National Contracting Co. v. Hudson River Water Power Co.

118 A.D. 665, 103 N.Y.S. 641, 1907 N.Y. App. Div. LEXIS 735
Appellate Division of the Supreme Court of the State of New York·Decided April 5, 1907·Published·Cited by 6 cases

Opinions

Clarke, J.:

The action was brought to recover damages' for the defendant’s alleged breach of contract for the construction of a dam and power plant upon the Hudson river, in the counties of Saratoga and Warren, at a place known as Spier Falls. The defendant, claiming that the breach of contract had been by the plaintiff, pleaded as a counterclaim its damages resulting from said breach.

Upon a former trial the plaintiff recovered a judgment for the ' sum of $554,680.43. Upon appeal to this court said judgment was reversed and a new trial ordered before another referee. (110 App. Div. 13,3.)

The learned referee upon the second trial, upon a record substantially similar, governed by the law and the interpretation of the facts as laid down by this court, dismissed the complaint. The court having held that the contract had been breached by the plaintiff and not. by the defendant, upon the former record, and the referee having reached the same conclusion upon this record, it follows [667]*667that the defendant was entitled upon its counterclaim to such damages as it was able to show were the direct consequences of said breach by- the plaintiff. The measure of damages in such a case is the difference between what the defendant would have had to pay to plaintiff under the contract, if the plaintiff had performed, and the actual cost to the defendant of completing the work, provided that the same was fair and reasonable.

“ A party to a contract which has been broken by the other has a right to fulfill it for himself as nearly as may be, but he must not do this unreasonably as regards the other party nor extravagantly.” (Sixth. Dam. [3d ed.] 268.)

“ The measxxre of damages for the breach of the defendant’s covenant was the reasonable cost of the work. The city could not pi'oceed in a reckless or extravagant manner, and charge the defendant for expenses unnecessarily or unreasonably incurred.” (Mayor, etc.,- of N. Y. v. Second Ave. B. B. Go., 102 N. T. 572.)

“The reasonable value of the work necessarily done * * *

to fully complete the contract according to the plans and specifications should have been deducted from the conti’act price.” (Powers v. Oity of Yonlcers, 114 N. T. 145.)

Although the point was not in any manner raised upon the trial before the referee, it is now suggested for the first time that the general rule of damages hereinbefore set forth does not apply. It is claimed that the contract itself in paragraph “ 0,” pi'ovides the measure of damages recoverable by the deféndant upon a breach by the plaintiff. This claim was not presented by the pleadings. The complaint asked damages “ not only in the value of the work done and materials and machinery purchased * * * but also in the amount of profits that it would have made if it had been permitted to proceed and carry out the terms and conditions of said contract.” The answer alleged abandonment and refusal to proceed by plaintiff and claimed damages by reason of the failure, neglect and refusal by the plaintiff to perform, and that defendant has been and will be put to great cost and expense in proceeding with the said dam. The reply denied each allegation of the fourth defense and counterclaim.

It does not seem that the provisions of paragraph “ O ” of the contract are applicable. That paragraph is as follows; “ The said [668]*668contractor further agrees that if the work to be done under this contract shall be abandoned, or if at any time the engineer shall be of the opinion, and shall so certify in writing to the company, that the said work is unnecessarily and unreasonably delayed, or that the said •contractor is wilfully violating any of the conditions or agreements of this contract, or is not executing said contract in good faith, or fails to show such .progress in the execution of the.work as will give reasonable grounds for anticipating its completion within the required time,-the said company shall have power to notify the said contractor to discontinue all work, or any part thereof, under this contract; and thereupon the said contractor shall cease to continue said work or such part thereof as the said company may designate, and the said company shall thereupon have the right at their discretion to contract with other parties for" the delivery or completion of all or any part of the work left uncompleted by said contractor, or for the correction of the whole" or any part of said work. And in case the expense so incurred by said company is less than the sum which would have been payable under this contract if the same had been completed by the said contractor, then the said contractor shall be entitled to receive the .difference; and in case such expense shall exceed the last said sum, then the contractor shall, on demand, pay the amount of said-excess to the said company, on notice from the said company of the excess so due; but such excess to be paid by the contractor shall not exceed the amount of the security for the performance of this contract.”

It will be noticed that that is an agreement on the part of the contractor. The contractor agrees that if it “ is wilfully violating any of the conditions or agreements of this contract or is not executing said contract in good faith,” etc., the company shall have power to notify it to discontinue all work and at'its discretion contract "with other parties for the delivery or the completion of all or any part of the work left uncompleted by said contractor..

The paragraph, it seems to me, conferred, a power upon the defendant which it could exercise if it wished, and the provisions of the paragraph became operative only upon the exercise of that power. It meant that if, upon the report of the engineer in charge, the water company was so dissatisfied with the manner in which the contracting company, was performing its contract that it notified it [669]*669to cease work and then made a new contract with another contractor, in the event that the new contract turned out to he more advantageous to the company than the old, the original contractor was to receive the difference; and if, on the other hand, it turned out less advantageous, the original contractor was to pay the difference up to $25,000. It was in the nature of a guaranty, on the part of the original contractor, that no other contractor could do the work for less than it had agreed to do it, and if any other contractor did so do the Work, the original contractor would pay the difference up to $25,000. But it was not in consequence of any notice to the contractor by the company to cease work that the plaintiff abandoned the job and the defendant did not exercise its discretion to make a new contract after such notice to the-plaintiff to cease work. There . was a total abandonment by the National Contracting Company. It quit the works ; it took away its tools;. it breached the contract; it was not ordered off the premises; no notice was given it to cease work; it walked out, as has been found, unreasonably and wrongfully. The water power company proceeded to do the work itself, and it distinctly notified the plaintiff that inasmuch as it had abandoned the work, the defendant considered the abandonment and refusal to proceed a. breach of contract, and it proposed at once proceeding with the work and would hold the plaintiff responsible for all damages which it would sustain from such breach of the contract by it. To that measure of damages, the plaintiff entered no protest or objection.

Free access — add to your briefcase to read the full text and ask questions with AI

National Contracting Co. v. Hudson River Water Power Co., 118 A.D. 665, 103 N.Y.S. 641, 1907 N.Y. App. Div. LEXIS 735 (N.Y. Ct. App. 1907).

118 A.D. 665 (National Contracting Co. v. Hudson River Water Power Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Smith Sand & Gravel Co. v. Corbin
173 P. 16 (Washington Supreme Court, 1918)
Mulcahy & Gibson, Inc. v. Pacific Coast Casualty Co.
79 Misc. 160 (City of New York Municipal Court, 1913)
Gay v. Hudson River Electric Power Co.
184 F. 631 (U.S. Circuit Court for the District of Northern New York, 1911)
Bacigalupi v. Phoenix Building & Construction Co.
112 P. 892 (California Court of Appeal, 1910)
Moses v. Autuono
56 Fla. 499 (Supreme Court of Florida, 1908)