E. J. Albrecht Co. v. New Amsterdam Casualty Co.

163 F.2d 16, 1947 U.S. App. LEXIS 3163
CourtCourt of Appeals for the Seventh Circuit
DecidedJuly 3, 1947
DocketNo. 9210
StatusPublished
Cited by7 cases

This text of 163 F.2d 16 (E. J. Albrecht Co. v. New Amsterdam Casualty Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
E. J. Albrecht Co. v. New Amsterdam Casualty Co., 163 F.2d 16, 1947 U.S. App. LEXIS 3163 (7th Cir. 1947).

Opinion

KERNER, Circuit Judge.

Plaintiff brought an action for damages against New Amsterdam Casualty Company alleging breach of a construction sub-contract between plaintiff and William Dush-ney. The complaint was filed against New Amsterdam, because, as surety, it had executed a bond running to plaintiff, with Dushney as principal, for the faithful performance of the sub-contract. Dushney (also referred to as defendant and counter-claimant) thereupon moved and was granted leave to intervene as a party-defendant. He filed an answer and counterclaim denying liability as to plaintiff and alleging his damages to be $96,520.28.

The issues raised by plaintiffs complaint were submitted to a jury and were decided in favor of defendants. As to Dushney’s counterclaim, upon plaintiff’s motion for a directed verdict, the jury was directed to find, and did so find, in favor of plaintiff, except as to plaintiff’s admitted liability in the sum of $167.02.

Dushney brings this appeal from that portion of the judgment which minimized the amount of the judgment on his counterclaim. The issue before this court then is whether the District Court was correct in directing the verdict on the counterclaim.

In oral argument both plaintiff and defendant conceded that disposition of this case depends on whether the court erred in excluding Dushney’s evidence on his counterclaim.

In his counterclaim, Dushney alleged the existence of a general contract between plaintiff and the United States dated December 30, 1941 and entered into for the purpose of constructing Berlin Dam, a concrete and earth dam on the Mahoning River in Ohio. Subsequently, a written sub- r contract dated March 25, 1942 was entered into between plaintiff and counterclaimant with the consent of the government. By this sub-contract the counterclaimant agreed to haul and dump excavated materials, as was required to be done by the plaintiff in its contract with the government. Measurement and payment for the work performed were to be in accordance with the provisions of the general contract, except for the unloading of cement and crushed stone, separate provision for which was made in the sub-contract. A separate agreement, pursuant to the sub-contract, for the hauling of stone, cement, and sand was also alleged. In addition, it was alleged that under the terms of the sub-contract it was the duty of plaintiff to keep records of the work done by the counterclaimant; that the records kept were incorrect; that plaintiff intermingled its hauling equipment with that of counterclaimant’s and failed to distinguish between the work done [18]*18by the two parties; that plaintiff failed to give counterclaimant full credit for the hauling of stone and cement from railroad sidings; that plaintiff was a fiduciary of funds and accounts related to the sub-contract and, in such capacity, overcharged the counterclaimant for workmen’s compensation insurance purchased on behalf of Dushney; that plaintiff made wrongful additions of state gasoline taxes in keeping the record of counterclaimant’s expenses for the purpose of computing the latter’s earnings; and that plaintiff kept counter-claimant’s equipment idle for a substantial portion of the term of the sub-contract thereby causing additional damages. Itemized, the damages were listed as follows:

Yardage of dirt and rock hauled but not paid for............ $34,397.55

Crushed stone, cement and sand hauled but not paid for...... 8,433.19

Overcharge for Workmen’s Compensation insurance..... 1,294.81

Charge for Ohio State gasoline taxes ..................... 1,279.96

Discounts wrongfully withheld (since waived) ............. 1,710.77

Idleness of hauling equipment and unreasonable delay...... 49,404.00

Total ................... $96,520.28

The sub-contract provided that the measurement and payment for the hauling of excavated materials (which were items under the general contract) by Dushney were to be made in accordance with the provisions of the general contract. It also provided that the measurement and payment for the hauling of common and rock excavations in stockpile (which were not items under the general contract) were to be made in the same manner as those items under the general contract, except that the. measurements were to be based upon surveys of the stockpile. The general contract specified that measurement and payment for the hauling of excavated materials, as provided therein, should be made by means of surveys made before and after the excavations. As prescribed in both the general contract and the sub-contract the survey method consisted of surveying “the site area of the specified work * * * and the original ground surface determined by this survey shall form the basis for the measurement of all excavation quantities. Measurement for payment for common excavation shall be made between the finished slopes * * * and the surface determined by the survey.”

The counterclaimant concedes that his sub-contract with the plaintiff called for measurement by survey. He admits that the survey method is superior as a method of measurement, but insists that this provision of the sub-contract was not binding upon the parties, and contends that the court erred in excluding his evidence as to the quantity of excavated materials he hauled, even though his was secondary evidence and contrary to the method of measurement as provided in the sub-contract. The excluded evidence was a load count record of measurement kept by counter-claimant himself and consisted of daily reports kept by his drivers and foremen of the daily loads hauled by each of his trucks. The load count method then is based upon the number and size of the loads hauled by the trucks, and the estimates necessarily are of the earth and the rock in loose formation and not in the solid mass which is a condition of the survey method.

There is no question that in cases of separate and conflicting methods of measurements, the terms of the contract, if clear and unambiguous, must determine the method of measurement. Bowers Hydraulic Dredging Co. v. United States, 211 U.S. 176, 29 S.Ct. 77, 53 L.Ed. 136, and Franklin A. Snow Co. v. Commonwealth, 303 Mass. 511, 22 N.E.2d 599. In view of the clearly expressed and admitted provision in the sub-contract that the measurement and payment for the hauling of materials be done by survey, the court did not err in excluding Dushney’s evidence relating to load count and his claim for the amount of yardage hauled.

Dushney contends that he impeached plaintiff’s survey records by evidence which showed them to be incomplete and inaccurate, and that the court therefore should have accepted the next best evidence, the load count method, as the true factual situation. In this connection he points to [19]*19the testimony of his expert witness, a civil engineer, who picked two cross-sections (in the survey method of measurement, a quantity computation made from the surveyors’ notes of the surveys) out of 263 and criticized them as inaccurate and uncoordi-nate. Assuming arguendo, that the testimony was well founded, the counterclaim-ant has only himself to blame. An examination of the record shows that the surveys were taken by the government with two crews of five men each and by the plaintiff with two men, and- that plaintiff accepted the government’s survey records as conclusive when the latter paid plaintiff.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Aircraft Gear Corp. v. Kaman Aerospace Corp.
875 F. Supp. 485 (N.D. Illinois, 1995)
Johnson, Drake & Piper, Inc. v. State
41 Misc. 2d 804 (New York State Court of Claims, 1964)
Charles v. Judge & Dolph, Ltd.
111 F. Supp. 794 (N.D. Illinois, 1953)
Maryland Casualty Co. v. United States
169 F.2d 102 (Eighth Circuit, 1948)
E. J. Albrecht Co. v. New Amsterdam Casualty Co.
164 F.2d 389 (Seventh Circuit, 1947)

Cite This Page — Counsel Stack

Bluebook (online)
163 F.2d 16, 1947 U.S. App. LEXIS 3163, Counsel Stack Legal Research, https://law.counselstack.com/opinion/e-j-albrecht-co-v-new-amsterdam-casualty-co-ca7-1947.