Sinnott v. Schumacher

187 P. 105, 45 Cal. App. 46, 1919 Cal. App. LEXIS 322
CourtCalifornia Court of Appeal
DecidedDecember 16, 1919
DocketCiv. No. 3065.
StatusPublished
Cited by8 cases

This text of 187 P. 105 (Sinnott v. Schumacher) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sinnott v. Schumacher, 187 P. 105, 45 Cal. App. 46, 1919 Cal. App. LEXIS 322 (Cal. Ct. App. 1919).

Opinion

RICHARDS, J.

This is an appeal from a judgment in favor of the defendants and cross-complainants for the sum of $15,972 upon their cross-complaint against the plaintiff and the cross-defendant, Pacific Coast Casualty Company.

The action was one originally brought by the plaintiff against the defendants to recover the sum of $6,800.28, the alleged value of labor and materials furnished by said plaintiff to said defendants under a building contract- for the erection of a structure for said defendants at a cost of fifty thousand dollars. The plaintiff entered upon the performance of said contract and proceeded therewith up to a time when, according to his complaint, the first installment would be due and payable to him under his contract, and he alleges that after repeatedly demanding the payment of this installment so that he might be enabled to proceed with his work under said contract, but failing to receive any portion of the same, he abandoned work upon said building for that reason and gave notice of the rescission of said contract, and thereafter commenced this action in quantum meruit for the reasonable value of the work and materials supplied by him upon said building. The defendants answered, admitting *48 the making of said contract, but denying that any installment was due or payable to the plaintiff at the time of his abandonment of such contract and of his notice of rescission thereof. The defendants also filed a cross-complaint against said plaintiff and against the Pacific Coast Casualty Company, his bondsman under said contract, by which they alleged that the said plaintiff’s abandonment of his said contract and of the construction of said building was without cause, and that in consequence thereof said defendants were obliged to incur additional costs and expenses in the completion of said building amounting to a large sum, for which they prayed judgment upon their cross-complaint. The trial court found against the plaintiff upon his complaint and in favor of the defendants upon their cross-complaint, and thereupon rendered judgment against plaintiff and his said bondsman for the sum above stated. From such judgment the plaintiff and the cross-defendant, Pacific Coast Casualty Company, have taken this appeal.

The record in the case is quite voluminous, but the questions presented upon the appeal, when stripped of much of the involvement in their discussion in the elaborate briefs of counsel, would seem to be few and simple.

The first and in fact the main contention of the appellants is that a number of the findings of the court are not sufficiently supported by the evidence in the case. The first finding thus attacked is that portion of finding 10 which reads as follows:

“And the court further finds that said Bi chard Sinnott never at any time furnished to said owners or their architect any written report setting forth the exact or correct percentage of materials received at the building, or the exact or correct percentage of the work installed, but on the contrary demanded payment on and after the fourth day of December, 1914, for a percentage of work not installed and for a percentage of materials not received at the building far in excess of the actual percentage of work installed and materials received, to wit, for the sum of four thousand dollars or thereabouts.”

This finding is an essential one, in view of the provisions' of the contract between the parties, which contains the following stipulation:

*49 “On the first day of each month as the work progresses a sum equal to seventy-five per cent of the actual value of the materials and labor incorporated into the said building . . . the architect shall compute the amounts at the times when the payments become due . . . the contractor shall furnish to the architect at each time when payments become due a written report setting forth the exact percentage of the materials 'received at the building and the exact percentage of the work installed. ’ ’

We are unable to agree with the appellants’ first contention. The only evidence upon which the appellants rely as supporting their claim that the uneontradieted evidence shows that the plaintiff (contractor) did in fact comply with the terms of the foregoing clause in the contract between the parties, consists in certain letters which the plaintiff wrote to the defendants or their architect which contained the general statement “that the exact percentage as near as is possible to make it of the materials received at the building is eight per cent thereof, and the exact percentage of the work installed as near as is possible to make it is eight per cent thereof. I also notify you that there Is now due, owing, and unpaid to me as original contractor for the pro rata of materials received at the building, and the pro rata of the work installed, the sum of four thousand dollars, or eight per cent of the total contract price.” [1] It will be noted that the terms of the foregoing clause in the contract with which the appellants claim that the above-quoted matter amounts to a compliance, read as follows: “The contractor shall furnish to the architect at each time when payments become due a written report setting forth the exact percentage of the materials received at the building and the exact percentage of the work installed.” The purpose of requiring such a report from the contractor to be made to the architect is manifestly to enable the architect to correctly compute the amount of the installment which shall be due and payable to the contractor on the first day of each month as the work progresses; and it should require no argument to show that the mere general statement or conclusion of the contractor as to the percentage of materials received and work installed upon the building at the time he requires the installment payment upon the cost thereof does not *50 amount to a compliance with the foregoing provision of said contract.

But aside from this conclusion as to the sufficiency of the plaintiff’s showing in the above respect, the appellants contend that the contract between the parties requires the architect of the building to supply to the contractor upon demand a blank form upon which to make out and furnish the information as to the percentage of work done upon the building required by the foregoing clause in said contract, and that the architect supplied the contractor with the wrong blank form, which the plaintiff filled in with certain data which amounted to an insufficient compliance with the terms of the contract. Conceding this to be true, there is nothing in the evidence to show that the contractor, upon receipt of said blank form from the architect and upon his discovery that it was insufficient, ever applied to the architect, as the contract requires, for the proper form or blank, and the finding of the trial court in this respect which the-appellant assails is fully supported by the evidence in the record.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pacific Employers Insurance v. City of Berkeley
158 Cal. App. 3d 145 (California Court of Appeal, 1984)
Aetna Casualty & Surety Co. v. Board of Trustees
223 Cal. App. 2d 337 (California Court of Appeal, 1963)
Six Companies of California v. Joint Highway Dist. No. 13
24 F. Supp. 346 (N.D. California, 1938)
Laiblin v. San Joaquin Agricultural Corp.
213 P. 529 (California Court of Appeal, 1923)

Cite This Page — Counsel Stack

Bluebook (online)
187 P. 105, 45 Cal. App. 46, 1919 Cal. App. LEXIS 322, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sinnott-v-schumacher-calctapp-1919.