San Ore-Gardner v. Missouri Pacific Railroad

496 F. Supp. 1337, 1980 U.S. Dist. LEXIS 9356
CourtDistrict Court, E.D. Arkansas
DecidedJune 27, 1980
DocketLR-73-C-123
StatusPublished
Cited by3 cases

This text of 496 F. Supp. 1337 (San Ore-Gardner v. Missouri Pacific Railroad) is published on Counsel Stack Legal Research, covering District Court, E.D. Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
San Ore-Gardner v. Missouri Pacific Railroad, 496 F. Supp. 1337, 1980 U.S. Dist. LEXIS 9356 (E.D. Ark. 1980).

Opinion

MEMORANDUM OPINION

ROY, District Judge.

Some background information may be helpful in understanding the issues involved in this cause of action. Under the authority of Public Law 525, 79th Congress, July 24, 1946, 60 Stat. 634, the Government undertook the development of a multiple-purpose *1339 project known as the Arkansas River Project to improve the navigability of the Arkansas and White Rivers.

At all times material herein, the Missouri Pacific Railroad Company (Missouri Pacific or the Railroad) has been the owner and operator of a railroad bridge across the White River near Benzal, Arkansas, known as the Missouri Pacific Railroad Benzal Bridge. The Government, believing it to be necessary for the completion of the aforesaid project, entered into a contract with Missouri Pacific to rearrange and alter the Benzal Bridge on June 19, 1967. (“Government-Missouri Pacific Contract,” Pl. Ex. 5). The Government entered into similar contracts with four different railroads as a part of the Arkansas River Project, including two other contracts with Missouri Pacific relating to bridges known as the Baring Cross Bridge and the Junction Bridge.

The Government-Missouri Pacific Contract was subtitled “Cost Reimbursable,” meaning that the Government was obligated to reimburse “all reasonable and legitimate costs” incurred by the Railroad in arranging and altering the Benzal Bridge. The Government-Missouri Pacific Contract provided in substance that the Railroad would invite bids from construction contractors for the alteration of the Benzal Bridge pursuant to plans and specifications approved by the Government. For assistance in devising the plans and specifications, the Government entered into a contract with Sverdrup & Parcel and Associates, Inc., a consulting engineering firm. Subsequently, Missouri Pacific also contracted with Sverdrup & Parcel to provide engineering services during the performance of the alterations. After the Government approved the plans and specifications, Missouri Pacific issued invitations to twenty-eight contractors. Bids were let on August 28,1968, with only two bids submitted. San Ore-Gardner (S.O.G.) was the low bidder with a bid of $4,837,586.00, as compared to a bid of $5,436,365.00 from the other contractor. Both of these bids were considerably in excess of the $3,657,402.00 estimated by Sverdrup & Parcel. Sverdrup & Parcel later conceded that its estimate was too low, and that the higher bids were justified due to factors such as the high risk, low productivity and the remote and inaccessible site of the work.

S.O.G.’s bid was accordingly accepted, and Missouri Pacific entered into a contract with S.O.G. with regard to the work on November 5, 1968. (“Missouri Pacific-S.O.G. Contract,” Pl. Ex. 6).

After difficulties arose between the parties, this action was filed by plaintiff, S.O.G., against Missouri Pacific, defendant. The Court has jurisdiction of this suit by virtue of 28 U.S.C.A. §§ 1332 and 2201, and venue pursuant to 28 U.S.C.A. § 1391. S.O.G.’s amended and substituted complaint was filed January 8, 1975. In response to S.O.G.’s Amended and Substituted Complaint, Missouri Pacific moved to dismiss the case for lack of joinder of an allegedly indispensible party, the United States of America (“the Government”), acting through the Corps of Engineers, and alternatively to require plaintiff to make the Government a party to the suit. This Motion was overruled on September 9, 1975. Thereafter, and as a result of a pretrial conference herein on January 27, 1977, Missouri Pacific filed a Third Party Complaint against the Government and Travelers Indemnity Company, surety for S.O.G., on February 17, 1977.

By way of response, the Government moved to dismiss the Third Party Complaint on the grounds that this Court lacks subject matter jurisdiction and that, in any event, Missouri Pacific has failed to exhaust its administrative remedies. The Motion was granted dismissing the Government on March 3, 1980. 1 2

At a pretrial hearing the Court ordered a bifurcated trial of this cause, first as to the issues of liability and thereafter as to the *1340 amount of damages or adjustment if the parties were unable to agree thereon. The trial commenced on April 14, 1980 continuing through April 18, 1980. Excellent briefs have been submitted by the parties and the cause is now ready for determination on the issue of liability.

From the very beginning this construction project was fraught with many problems. Some of these problems were created by the parties’ own actions or inactions, and other problems by circumstances over which none of the parties had any control.

After reviewing the evidence adduced at the week-long trial, and also considering the many exhibits 3 introduced, the court has reached the conclusion that both sides were at fault to some extent.

The plaintiff’s main contentions are as follows:

The exchange of letters between Missouri Pacific and S.O.G. of June 13,1969 and July 14, 1969 constituted a new written agreement between the parties, as provided for in Paragraph 49 of the Missouri Pacific S.O.G. Contract; an implied term of the written agreement was that S.O.G. would recover all its increased costs as a result of the funding delay.

Plaintiff contends, alternatively, that if no new letter agreement was made between the parties, Missouri Pacific breached Paragraph 49 of the Missouri Pacific-S.O.G. Contract by failing to suspend the work upon learning of the lack of funding and consequently the Railroad is liable in damages for the increased costs incurred by reason of the breach.

Next plaintiff alleges that the imposition of a seasonal restriction on changeover and immobilization of the span by the Government after S.O.G. had entered into the Missouri Pacific-S.O.G. Contract constituted a material breach of the owner’s implied obligation not to hinder or delay performance. In this connection it is contended that both the Government and the Railroad failed to disclose to S.O.G. material information which would have affected S.O.G.’s position, i. e., receiving approval of the Coast Guard for a permit, the seasonal limitation on changeover, and immobilization of the span.

S.O.G. also claims damages because the Railroad allegedly breached its implied obligation not to hinder or delay S.O.G.’s performance by failing to timely apprise the Government of S.O.G.’s float-in and erection plans.

Finally plaintiff contends that the liquidated damage clause of the Missouri Pacific-S.O.G. Contract is unenforceable and 5.0. G. is entitled to the return of all moneys withheld by the Railroad as liquidated damage and to all moneys withheld by the Railroad on account of noise in the bearings.

The Railroad vigorously denies that any of plaintiff’s contentions have merit. The defendant Railroad specifically contends that under the terms of the contract between S.O.G. and Missouri Pacific the plaintiff is not entitled to any increased cost for delays at any stage of the construction.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
496 F. Supp. 1337, 1980 U.S. Dist. LEXIS 9356, Counsel Stack Legal Research, https://law.counselstack.com/opinion/san-ore-gardner-v-missouri-pacific-railroad-ared-1980.