J-Way Southern, Inc. v. United States Army Corps of Engineers

CourtDistrict Court, D. Massachusetts
DecidedMay 14, 2020
Docket1:19-cv-12423
StatusUnknown

This text of J-Way Southern, Inc. v. United States Army Corps of Engineers (J-Way Southern, Inc. v. United States Army Corps of Engineers) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J-Way Southern, Inc. v. United States Army Corps of Engineers, (D. Mass. 2020).

Opinion

UNITED STATES DISTRICT COURT DISTRICT OF MASSACHUSETTS

___________________________________ ) J-WAY SOUTHERN, INC., ) ) Plaintiff, ) ) Civil Action v. ) No. 19-12423-PBS ) UNITED STATES, ) ) Defendant. ) ___________________________________)

MEMORANDUM AND ORDER May 14, 2020 Saris, D.J. The United States Army Corps of Engineers terminated its contract with Plaintiff J-Way Southern, Inc. for dredging in Menemsha Harbor, Martha’s Vineyard. J-Way alleges that the Government improperly terminated and breached the contract, and seeks monetary damages. The Government moves to dismiss or transfer, arguing, among other things, that exclusive jurisdiction lies in the United States Court of Federal Claims. Plaintiff responds that the contract is a maritime contract over which federal district courts properly have jurisdiction. After hearing, the Court DENIES the motion to dismiss for lack of subject matter jurisdiction. Because this jurisdictional issue is a matter of first impression, the Court certifies this Order for interlocutory appeal pursuant to 28 U.S.C. 1292(b) and defers ruling on the Government’s remaining arguments for dismissal for at least 60 days. FACTUAL BACKGROUND The following facts come from the complaint and submissions

and are largely undisputed except where stated. I. The Contract J-Way entered into a contract with the Army Corps of Engineers (“USACE”) in June 2015. The contract was for the dredging of “[a]pproximately 62,000 cubic yards of sandy sediment” from Menemsha Harbor in Martha’s Vineyard, Massachusetts to be disposed of on Lobsterville Beach through a temporary pipeline. Docket No. 1 ¶ 14. The bid solicitation identified the “Project Location” as “Menemsha Creek . . . [which] serves host to a U.S. Coast Guard station and is used by recreational craft, a small fishing fleet, and transient boats.”

Docket No. 1-1 at 91. The solicitation’s “General Description of the Work” stated that “[t]he work of this project will consist of the maintenance dredging of shoaled areas within the existing Federal Navigation Channel . . . and the upland disposal of the dredged material.” Id. J-Way was to provide the labor, supervision, materials, and equipment necessary to complete the work. USACE agreed to pay a price per cubic yard of dredged material, plus additional compensation for mobilization and demobilization. “The contract price per cubic yard” of dredging material included “all cost of removal[,] disposal . . . and grading of the dredging material at the disposal site,” Lobsterville Beach. Id. at 103. The contract contained terms regarding the timing and

safety of the work, as well as general terms related to federal construction contracts. It also required J-Way to avoid obstructing traffic in navigable waterways. The contract indicated that certain portions of work would occur on land, such as the hauling and staging of equipment, the laying of pipeline routes, and the disposal and grading of dredged material on Lobsterville Beach. The contract also included provisions related to the protection of local wildlife and vegetation. The contract required J-Way to complete the work by January 31, 2016. J-Way did not complete the work within that time.

II. First Termination for Default In May 2016, USACE issued a first Termination Notice, finding J-Way in default. In August 2016, J-Way filed an administrative claim under the Contract Disputes Act (“CDA”) with USACE’s Contracting Officer (“CO”). J-Way argued the delay was excusable and that the contract deadline should be extended to the following dredging season. The CO reviewed the claim and in August 2016 rescinded the default. In September 2016, USACE and J-Way executed an Agreement to Proceed, which modified the contract to allow J-Way to complete the work by January 16, 2017. III. Second Termination for Default J-Way recommenced dredging but again experienced delays.

USACE issued a Determination and Findings on March 3, 2017, stating that J-Way’s failure to perform the work was not excusable. USACE then issued a second Termination Notice for Default on March 6, 2017. USACE then made a demand upon J-Way’s performance bond to complete the work. In June 2017, USACE and J-Way’s surety, U.S. Specialty Insurance (“Surety”), executed a Takeover Agreement. Pursuant to the Takeover Agreement, the Surety procured a new contractor that timely completed the work. USACE did not assess liquidated damages or excess reprocurement costs against the new

contractor, though J-Way alleges that the Surety paid for procurement costs and other expenses to complete the contract. USACE made its final payment to the Surety in January 2019, at which point the Surety released all claims against the United States. IV. Current Proceedings In November 2018, the Surety brought suit against J-Way in the District Court the District of Massachusetts. See Complaint, U.S. Specialty Ins. Co. v. J-Way Southern, Inc., No. 18-cv-12464 (ECF 1). The Surety sought indemnity pursuant to its contract with J-Way.

