the first contract, the claimant demands compensation for filling a second time the cribs on the shore arm, which were washed out by the storms of September 10 and 17, 1875. The contract provided that payment for the work should be made in monthly installments, after delivery and acceptance of the materials and labor contracted for, and also that no work or material should be accepted and paid for until in a proper position in the breakwater. The work was to be at the risk of the contractor till accepted, and after acceptance was to be at the risk of the defendants.

The latter had an agent on the spot to see that the work was done according to the contract. As each crib was completed by the contractor, with the eye of the defendants’ agent ujpon him, it was sunk into place and then packed with stone. The defendants’ agent then made- estimates of the labor and material, at the contract rates, in the cribs thus sunk and packed during the month, and forwarded them to his superior as the basis for the preparation of vouchers. In due time the voucher was paid. We regard such an estimate as the acceptance of the work on which it was made. Inasmuch as estimates had been made upon the cribs which were damaged by these September storms, the court is of opinion that the cribs had been accepted, [531]*531and tbat they were at tbe defendants’ risk wben tbe injury took place. ,Tbe defendants’ agents were also of tbis opinion. Tbey paid tbe claimant for tbe loss of 35 cords of tbis stone, and tbe captain of engineers in charge reported tbat if it could be proved that more than tbis quantity was washed out, and tbat tbe claimant replaced it, be ought to be paid for it. Tbe amount due tbe claimant on tbis account is $2,374.83.

Tbis leaves for consideration all tbe items claimed under tbe second contract, and items 2, 3, and 7 of tbe claims under tbe first contract.

Tbe defendants set up against all these claims, 1st, receipts of tbe claimant in full under both contracts, and, 2d, tbat tbe changes were ordered by them in tbe exercise of a right reserved in each contract.

As to tbe first of these defenses, it is to be said tbat tbe receipts given on tbe vouchers prepared under tbe final estimates made on tbe two contracts respectively are acknowledgments of payment of tbe value of tbe labor and materials included in tbe estimates at tbe prices therein set forth, and are so far binding on tbe claimant. In tbe absence of proof tbat be assented to tbe correctness of tbe estimates as an estimate in each case oñ tbe entire work, and agreed to be bound by them and to make no further claim, or of proof tbat tbe payment was made and accepted in settlement of a disputed claim, we cannot give tbe receipts tbe force for which tbe defendants contend.

Copies of these receipts, certified in tbe usual way by tbe Secretary of tbe Treasury, were offered in evidence by tbe defendants. These being objected to by tbe claimant, tbe court gave him tbe option of either allowing them to be received in evidence with tbe same force which tbe originals would have bad or of a continuance. ■ He elected to waive bis objection to tbe receipt of tbe evidence. Tbis is a complete answer to tbe unusual request to have a ruling upon tbe admissiblity of evidence inserted among tbe findings of fact.

As to tbe second point in tbe defense, it is to be said tbat tbe clause upon which tbe defendants rely is to be found in both contracts. In tbe first it is stated in tbe following form:

“No variation from these specifications will be permitted without tbe consent of tbe United States engineer officer in charge of tbe improvement, to whom tbe right to make any change in tbe plans and specifications which be may at any time deem expedient is expressly reserved.”

[532]*532Tlie second contract varies from the first only by inserting tlie words “ or location” after tlie word specifications.”

Tlie provisions of tliese contracts concerning xiayment are somewhat anomalous.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ferris v. United States
28 Ct. Cl. 332 (Court of Claims, 1893)
Ford v. United States