Bacigalupi v. Phoenix Building & Construction Co.

112 P. 892, 14 Cal. App. 632, 1910 Cal. App. LEXIS 65
CourtCalifornia Court of Appeal
DecidedNovember 23, 1910
DocketCiv. No. 833.
StatusPublished
Cited by28 cases

This text of 112 P. 892 (Bacigalupi v. Phoenix Building & Construction Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bacigalupi v. Phoenix Building & Construction Co., 112 P. 892, 14 Cal. App. 632, 1910 Cal. App. LEXIS 65 (Cal. Ct. App. 1910).

Opinion

HALL, J.

Plaintiffs entered into a contract with the Phoenix Building and- Construction Company (which shall hereinafter be designated as the building company), for the construction of a building for the sum of $14,000. The Title Guaranty and Surety Company gave a bond to plaintiffs, in the sum of $3,500, as sureties for the performance of the contract by the building company. The building company did not complete said building or perform its contract, but abandoned the same. The plaintiffs brought this action against the building company and the surety company to recover damages in the sum of $3,500 for breach of the contract. The building company defaulted, but the surety company defended. The jury returned a verdict for plaintiffs for the sum of $3,300, for which judgment was entered.

1. Appellant’s first contention is that the complaint fails to state a cause of action, and that for that reason the court erred in overruling its demurrer to the complaint.

The point of the attack made by the demurrer, as indicated in appellant’s opening brief, is the alleged insufficiency of the allegation as to any damage caused plaintiffs by the failure of the building company to perform its contract.

The allegation of the complaint upon this point is as follows: “That the reasonable cost to complete said building, over and in excess of the contract price, was thirty-three hun *636 dred ($3,300) dollars.” The complaint also concludes with a prayer for judgment in the sum of $3,500.

It is urged that it does not appear that the building was ever completed according to the original plans and specifications, or that the reasonable cost to complete the building according to the original plans and specifications was $3,300, or any other sum.

So far as the attack by general demurrer is concerned, we think the allegation is sufficient. The words “said building” fairly mean the building as contracted for, and not a different building or building other than as contracted for. It clearly appears from the allegations of the complaint that the building company failed and refused to build said building, but that it abandoned the work and left the said building in an uncompleted condition, and refused to continue under its contract. The facts stated would sustain a judgment for damages, and in such a case it has been held that the demand in the prayer is a sufficient statement of the amount of damages sustained, as against a general demurrer (Riser v. Walton, 78 Cal. 490, [21 Pac. 362]). But however that may be, the most that can be said against the allegation of damage in the case at bar is that it is not as definite and certain as good pleading demands.

In this connection appellant in his reply brief calls attention to the fact that the allegation as to damage was attacked in the demurrer for uncertainty. It is perhaps sufficient to say that we are not called upon to notice points not presented by appellant in his opening brief, and only do so when cogent reasons are presented why the point was not made in the opening brief. Furthermore, in the case at bar the evidence showed that the building was in fact completed according to the original plans and specifications, and the jury specially found that the reasonable and necessary cost for so doing was $3,300. The appellant was thus not injured by the action of the court in overruling its demurrer for uncertainty. The allegation as to the reasonable cost of completing the “said building” was treated on the trial as an allegation as to the reasonable cost of completing the building according to the original contract, and the jury found $3,300 to be the reasonable and necessary cost of completing the building according *637 to the original contract. No reversible error was committed in overruling the demurrer.

2. Appellant’s second contention is that “Plaintiffs failed to prove any loss or damage for failure of the building company to carry out its contract. ’ ’

Under this head it is contended that although it was shown that the building was completed, it is not shown that it was completed in accordance with the original contract with the building company, and that though it was shown that it did in fact cost $3,300 more than the price fixed in the original contract to complete the building, it was not shown that this cost was a reasonable cost or price.

As to the first contention the evidence in the record does show that the building was completed in accordance witn the original contract.

