Rockefeller Center Construction Corp. v. Sonoma v (In Re Sonoma V)

23 B.R. 789, 1982 Bankr. LEXIS 3442
CourtUnited States Bankruptcy Appellate Panel for the Ninth Circuit
DecidedAugust 27, 1982
DocketBAP No. NC-81-1178 VEK, Bankruptcy No. 1-80-00463, Adv. No. 1-80-0097
StatusPublished
Cited by13 cases

This text of 23 B.R. 789 (Rockefeller Center Construction Corp. v. Sonoma v (In Re Sonoma V)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Appellate Panel for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rockefeller Center Construction Corp. v. Sonoma v (In Re Sonoma V), 23 B.R. 789, 1982 Bankr. LEXIS 3442 (bap9 1982).

Opinion

OPINION

VOLINN, Bankruptcy Judge:

Sonoma V, a general partnership, was a developer of a shopping center known as the Sonoma Marketplace. Rockefeller Center Construction Corporation of California (Rockefeller), is a general contractor. So-noma V and Rockefeller entered into three contracts with respect to the Sonoma Marketplace: a contract executed on March 17, 1979, for site work; a basic building shell contract executed on March 13,1979; and a contract for tenant improvements signed on March 30, 1979. Sonoma chose Rockefeller after receiving bids from qualifying contractors.

Rockefeller appeals from a judgment of the Bankruptcy Court in favor of Sonoma V. Aside from Rockefeller’s claim to prejudgment interest on amounts Sonoma owed on the building shell and site work contracts, the issues in the instant appeal involve the tenant improvement contract.

I. FACTS

Rockefeller agreed to build the tenant improvements for a lump sum of $232,666. This amount was reduced to $192,166 by subsequent agreement, following removal of the fire sprinkler system. The parties used the standard “Stipulated Sum Contract” drafted by the American Institute of Architects. The tenant improvement contract was based upon a typical space of 1600 square feet with specified standard improvements. This was called the T-l. The standard materials were itemized on a unit price list which was attached to and made part of the tenant improvement contract. The parties intended that the unit price list be used when, and to the extent, that the actual tenant improvements varied from the standard T-l. When items were used which were not on the unit price list, Rockefeller was entitled to charge the cost of the item plus 15%. If more standard items were used, Rockefeller would be entitled to the price on the unit price list. Conversely, if changes from the T-l resulted in the reduction of items (i.e., toilets or lighting fixtures), or where different items were used, Sonoma was entitled to an adjustment in the base contract price reflecting the reduced cost.

Rockefeller began work on the tenant improvements in late September or early October, 1979. It continued to perform until March, 1980. At that time, it left the job. Rockefeller and some of its subcontractors filed liens against the project. The bank then refused to disburse further funds under the construction loan agreement. Mounting financial problems led Sonoma to file a voluntary petition for relief under Chapter 11 of the Bankruptcy Code on May 16, 1980.

Rockefeller filed a proof of secured lien claim in the amount of $412,130.30. Sono-ma filed a complaint objecting to Rockefeller’s failure to pay subcontractors and ma-terialmen who filed liens against the project, and for a set-off or damages incurred as a result of Rockefeller’s breach of *792 contract. After a lengthy trial, the court entered judgment on June 24,1981, in favor of Sonoma V for $248,937. This sum was reduced by amendment and stipulation to $156,546, which included damages for Rockefeller’s breach of the tenant improvement contract and attorneys’ fees for Sonoma V in the amount of $78,187.

II. ISSUES.

Rockefeller appeals this judgment, asserting that the evidence does not support the finding that it breached the tenant improvement contract; that it is entitled to receive the reasonable value of the improvements it made; that even if it did breach the tenant improvement contract, the breach did not proximately cause Sonoma to suffer damages; that Rockefeller should have been awarded prejudgment interest on liquidated claims Sonoma owed it for work performed under the site work and shell contracts; and that Sonoma is not entitled to attorney fees.

