Jefferson Hotel Co. v. Brumbaugh

168 F. 867, 94 C.C.A. 279, 1909 U.S. App. LEXIS 4513
CourtCourt of Appeals for the Fourth Circuit
DecidedMarch 12, 1909
DocketNos. 852, 888
StatusPublished
Cited by35 cases

This text of 168 F. 867 (Jefferson Hotel Co. v. Brumbaugh) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jefferson Hotel Co. v. Brumbaugh, 168 F. 867, 94 C.C.A. 279, 1909 U.S. App. LEXIS 4513 (4th Cir. 1909).

Opinion

DAYTON, District Judge.

The matter in controversy here arises under a building contract between Brumbaugh and the Jefferson Hotel Company for a part of the rebuilding of the Jefferson Hotel in Richmond, Va., which had been partially destroyed by fire. Jurisdiction in equity is acquired by reason of the bill setting up and seeking to enforce a mechanic’s lien against the property by the contractor for labor done and materials furnished under the contract. To the bill a number of subcontractors, who had filed mechanics’ liens as such, are made parties defendants. The contractor claims in his bill for a balance of contract price and for extra work performed. The hotel company defends because (a) of contract being uncompleted, (b) of denial of contractor’s claims for extras, and (c) of its own claim against the contractor for delays in completion of the contract within the time fixed by it. The contract was executed in duplicate in July, 1901 —the exact day is matter of dispute — and provides that the contractor was to furnish all labor and material necessary for the reconstruction according to plans and specifications .made by A. H. Elwood & Sons, architects, “who will also superintend the work”; that the work was to be completed on or before the 1st day of October, 1901, “excepting [870]*870delays caused by the party of the second part” — the hotel company— and in default of completion within the time fixed the contractor was to pay a penalty of $150 for each day of delay thereafter, and, on the other hand, he was to be paid a bonus of $150 for each day the contract might be completed prior to said October 1st. The contract price of $48,700 was to be paid from time to time as the work progressed upon estimates made by architects, with reservations of 20 per centum until the work was completed. The conditions of the plans and specifications material to this controversy are:

“Inspection: "Work and materials to be subject to inspection at all times by tbe superintendent. Should'the contractors refuse or neglect to remove work or material declared by the superintendent to be faulty within three days after having been notified in writing by the superintendent to so remove it, then the owner shall have the right to have such faulty work or material removed, and proper work or material substituted therefor, at the contractors' expense. Should the contractors refuse or neglect at any time during the progress of the building to supply a sufficiency of materials or workmen, or cause any unreasonable delay of the work, or fail or refuse to comply with any of the articles of agreement, including these specifications, the owner shall have the right to enter upon and take possession of the premises and provide materials and workmen sufficient to finish said work, after three days’ written notice, directed and mailed to the residence of or delivered personally to the contractors by the' owner, or by the superintendent.
“The expense of finishing said work to be deducted from the contract price.
“Changes: The owner reserves the right to make any changes that he may decree expedient during the progress of the work, without invalidating any agreements or contracts; but previous to any change being made the price of such change shall not be considered an extra unless written orders have been given therefor, and the price thereof stipulated in such order.
“Payments: Payments will be made during the progress of the work upon the estimates of the superintendent; twenty per cent, of the value of. all work done being always retained until the completion of the work and a final settlement has been made, after which a final estimate shall be made covering all balances due.
“Payments made during the progress of the work shall not be considered as an acceptance either of work or material, but the contractor shall be held to all the conditions of the contract until all the work is completed and accepted.
“Measurements: Scale measurements upon the drawings are never to be taken where figures for the same are given either in drawings or in specifications. .Shy discrepancy appearing between plans, details and specifications shall be referred to the architect for decision and in no case shall the work proceed in uncertainty, but the contractors shall apply to the architect who will supply'all further details or explanations as may be necessary for the full understanding of the work and such further details and directions shall be received and executed as a part of this contract.”

In addition to this contract, the hotel company awarded some 11 other independent contracts for elevator work, kitchen apparatus, cold storage, electric work, heating, plumbing, ventilation, machinery, tile and marble work, art and skylight glass, and for wrecking and removal of old walls.

