Six Companies of California v. Joint Highway Dist. No. 13

24 F. Supp. 346, 1938 U.S. Dist. LEXIS 1931
CourtDistrict Court, N.D. California
DecidedAugust 8, 1938
DocketNo. 20101-R
StatusPublished
Cited by4 cases

This text of 24 F. Supp. 346 (Six Companies of California v. Joint Highway Dist. No. 13) is published on Counsel Stack Legal Research, covering District Court, N.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Six Companies of California v. Joint Highway Dist. No. 13, 24 F. Supp. 346, 1938 U.S. Dist. LEXIS 1931 (N.D. Cal. 1938).

Opinion

ROCHE, District Judge.

This is an action for damages for breach of contract. It is submitted to the [347]*347court in the form of a cross-complaint, brought by the Joint Highway District No. 13, a public corporation of the state of California, hereafter called the District, against the Six Companies of California, a Nevada Corporation, licensed as a contractor in the State of California, and numerous foreign corporations, sureties on the Six Companies’ bond. Hereafter the Six Companies will also be referred to as the Contractor.

On July 1, 1936, litigation was begun by the Six Companies, which sought to recover $3,259,659.04, the balance claimed to be due for work done and materials furnished to the District. An answer and cross-complaint were filed by the District, which denied any indebtedness and set forth its own claims.

The District’s cross-complaint alleges that on June 4, 1934, the District, in accordance with its authority, entered into a contract with the Six Companies whereby the latter agreed to undertake a project for the construction of a highway and highway tunnels and to furnish a faithful performance bond to the District. The surety companies, which have been joined as cross-defendants, were made jointly and severally liable with the Contractor upon the bond.

The District further alleges as follows: On June 13, 1936, the Six Companies abandoned their work, which was then about 70% completed. The Six Companies claimed the right to rescind the contract on several grounds, which were set forth in the notice delivered to the District upon the cessation of work by the Contractor. The District promptly notified the Contractor and the surety Companies that they must proceed with their work; that if the job were not resumed, the District would have the project completed and would hold the Contractor and the sureties liable for the cost. Neither the Six Companies nor the sureties resumed construction and The District, after calling for bids, let contracts to other corporations for the completion of the work at a cost of $1,751,611.74.

The cross-complaint acknowledges that the District has retained $224,560.79, or 10% of the contract price for work done prior to May 1, 1936; that the District has in its possession an additional $265,891.82 for work performed by the Companies after May 1, 1936; that the District is holding $2,806.55 on behalf of the Companies for past work performed; that these three amounts total $493,259.16, from which sum must be deducted $10,000 retained by the District as liquidated damages, thus leaving a credit of $483,259.16. The District claims that the difference between the reasonable cost of completing the work and the contract price for the uncompleted work is $591,325.47. This sum, less the above mentioned $483,259.16 still retained for the Six Companies, leaves $108,066.31 as the reasonable cost of completing the work necessitated by the Six Companies’ default.

The District alleges that it became necessary for it (a) to protect and maintain the work at a reasonable cost of $47,944.-33; (b) to measure the work at a reasonable cost of $5,134.22; (c) to readvertise for bids at a reasonable cost of $1,862.45; (d) to procure insurance at a reasonable cost of $14,060.85. These sums total $69,001.85. Furthermore, it is alleged that there was a delay of 433 days in the completion of the work directly attributable to the delay and abandonment on the part of the Six Companies. This was a reasonable period for the District to take to complete the project. It is extremely difficult to estimate all of the damages caused by the delay in the completion of the work. Liquidated damages of $500 per day for this delay are asked by the District in accordance with #4(d) of the contract, which reads as follows:

“(d) Damages for Delay. — The Parties hereto expressly stipulate and agree that time is the essence of this contract. In case the work is not completed within the time specified in the contract or within such extensions of the contract time as may be allowed as herein provided, it is distinctly understood and agreed that the contractor shall pay the District as agreed and liquidated damages and' not as a penalty five hundred dollars ($500.00) for each and every working day which may elapse between the limiting date as herein provided and the date of actual completion of the work, said sum being specifically agreed upon as a measure of the damage to the District by reason of delay in the completion of the work; it being expressly stipulated and agreed that it would be impracticable to estimate and ascertain the actual damages sustained by the District under such circumstances, and the Contractor agrees and consents that the amount of such liquidated damages so fixed, shall be deducted and retained by-[348]*348the District from any money then due, or thereafter to become due, the Contractor.”

The District asks for a judgment against the Companies in the sum of $383,-568.16, based on the allegations of the reasonable cost of completing the work, less credits, plus interim expenditures, plus damages caused by delay.

The Contractor and the sureties, in their answer to the cross-complaint, allege that the District had breached the contract by failing to furnish lines and grades as required by the contract, by not granting the contractor an extension of time to complete the work, by deducting liquidated damages from a progress payment made to the Contractor by the District; and finally it is alleged that the District presented plans and specifications to the Contractor which were deceiving and misleading in that the Six Companies were led to believe that the ground to be encountered in driving the tunnels would be found to be self-supporting and require little timber re-inforcement during construction, but that actually the entire tunnels needed timber, thus causing the Contractor to do more excavation than planned and furnish more concrete than anticipated.

After a hearing, the Court ruled against the Six Companies on the common counts, and concluded that the plaintiffs were guilty of a breach of contract. Thus it follows that the District is entitled to relief on its cross-complaint and the only remaining question concerns itself with the amount of damages which must be awarded to the District.1 The problem may be stated as follows: When a builder breaches a contract by reason of an abandonment, and such a contract contains a liquidated damage clause, to what extent is the builder liable in damages?

There is no dispute as to the accuracy of the various damage figures presented by the District. But the Companies, assuming a breach of contract as found by the court, deny that they are liable for liquidated damages or for the interim expenditures. The Companies assert that the provision for liquidated damages can have no application to a delay occurring after the contract has been abandoned. They further maintain that even if the provision for liquidated damages is applicable, it must be held to be unenforceable because it is a penalty.

In support of the contention that a provision for liquidated damages is inapplicable to a situation in which delay occurs because of abandonment, the Companies rely chiefly upon two California cases, namely Bacigalupi v. Phoenix Bldg. & Construction Co., 1910, 14 Cal.App. 632, 112 P. 892, and Sinnott v. Schumacher, 1919, 45 Cal.App. 46, 187 P. 105. These cases hold that a plaintiff may sue for actual damages when a defendant has breached his contract, notwithstanding a liquidated damage clause in the agreement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pacific Employers Insurance v. City of Berkeley
158 Cal. App. 3d 145 (California Court of Appeal, 1984)
Westinghouse Electric Corp. v. County of Los Angeles
129 Cal. App. 3d 771 (California Court of Appeal, 1982)
Silva & Hill Construction Co. v. Employers Mutual Liability Insurance
19 Cal. App. 3d 914 (California Court of Appeal, 1971)
Clemente Construction Corp. v. P. T. Cox Contracting Co.
172 Misc. 904 (New York Supreme Court, 1939)

Cite This Page — Counsel Stack

Bluebook (online)
24 F. Supp. 346, 1938 U.S. Dist. LEXIS 1931, Counsel Stack Legal Research, https://law.counselstack.com/opinion/six-companies-of-california-v-joint-highway-dist-no-13-cand-1938.