In May 2019, J-Way submitted a second administrative claim under the CDA to USACE’s contracting officer, arguing that the March 2017 default termination was unlawful because the delay arose from “unforeseeable causes” such as “unusually severe weather, unforeseeable mechanical breakdowns due to equipment manufacturer defects, USACE’s own acts and omissions, and a previously-scheduled fishing tournament that prevented dredging and was unknown to J-Way when it bid on and was awarded the contracts.” Docket No. 1 ¶ 4. The CO did not reconsider the Termination for Default and took no action on the claim. In November 2019, J-Way brough the present action in U.S.

District Court. The action alleges improper default termination, breach of contract, and breach of implied covenant of good faith and fair dealing, both on behalf of J-Way and its Surety, U.S. Specialty Insurance. J-Way asserts admiralty jurisdiction. STANDARD OF REVIEW Here, the United States moves for dismissal or transfer for lack of subject matter jurisdiction under Rule 12(b)(1). In the alternative, the Government argues J-Way’s claims should be dismissed for failure to state a claim under Rule 12(b)(6). A Rule 12(b)(1) motion is used to dismiss complaints for lack of subject matter jurisdiction. See Fed. R. Civ. P. 12(b)(1). “[W]hen a motion to dismiss for lack of subject matter jurisdiction under Fed. R. Civ. P. 12(b)(1) involves factual

questions,” the court’s standard of review depends on “whether the relevant facts, which would determine the court’s jurisdiction, also implicate elements of the plaintiff’s cause of action.” Torres-Negron v. J & N Records, LLC, 504 F.3d 151, 162-63 (1st Cir. 2007) (citation omitted). Where “the jurisdictional issue and substantive claims are so intertwined” that “resolution of the jurisdictional question is dependent on factual issues going to the merits,” the court applies a summary judgment standard. Id. at 163 (quoting Autery v. United States, 424 F.3d 944, 956 (9th Cir. 2005)). By contrast, “if the facts relevant to the jurisdictional inquiry

are not intertwined with the merits of the plaintiff’s claim,” then the court “is free to weigh the evidence and satisfy itself as to the existence of its power to hear the case.” Id. (quoting Lawrence v. Dunbar, 919 F.2d 1525, 1529 (11th Cir.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bowers Hydraulic Dredging Co. v. United States
211 U.S. 176 (Supreme Court, 1908)
Sutton v. United States
256 U.S. 575 (Supreme Court, 1921)
United States v. L. A. Tucker Truck Lines, Inc.
344 U.S. 33 (Supreme Court, 1952)
Amell v. United States
384 U.S. 158 (Supreme Court, 1966)
Caraballo-Seda v. Municipality of Hormigueros
395 F.3d 7 (First Circuit, 2005)
Torres-Negron v. J & N RECORDS, LLC
504 F.3d 151 (First Circuit, 2007)
Stuyvesant Dredging Company v. The United States
834 F.2d 1576 (Federal Circuit, 1987)
Dolcie Lawrence v. Peter Dunbar, United States of America
919 F.2d 1525 (Eleventh Circuit, 1990)
Donald D. Huston v. The United States
956 F.2d 259 (Federal Circuit, 1992)
Autery v. United States
424 F.3d 944 (Ninth Circuit, 2005)
Thrustmaster of Texas, Inc. v. United States
59 Fed. Cl. 672 (Federal Claims, 2004)
Red River Holdings, LLC v. United States
87 Fed. Cl. 768 (Federal Claims, 2009)
Jay Cashman, Inc. v. United States
88 Fed. Cl. 297 (Federal Claims, 2009)
Stuyvesant Dredging Co. v. United States
33 Cont. Cas. Fed. 75,152 (Court of Claims, 1987)
Weeks Dredging & Contracting, Inc. v. United States
34 Cont. Cas. Fed. 75,356 (Court of Claims, 1987)
Pigeon v. United States
27 Ct. Cl. 167 (Court of Claims, 1892)

Cite This Page — Counsel Stack

Bluebook (online)
J-Way Southern, Inc. v. United States Army Corps of Engineers, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-way-southern-inc-v-united-states-army-corps-of-engineers-mad-2020.