General Insurance Co. of America v. Commerce Hyatt House

5 Cal. App. 3d 460, 85 Cal. Rptr. 317, 1970 Cal. App. LEXIS 1453
CourtCalifornia Court of Appeal
DecidedMarch 17, 1970
DocketCiv. 33861
StatusPublished
Cited by20 cases

This text of 5 Cal. App. 3d 460 (General Insurance Co. of America v. Commerce Hyatt House) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
General Insurance Co. of America v. Commerce Hyatt House, 5 Cal. App. 3d 460, 85 Cal. Rptr. 317, 1970 Cal. App. LEXIS 1453 (Cal. Ct. App. 1970).

Opinion

Opinion

HERNDON, J.—

Statement of the Case

Respondent General Insurance Company of America brought this action to recover money alleged to be due and owing from appellants upon a *464 written contract for the construction of a hotel building and related facilities and for extra work performed beyond that called for in the contract.

Respondent was the surety on the performance bond of Centron Construction Company, the original contractor. During the course of construction Centron defaulted and appellants demanded that respondent perform in conformity with the terms of its bond. Accordingly, respondent undertook performance of the contract. Defendants and appellants Commerce Hyatt House, a joint venture, and its components, Herman Investment Company, a copartnership, Hyatt Corporation of America, a corporation, and Burcru Realty Corporation, were the owners who contracted with Centron.

In its complaint respondent alleged that its principal had defaulted in the performance of the construction contract and that it had undertaken and completed performance by virtue of its obligations under the terms of the performance bond. Respondent further alleged in substance that by reason of the failure of appellants to pay the amount which remained due and owing under the contract as adjusted by the parties during the course of performance and appellants’ failure to pay for extra work authorized by them and not called for by the construction contract, there was a balance of $163,539.96 plus interest owing from appellants to respondent.

By their answer appellants denied that they were indebted to plaintiff and alleged that they were entitled to receive from respondent a complete accounting which had not been provided. The answer further alleged by way of counterclaim that appellants were entitled to $57,500 for liquidated delay damages, and the sum of $3,622.17 for additional architectural fees incurred by reason of the breach of the contract by respondent’s principal.

At the conclusion of the nonjury trial the court found that there was a balance due respondent on the adjusted contract price in the amount of $82,399 and that in addition respondent was entitled to recover $49,148.98 for extra work beyond that called for in the contract, the sum of $25,473.13 for overtime labor costs incurred at appellants’ request, and $14,798.69 as a reasonable allowance for overhead and profit on the cost of extra work and overtime labor. Respondent was awarded prejudgment interest on all of the sums found to be due except on the sum awarded for overhead and profit on the extra work and overtime items. The prejudgment interest awarded to respondent in the amount of $13,036.40, added to the other amounts above listed, totalled $184,856.20.

The court found that appellant's were entitled to credits and offsets in the sum of $22,123.69 by reason of items of work called for by the construction contract but not performed by respondent or its principal Centron. *465 On the basis of these findings judgment was rendered in favor of respondent in the net sum of $162,732.51.

Statement of Facts

The construction contract was executed by the parties thereto on November 26, 1962. The basic form of the contract was the “Standard Form of Agreement Between Contractor and Owner for Construction of Buildings” issued by the American Institute of Architects for use when a stipulated sum formed the basis of payment. The form is designated A.I.A. Document No. A-101, 1961 Edition.

By agreement of the parties the original contract was modified to provide that construction would be commenced on January 7, 1963, and that the work would be substantially completed on or before November 4, 1963. It is undisputed that the project was substantially completed on January 14, 1964, or 71 days later than the completion date agreed upon.

The contract provides that “if completion is delayed by general strikes, Act of God, general war or casualty beyond the control of the contractor then the time for completion will be extended for such additional time as shall be caused by such delay or as the architect may decide under Article 18 of the General Conditions of the contract.” Article 18 is entitled “Delay and Extensions of Time” and in pertinent part provides as follows:

“If the Contractor be delayed at any time in the progress of the work by any act or neglect of the Owner or the Architect, or of any employee of either, or by any separate Contractor employed by the Owner, or by changes ordered in the work, or by strikes, lockouts, fire, unusual delay in transportation, unavoidable casualties or any causes beyond the Contractor’s control, or by delay authorized by the Architect pending arbitration, or by any cause which the Architect shall, decide to justify the delay, then the time of completion shall be extended for such reasonable time as the Architect may decide.

