Smith Sand & Gravel Co. v. Corbin

173 P. 16, 102 Wash. 306, 1918 Wash. LEXIS 951
CourtWashington Supreme Court
DecidedMay 9, 1918
DocketNo. 14434
StatusPublished
Cited by3 cases

This text of 173 P. 16 (Smith Sand & Gravel Co. v. Corbin) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Smith Sand & Gravel Co. v. Corbin, 173 P. 16, 102 Wash. 306, 1918 Wash. LEXIS 951 (Wash. 1918).

Opinion

Chadwick, J.

The appellant began an action against respondent in tie year 1912 to recover dam[307]*307ages for breach of contract, setting forth in its complaint three causes of action. In the course of two trials in the lower court and two appeals to this court, all but the first cause of action was eliminated. On the third trial, the respondent was allowed by the trial court to amend his answer by setting up a counterclaim as an additional defense to the appellant’s cause of action. A trial before a jury resulted in a verdict in favor of the respondent on his counterclaim in the sum of $1,330.13. From a judgment thereon, the appellant prosecutes this appeal.

The first contention of the appellant is, the cause having been twice tried and twice heard on appeal on pro tanto admissions as to the justice of appellant’s claim, the respondent was estopped to amend his answer for the purpose of a third trial. The prior appeals did not involve any question npon the first cause of action and defenses thereto, hence we are not controlled by the doctrine of “law of the case.” Nothing more is involved than the right to amend a pleading upon a retrial so as to present a new defense. The appellant founded his cause of action on the respondent’s breach of a written contract under which appellant was to be paid fifty cents per cubic yard for the excavation and removal of rock from certain land owned by the respondent, payments to be made in monthly installments of ninety per cent as the work progressed, and ten per cent to be retained until final settlement. The appellant began the removal of the rock about August 1, 1909, but the work not proceeding with the diligence desired by respondent, he gave various notices, between October 3, 1910, and March 24, 1911, to appellant to remove his equipment, charging the contract had come to an end by lapse of time. The contract itself set no time for performance and was, accordingly, subject to the rule of reasonable time. The respondent having [308]*308taken possession of the land and prevented the appellant from carrying on its contract, the appellant brought an action to recover damages for its alleged' breach, setting up that it had actually earned $4,468.40, on which it had been paid $1,279.80, leaving a balance due for rock theretofore excavated in the sum of $3,-188.60. The respondent admitted the sum of $1,352.70 to be due the appellant and offered to submit to a judgment for that amount.

After the cause had been twice tried on this issue, and remanded for new trial after appeal by reasons of errors on other phases of the case, the respondent interposed a counterclaim, setting up that he had been compelled to employ another contractor to do the work at an expenditure of $9,133.33, for which he demanded judgment against appellant. The appellant argues that the act of the respondent in going to trial, admitting in the answer indebtedness on his part, estops him from setting up a new defense on a retrial which virtually nullifies his prior admissions. While it is the rule that an answer containing admissions is not amendable so as to deny the admissions, such a question is not presented here. The amendment interposed by the respondent contains no denial of the admissions in his former answer, but merely sets up a counterclaim which, to the extent that it might be established, would operate by way of set-off, or possibly by way of judgment over, as against any right of recovery established by appellant on its cause of action.

' Our statute (Rem. Code, § 273), permits a defendant to “set forth as many defenses and counterclaims as he may have,” whether legal or equitable; and Id., § 303, authorizes the court to allow amendments to pleadings, a matter that we have repeatedly held as within the discretion of the court, whose action will be set aside only upon a showing of abuse of discretion. [309]*309That such amendments are permissible on a retrial upon remand from the supreme court is a well recognized rule in this state. Jones v. Western Mfg. Co., 32 Wash. 375, 73 Pac. 359; Interstate Savings & Loan Ass’n v. Knapp, 20 Wash. 225, 55 Pac. 48, 931. The defenses set up are not objectionable as being inconsistent, but are such as the law allows. The only inconsistency was the action of the respondent in proceeding to trial on one defense when he had another that he might have interposed at the same time. Whether the omission of this defense was due to motive or oversight is immaterial. There was no element of estoppel which would preclude his asserting any valid defense at any stage of the proceedings, provided due notice and opportunity to meet it were'given to the adverse party.

The next contention of appellant is addressed to the alleged error of the court in admitting certain evidence in support of the respondent’s counterclaim.

The record shows that, after the respondent had rescinded his contract with appellant because of the latter’s breach, he entered into a new contract with one Margolius to complete the work remaining unperformed by the appellant. The Margolius contract was a written one, stipulating for the same rate of pay as provided by the contract with the appellant. Margolius entered upon the performance of the contract, but later threatened to abandon it because he was losing money. The respondent thereupon made a new arrangement with Margolius to continue the work and agreed to pay him the actual cost. The rock removed by Margolius, according to the original contract price of fifty cents per cubic yard, would have been worth $6,450.50, but the amount paid by respondent to Margolius under the terms of their altered contract was $9,133.33, being $2,682.83 more than it would have cost [310]*310under the contract between appellant and respondent:

The appellant claims that the respondent had a valid, enforceable contract with Margolius for the sum of $6,-450.50, that any payment in excess of that sum was a voluntary payment, hence such excess payment was not chargeable as a natural consequence of appellant’s breach of contract, and the admission of such excess, in evidence and the submission of that item to the jury was error. In arriving at their verdict the jury took into consideration this excess payment of $2,682.83 more than appellant would have been entitled to for the completion of its contract, deducted therefrom the sum of $1,352.70, which the respondent had admitted as justly due the appellant, leaving a balance of $1,330.13, for which they rendered their verdict. If, under the law, the excess payment of $2,682.83 over the contract price was a voluntary one, its submission to the jury was erroneous. The only damages recoverable on a breach of contract are such as arise directly and unavoidably from the breach. Under the original contract between appellant and respondent the completion of the work as contracted for would have cost the respondent $6,450.50 in addition to the sum previously earned by the appellant. The contract between the respondent and Margolius called for a continuance of the work at the same price. Margolius refused to carry out the contract because it was a losing one to him. The respondent had his remedy on the contract of the third party to hold him for damages of the same character as his remedy against appellant. But respondent elected to make a new contract with Margolius, promising to pay him a greater sum. As between these two it was a valid contract, as recognized by our decision in Evans v. Oregon & Washington R. Co., 58 Wash. 429, 108 Pac. 1095, 28 L. R. A. (N. S.) 455.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Bartholomew
710 P.2d 196 (Washington Supreme Court, 1985)
Hackendorn Contracting Co. v. Johnstown City
123 A. 415 (Supreme Court of Pennsylvania, 1924)

Cite This Page — Counsel Stack

Bluebook (online)
173 P. 16, 102 Wash. 306, 1918 Wash. LEXIS 951, Counsel Stack Legal Research, https://law.counselstack.com/opinion/smith-sand-gravel-co-v-corbin-wash-1918.