Rockefeller prefaces all of its arguments with the assertion that the trial court’s findings of fact and conclusions of law are clearly erroneous. These arguments are to be considered in the light of the following standards. Bankruptcy Rule 810 adopts Rule 52(a) of the Federal Rules of Civil Procedure which provides the standard of review with respect to a trial court’s findings of fact. Reversal is warranted only where the findings are clearly erroneous. “A finding is ‘clearly erroneous’ when although there is evidence to support it, the reviewing court on the entire evidence is left with the definite and firm conviction that a mistake has been committed.” United States v. United States Gypsum Co., 333 U.S. 364, 395, 68 S.Ct. 525, 541, 92 L.Ed. 746; Purex Corp. v. Procter & Gamble Co., 664 F.2d 1105 (9th Cir. 1981). The party seeking to reverse findings of fact of a Bankruptcy Court has the burden of demonstrating that the findings are clearly erroneous. A mere showing that the Bankruptcy Court could have reached another conclusion is not sufficient to warrant reversal. In re Huntington Ltd., 654 F.2d 578, 579 (9th Cir. 1981).

III. DOES THE EVIDENCE SUPPORT THE FINDING THAT ROCKEFELLER BREACHED THE TENANT IMPROVEMENT CONTRACT?

The most significant question Rockefeller raises involves the contract completion date for the tenant finish contract. Rockefeller asserts that the contract required the tenant finishes to be completed by November 1, 1979 and that thereafter, the contract became void and that it could bill Sonoma on whatever basis it chose. Rockefeller states that the “original contract price of $192,166 expired when the contract terminated on November 1, 1979.” Accordingly, Rockefeller argues, when Sonoma would not pay it $279,579 upon demand, on March 17, 1980, its abandonment was justified.

The trial court found that although November 1,1979, was a tentative target date, it was not the contractual termination date. Further, the court stated that “Rockefeller might have negotiated after November 1 with Sonoma for a reasonable adjustment of the base contract price”, and that “Sono-ma V had offered such an adjustment when the contract was made in the event that the tenant finishes were not completed by November 1.” But Rockefeller failed to take any reasonable steps to amend the contract and, in fact, led Sonoma to believe that the contract price was still in effect after November 1.

Under Article 3 of the tenant improvement contract, which is subtitled “Time of Commencement and Completion”, the following statements are found:

“Upon completion of building shell and not later than November 1, 1979.
Subject to Leasing Arrangements Per Construction Loan Agreement With Bank of America.”

Rockefeller prepared the contract and the president of Rockefeller, Charles Saunders, added the handwritten phrase “Subject to.... ” The shell work contract provided that the shell work would begin upon completion of the pad construction and that it would be completed by November 1, 1979. *793

Free access — add to your briefcase to read the full text and ask questions with AI

Related

ANTONIA ANDRADE-GARCIA
D. Nevada, 2021
In Re Nair
320 B.R. 119 (S.D. Texas, 2004)
Steffan v. Malakoff (In re Moore)
99 B.R. 27 (E.D. California, 1989)
Hein v. Bobbitt (In Re Hein)
60 B.R. 769 (S.D. California, 1986)
Johnson v. Righetti
756 F.2d 738 (Ninth Circuit, 1985)
In Re Johnson
756 F.2d 738 (Ninth Circuit, 1985)
Schlecht v. Alaska (In Re Schlecht)
36 B.R. 236 (D. Alaska, 1983)
Merced Production Credit Ass'n v. Sparkman
703 F.2d 1097 (Ninth Circuit, 1983)
Sparkman v. Sparkman
703 F.2d 1097 (Ninth Circuit, 1983)
In Re Banks
31 B.R. 173 (N.D. Alabama, 1982)
Fox v. Peck Iron and Metal Co., Inc.
25 B.R. 674 (S.D. California, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
23 B.R. 789, 1982 Bankr. LEXIS 3442, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rockefeller-center-construction-corp-v-sonoma-v-in-re-sonoma-v-bap9-1982.