Opinion

Mr. Justice White

delivered the opinion of the court.

The appellant, the dredge company, sued to recover $28,321.76. The relief sought was based on the averment that under a contract for dredging a channel, in the Christiana River and in or about the harbor of Wilmington, Delaware, made in 1399, and a supplementary contract made in June, 1901, ¡he dredge company had excavated 200,430 cubic yards *181 of earth, for which, at the contract price, it should have been paid the sum sued for, but that the United States, m making settlement under the contract, despite the protest of the dredge company, had declined to pay, upon the ground that excavating and removing the earth referred to was not within the' contract. The pertinent facts found by the court below are these (41 C. Cl. 214, 498):

Prior to September, 1899, the United States was engaged in excavating a channel in the Christiana River and about the harbor of Wilmington, Delaware. The work, in September, 1899, was in process of execution, under a contract between the United States and the New York Dredging Company. In the office of the United States engineer in charge of the. work there existed maps or drawings showing the condition of the. river prior to any work being done by the New York Dredging Company, the location of the channel in which the . work was being done, and the specifications controlling the contract, as well as the progress made in the work. Of these facts the dredge company had knowledge. On September 18, 1899, the United States engineer office at Wilmington, through William F. Smith, United States agent, advertised for proposals for the dredging and removing of about nine hundred thousand cubic yards of material in connection with the work then being done, as previously stated. In the advertisement inviting the proposals it was stated that specifications, blank forms for proposals, and all available information would be furnished on application to the engineer office. The specifications for the work in question recited:

“The project, for the completion of which contracts are authorized in the law above quoted, requires the dredging of the Christiana River to a depth of 21 feet at mean low water from the 21-foot curve in the Delaware River to the upper line of the pulp works; thence to the draw pier of the Shellpot branch, No. 4, of the P., W. & B. R. R., so as to give a depth which gradually diminishes to 10 feet at mean low water at the latter-named place and the removal of shoals having less *182 than seven (7) feet of water over them; thence to Newport— the width to be 250 feet to the mouth of the Brandywine, 200 feet thence to the upper line of the pulp works, and 100 feet above. Work is now in progress under contracts for dredging to a depth of 18 feet up to the pulp works, the width to be made being 200 feet, and for all above-described dredging above the pulp works. The work required under these specifications is the dredging that remains to complete the project additional to that done or to be done under the contracts above referred to until their' termination or completion. It is estimated that about 900,000 cubic yards will have to be removed.”

The character of the work required, the method of carrying on the same and the steps to be taken to fix the amount to become due under the contract when fully performed were stated in the specifications as follows:

“The amount of material removed will be paid for by the cubic yard measured in place, and shall be determined by surveys made before dredging is commenced and after it is completed. All surveys and measurements are to be made under the direction of the engineer in charge by persons employed by him for that purpose. The decision of the engineer in charge as to the amount of material excavated and removed, as well as to its location and deposit, shall be final and without appeal on the part of the contractor.
“The location of the work shall be plainly located by stakes and ranges. The level of mean low water as established by the engineer in charge shall not be changed during the progress of the work. The contractor shall be required to supply the lumber for the necessary stakes and ranges, and shall at all times when called upon furnish men and boats to set them and keep them set un^er the direction of the inspector, the expense thereof to be included in the contract price for the dredging.
“No guarantee is given as to'the nature of the bottom, but as far as it is known it is sand, mud, clay, and gravel. Bidders *183 are requested to satisfy themselves upon this point and to examine all other local conditions, as it will be assumed that their bids are based upon personal information. No extra allowance will be made for excavating material differing from that herein described.
■ “It is understood and agreed that the quantities given are approximate only, and it must be understood that no claim will be made against the United States on account of any excess or deficiency, absolute or relative, in the same. Bidders are expected to examine the drawings, and are invited to make the estimate of quantities for themselves. It is not expected that the actual quantities will vary more than 10 per centum from the estimates.
“Payments will be allowed for actual dredging to twenty-one (21) feet below mean low-water level. Work done outside of the. designated lines of excavation or below the specified depth will not be paid for, and any material deposited otherwise than specified and agreed upon must be removed by the contractor at his own expense.”

On November 20, 1899, the claimant (dredge company), whose proposal had been accepted, entered into a contract with the United States through General William F. Smith, United States agent, for the performance of the additional dredging, in conformity with the advertisements and specifications referred to in the preceding findings. It was provided in the contract that “the said Bowers Hydraulic Dredging Company shall furnish all labor, machinery and appliances necessary or proper for the faithful execution of the contract, and shall do the work called for, and in all respects carry out and comply with the said specifications for dredging.” The sum to be paid was fixed by the contract at 10§ cents for each and every cubic yard of material dredged, “measured in place,” the said price including removal and redeposit.

Presumably, in consequence of knowledge on the part of the dredge company of a refusal by the Government to pay the New York Dredging Company for the work being done by *184 it for the removal of any earth from the excavated channel, derived from the sliding from slopes of the same, the dredging company, before commencing work, addressed a letter to General Smith, engineer in charge, requesting to know whether its contract would be construed as excluding payment for removing such earth.

Free access — add to your briefcase to read the full text and ask questions with AI

Bowers Hydraulic Dredging Co. v. United States, 211 U.S. 176, 29 S. Ct. 77, 53 L. Ed. 136, 1908 U.S. LEXIS 1536, 44 Ct. Cl. 592 (1908).

211 U.S. 176 (Bowers Hydraulic Dredging Co. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Chong Yim v. City of Seattle
451 P.3d 675 (Washington Supreme Court, 2019)
Vendura, Jr. v. Boxer
845 F.3d 477 (First Circuit, 2017)
Greenfield v. Cincinnati Insurance Co.
737 N.W.2d 112 (Supreme Court of Iowa, 2007)
Western States Construction Co. v. United States
38 Cont. Cas. Fed. 76,376 (Court of Claims, 1992)
Avedon Corp. v. United States
35 Cont. Cas. Fed. 75,592 (Court of Claims, 1988)
Industrial Indemnity Co. v. United States
34 Cont. Cas. Fed. 75,437 (Court of Claims, 1988)
Hamann v. Crouch
508 P.2d 968 (Supreme Court of Kansas, 1973)
Verdugo Highlands, Inc. v. Security Insurance
240 Cal. App. 2d 527 (California Court of Appeal, 1966)
Johnson, Drake & Piper, Inc. v. State
41 Misc. 2d 804 (New York State Court of Claims, 1964)
Cresswell v. United States
173 F. Supp. 805 (Court of Claims, 1959)
United States v. St. Paul-Mercury Indemnity Co.
194 F.2d 68 (Third Circuit, 1952)
E. J. Albrecht Co. v. New Amsterdam Casualty Co.
163 F.2d 16 (Seventh Circuit, 1947)
Kerr v. State
142 A. 197 (Supreme Judicial Court of Maine, 1928)
Norton Iron Works v. Standard Slag Co.
13 F.2d 622 (Sixth Circuit, 1926)
District of Columbia v. Cranford Paving Co.
271 F. 374 (D.C. Circuit, 1921)