The cause was referred to a special master, who was directed to ascertain and report (1) what amount, if any, was due to the plaintiff by the defendant under the contract; (2) what amounts, if any, were due subcontractors under mechanics’ liens filed by them; (3) all liens against the hotel company’s real estate; and (4) any other pertinent matter deemed necessarv by himself or required by the parties to be [871]*871staled. The special master took a large amount of testimony, and returned an elaborate report, to which exceptions were taken by both plaintiff and defendant hotel company. The plaintiff, however, withdrew his objections and now abides by the report, failing to perfect a cross-appeal taken by him. The defendant hotel company insisted upon its exceptions, but they were overruled by the court below, the master’s report in all respects was confirmed, and a decree entered holding the hotel company liable for a balance of $14,209.37 of contract price and for $13,881.13 for extra work done. From this decree the hotel company has appealed.

Meanwhile, on the same day this decree was entered, Meredith & Cocke and James L,. Harman, attorneys, filed their petition in the cause, alleging, in substance, that they were employed by Brumbaugh, the contractor, to enforce his mechanic’s lien .against the hotel company, for the benefit of his subcontractors, to the extent of some $28,-000; that, as to such subcontractors, Brumbaugh virtually acted in the capacity of trastee; that the sums found due by the master’s report were not sufficient by about 2 per cent, to pay the claims of such subcontractors; that Brumbaugh was bankrupt and nonresident of the state ; that they were entitled to reasonable fees as such attorneys, had a lien therefor upon the fund, that a large majority of the subcontractors had voluntarily admitted the existence of such lien, and had offered to pay them 15 per cent, of their claim in satisfaction thereof, which they were willing to accept, although insufficient, in friendly adjustment, inasmuch as such subcontractors had their own counsel, who had to be paid; that several of said subcontractors, however, declined to consent to such payment, wherefore they ask that ’he court decree them 15 per cent, of the claims of such subcontractors declining to pay. Upon this petition no process issued, but, by the decree complained of entered the same day this petition was filed, its prayer was granted, and 15 per cent, of the fund was awarded and decreed to them. Among the subcontractors whose claims were so decreed was one in favor of George Arents, assignee of the Richmond Woodworking Company.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Winmar, Inc. v. Al Jazeera International
741 F. Supp. 2d 165 (District of Columbia, 2010)
Service Steel Erectors Co. v. SCE, INC.
573 F. Supp. 177 (W.D. Virginia, 1983)
S.O.G.-San Ore-Gardner v. Missouri Pacific Railroad
658 F.2d 562 (Eighth Circuit, 1981)
San Ore-Gardner v. Missouri Pacific Railroad
496 F. Supp. 1337 (E.D. Arkansas, 1980)
J & J Electric, Inc. v. Gilbert H. Moen Co.
516 P.2d 217 (Court of Appeals of Washington, 1973)
United States v. Citizens & Southern National Bank
367 F.2d 473 (Fourth Circuit, 1966)
Fruin-Colnon International, S.A. v. Concreto, S.A.
231 F. Supp. 14 (District Court, Canal Zone, 1964)
Aetna Casualty & Surety Co. v. Board of Trustees
223 Cal. App. 2d 337 (California Court of Appeal, 1963)
Eastover Stores, Inc. v. Minnix
150 A.2d 884 (Court of Appeals of Maryland, 1959)
E. J. Albrecht Co. v. New Amsterdam Casualty Co.
163 F.2d 16 (Seventh Circuit, 1947)
Gogo v. Los Angeles County Flood Control District
114 P.2d 65 (California Court of Appeal, 1941)
Montgomery v. Karavas
114 P.2d 776 (New Mexico Supreme Court, 1941)
Schmoll v. United States
91 Ct. Cl. 1 (Court of Claims, 1940)
Wallace v. Fiske
80 F.2d 897 (Eighth Circuit, 1936)
State v. Commercial Casualty Insurance
248 N.W. 807 (Nebraska Supreme Court, 1933)
Camp Sales Corp. v. United States
77 Ct. Cl. 659 (Court of Claims, 1933)
Bethlehem Steel Co. v. United States
75 Ct. Cl. 845 (Court of Claims, 1932)
Snare & Triest Co. v. United States
75 Ct. Cl. 326 (Court of Claims, 1932)

Cite This Page — Counsel Stack

Bluebook (online)
168 F. 867, 94 C.C.A. 279, 1909 U.S. App. LEXIS 4513, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jefferson-hotel-co-v-brumbaugh-ca4-1909.