“No such extension shall be made for delay occurring more than seven days before claim therefor is made in writing to the Architect. In the case of a continuing cause of delay, only one claim is necessary.”

The contract provided that in the event of unexcused delay in completion, the owners could deduct from the contract sum $500 per day for each day of delay. During the course of construction delays resulting from a variety of causes were encountered. Among the causes to which delays were attributable were the difficulties encountered in securing a sufficient number of plumbers. As the result of unusually heavy rains during the months of February and March of 1963, the construction site was flooded. The flood *466 waters created problems in getting trucks on and off the site; water and mud covered the footings and made it necessary to scrape the footings clean in order to continue the construction.

Delay also resulted from the default of Centron after its president, Robert A. Gray, absconded with more than $200,000 of its funds. Appellants point out that after Gray disappeared “there was practically nobody on the job and it took about four weeks to get the construction going again.”

An error in the drawings made by the County of Los Angeles showing incorrect street elevations necessitated corrective work in connection with the design and construction of an on-site sewer. Another cause of delay was a jurisdictional dispute between the plumbers and the carpenters over which trade would install prefabricated plaster shower stalls.

Other delays were caused by changes required by state and county agencies. The Los Angeles County Building and Safety Department required redesign and strengthening of the exterior wall studding of the hotel building. This change was ordered after the walls were approximately half completed and it caused a substantial delay. After the balcony railings had been installed, a State Industrial Safety Commission inspector required that additional rails be installed to prevent people from falling through the railings.

Additional delays were occasioned by changes ordered by the appellants. One such change involved an occupancy rating when the owners decided to permit dancing in the restaurant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Greg Opinski Construction, Inc. v. City of Oakdale
199 Cal. App. 4th 1107 (California Court of Appeal, 2011)
Calumet Construction Corp. v. Metropolitan Sanitary District
533 N.E.2d 453 (Appellate Court of Illinois, 1988)
Monsen Engineering Co. v. Tami-Githens, Inc.
530 A.2d 313 (New Jersey Superior Court App Division, 1987)
In Re Marriage of Buol
705 P.2d 354 (California Supreme Court, 1985)
Central Steel Drum Co. v. Gold Cooperage, Inc.
491 A.2d 49 (New Jersey Superior Court App Division, 1985)
Chesapeake Industries, Inc. v. Togova Entreprises, Inc.
149 Cal. App. 3d 901 (California Court of Appeal, 1983)
Marine Terminals Corp. v. Paceco, Inc.
145 Cal. App. 3d 991 (California Court of Appeal, 1983)
People v. Southern Pacific Co.
139 Cal. App. 3d 627 (California Court of Appeal, 1983)
Utica Mut. Ins. Co. v. DiDonato
453 A.2d 559 (New Jersey Superior Court App Division, 1982)
National Elevator Services, Inc. v. Department of Industrial Relations
136 Cal. App. 3d 131 (California Court of Appeal, 1982)
San Ore-Gardner v. Missouri Pacific Railroad
496 F. Supp. 1337 (E.D. Arkansas, 1980)
Nicholson-Brown, Inc. v. City of San Jose
62 Cal. App. 3d 526 (California Court of Appeal, 1976)
Buckley & Co., Inc. v. State
356 A.2d 56 (New Jersey Superior Court App Division, 1975)
Homes & Son Construction Co., Inc. v. Bolo Corp.
526 P.2d 1258 (Court of Appeals of Arizona, 1974)
Esgro Central, Inc. v. General Insurance
20 Cal. App. 3d 1054 (California Court of Appeal, 1971)
Nomellini Construction Co. v. State Ex Rel. Department of Water Resources
19 Cal. App. 3d 240 (California Court of Appeal, 1971)
Daugherty Co. v. Kimberly-Clark Corp.
14 Cal. App. 3d 151 (California Court of Appeal, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
5 Cal. App. 3d 460, 85 Cal. Rptr. 317, 1970 Cal. App. LEXIS 1453, Counsel Stack Legal Research, https://law.counselstack.com/opinion/general-insurance-co-of-america-v-commerce-hyatt-house-calctapp-1970.