Plaintiffs did prove that the actual cost for completing the abandoned contract was $3,300 in excess of the original contract price; that plaintiff received bids for completing the work, and gave the contract to complete the work to the lowest bidder, which brought the total to a sum $3,300 in excess of the original contract price. No witness testified in terms that the accepted bid was a reasonable price or represented the reasonable cost of completing the abandoned contract; but no objection was made to this evidence. No evidence was given that the reasonable cost of completing the building was less than what it actually cost plaintiffs to complete it, or that it could have been completed for any less amount. Under the circumstances the evidence was sufficient to prove the reasonable cost. In the absence of any evidence to the contrary it tended to prove the reasonable cost. The actual cost is some evidence of the value or reasonable cost. (Angell v. Hopkins, 79 Cal. 181, [21 Pac. 769]; Bunting v. Salz (Cal.), 22 Pac. 1132; Greenebaum v. Taylor, 102 Cal. 624, [36 Pac. 957]; Levy v. Scott, 115 Cal. 39, [46 Pac. 892].)

The appellant also claims that the original contract fixes the measure of damages. The clause relied on provides that, “Should the contractor fail to complete this contract and the work provided for therein within the time fixed for such completion ... he shall become liable to the owner for all loss and damages which the latter may suffer on account thereof, but not to exceed the sum of $5 per day for each *638 day said work shall remain uncompleted beyond such time for completion.”

Manifestly this clause has relation only to damages resulting from delay only, and has no bearing upon the measure of damages for an abandonment of the contract and failure to complete the work at all.

3. The action was not prematurely brought because brought before the building was completed. The cause of action accrued as soon as the building company abandoned the contract. (Taylor v. N. P. C. R. R. Co., 56 Cal. 317; Lawton v. Fitchburg R. R. Co., 8 Cush. (Mass.) 230, [54 Am. Dec. 753]; Cincinnati etc. Ry. Co. v. Village of Carthage, 36 Ohio St. 631.)

4. Appellant also contends that “Plaintiffs had no right to consider the contract of the building company abandoned, and to complete the building themselves.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cates Construction, Inc. v. Talbot Partners
980 P.2d 407 (California Supreme Court, 1999)
Pacific Employers Insurance v. City of Berkeley
158 Cal. App. 3d 145 (California Court of Appeal, 1984)
Gerwin v. Southeastern California Ass'n of Seventh Day Adventists
14 Cal. App. 3d 209 (California Court of Appeal, 1971)
Integrated, Inc. v. Alec Fergusson Electrical Contractor
250 Cal. App. 2d 287 (California Court of Appeal, 1967)
Meier v. Paul X. Smith Corp.
205 Cal. App. 2d 207 (California Court of Appeal, 1962)
Batter Building Materials Co. v. Kirschner
110 A.2d 464 (Supreme Court of Connecticut, 1954)
Oden Const. Co. v. HELTON
65 So. 2d 442 (Mississippi Supreme Court, 1953)
Pierce v. Wright
256 P.2d 1049 (California Court of Appeal, 1953)
Wood v. Moore
148 P.2d 91 (California Court of Appeal, 1944)
Six Companies of California v. Joint Highway Dist. No. 13
24 F. Supp. 346 (N.D. California, 1938)
Pearson v. Washingtonian Pub. Co.
98 F.2d 245 (D.C. Circuit, 1938)
County of Los Angeles v. Margulis
44 P.2d 608 (California Court of Appeal, 1935)
Milwaukee Building Co. v. Wetzel
270 P. 382 (California Court of Appeal, 1928)
Southern Pac. Co. v. Globe Indemnity Co.
21 F.2d 288 (Second Circuit, 1927)
Payne v. De Vaughn
246 P. 1069 (California Court of Appeal, 1926)
Troy v. Troy
238 P. 143 (California Court of Appeal, 1925)

Cite This Page — Counsel Stack

Bluebook (online)
112 P. 892, 14 Cal. App. 632, 1910 Cal. App. LEXIS 65, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bacigalupi-v-phoenix-building-construction-co-calctapp-1910.