Mulcahy & Gibson, Inc. v. Pacific Coast Casualty Co.

79 Misc. 160, 140 N.Y.S. 747
CourtCity of New York Municipal Court
DecidedJanuary 15, 1913
StatusPublished

This text of 79 Misc. 160 (Mulcahy & Gibson, Inc. v. Pacific Coast Casualty Co.) is published on Counsel Stack Legal Research, covering City of New York Municipal Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mulcahy & Gibson, Inc. v. Pacific Coast Casualty Co., 79 Misc. 160, 140 N.Y.S. 747 (N.Y. Super. Ct. 1913).

Opinion

Green, J.

This action is brought by the plaintiff against the defendant upon a bond or undertaking given by the defendant, a surety company, to the plaintiff, and which guaranteed the performance by the Bagge-Stillman Company of a certain contract for doing certain work made by it with the plaintiff. The Bagge-Stillman Company failed to complete its contract. Plaintiff was compelled to complete the contract, and expended in its completion the sum of $1,-748.20 in excess of the amount agreed upon by the Bagge-Stillman Company to do the work. If in this case plaintiff is entitled to recover it is conceded that plaintiff should have [162]*162judgment for the full amount claimed, with interest to date and costs. The defense interposed herein is that the plaintiff has failed to bring this action within the period limited hy the provisions of the bond or undertaking; that plaintiff has failed to join with the defendant the principal who executed the original contract for which defendant guaranteed performance, and that as by the terms of the undertaking these provisions were made conditions precedent to the right of recovery plaintiff is not entitled to judgment. The plaintiff in avoidance of these defenses has sought in its complaint to excuse the nonperformance of these conditions of the bond by alleging that the reason the action was not commenced within the period provided by the bond was because it was unable within the period designated to ascertain its damage, and that the reason the principal was not made a party defendant as therein also provided was because the principal was in bankruptcy. As dates are material in this case for the proper determination of the rights of the parties, as well as a clear understanding of their respective contentions, they may be stated to be as follows, and about which there is no dispute: The contract for the work which was executed between the plaintiff and the Bagge-Stillman Company was made August 24, 1911. The undertaking upon which this suit is brought was executed by the defendant October 5, 1911, and this guaranteed the performance of the work to be done under the contract dated August 24, 1911. On November 28, 1911, the receiver in bankruptcy of the Bagge-Stillman Company was appointed. On December 1, 1911, plaintiff gave three days’ notice under the contract to the Bagge-Stillman Company to complete the work, and about the same day gave notice to the receiver in bankruptcy to 1he same effect. On November 29, 1911, plaintiff notified defendant • of the principal’s default, and on December 8, 1911, notified defendant that, having given notice to both, they would complete the work, and proceeded so to do. On June 21, 1912, the work was entirely completed and this action was brought against the defendant on August 28, 1912. The time limit contained in the undertaking within which plaintiff might bring an action was six months after the first breach of the [163]*163contract, and in no event after the expiration of six months from the date of the completion of the work under said contract, and the question thus presented is, did plaintiff have until six months after the work was completed by plaintiff within which to bring its action, and did the bankruptcy of the principal excuse the plaintiff from making such principal or the receiver a party to the action, as required by the undertaking given by the defendant? The provisions of the undertaking material to the questions before the court are important and they are as follows: Notwithstanding that said contract is hereby referred to, this bond is nevertheless issued subject to the following express conditions, which shall be conditions precedent to the right of the obligee to recover hereunder. * * * Nine. Any suits at law or proceedings in equity brought or to be brought against the surety to recover any claim hereunder must be instituted within six (6) months after the first breach of said contract, and in no event shall any action or proceeding be brought against the surety hereunder after the expiration of six (6) months from the date of the completion of the work under said contract, and the principal shall be made a party to any suit or action and be served with process commencing the same, if the principal can with reasonable diligence be found, and no judgment shall be rendered against the surety in excess of the penalty hereof. None of the conditions or provisions contained in this instrument shall be deemed waived by the surety unless the written consent to such waiver be duly executed by its president or vice-president and its seal be thereto affixed and duly attested.” It is thus evident that if these provisions require that the action be brought within six months after the first breach of the contract the plaintiff cannot recover, for the first breach arose about December 1, 1911, and this action was not commenced until August 28, 1912, more than six months thereafter. If, however, the provision of the undertaking permits an action to be brought with six months after the completion of the contract by plaintiff, then plaintiff may recover, for the work was completed. June 1, 1912, and the action was brought August 28, 1912; .provided, however, that the bankruptcy of the principal obviated the neces[164]*164sit-y of making it a party to this action notwithstanding the tenor of the bond given by the defendant. This is substantially the third trial of the questions herein involved. At the first trial a motion to dismiss was made.and a mistrial for some reason was ordered. Thereafter a motion for judgment upon the pleadings was made by the defendant and denied, and is now on appeal. The third trial upon substantially the same questions is now before the court, submitted, however, to the court without a jury upon both the law and the facts. The provisions hereinbefore referred to were made conditions precedent to plaintiff’s right of action or recovery, and no argument is necessary to establish the proposition that they were reasonable, operative and binding upon the parties thereto. The undertaking provides, as hereinbefore set forth, that any suits at law or proceedings in equity brought or to be brought against the surety to recover any claim hereunder must be instituted within six months after the first breach of the said contract, and in no event shall any action or proceeding be brought against the surety hereunder after the expiration of six months from the date of the completion of the work under said contract.” The plaintiff insists that this clause should be interpreted to mean “ if the principal defaulted on his contract under ordinary circumstances' suit against his surety must be brought within six months after such default, and if the holder of the bond after the default completed the work, in that event suit must be brought within six months after completion of the work.” The defendant, on the other hand, contends that this clause has no application to a case like the one at bar, and that “ it applies to a case where after the contract has been finished the obligee discovers that the contract was not properly performed, and in such a case no recovery can be had unless the action is brought within six months after completion, so that if the obligee did not discover until after six months after completion that the contract was not properly performed it cannot recover.” I am of the opinion that as to the proper interpretation of the language of the bond the view of counsel for the defendant is correct, and consequently the clause of the bond or undertaking which inhibits the [165]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pargoud v. United States
80 U.S. 156 (Supreme Court, 1872)
Wilcox v. Equitable Life Assurance Society of the United States
65 N.E. 857 (New York Court of Appeals, 1903)
Whiteside v. North American Accident Insurance
93 N.E. 948 (New York Court of Appeals, 1911)
Mayor, Etc., of N.Y. v. . SEC. Ave. R.R. Co.
7 N.E. 905 (New York Court of Appeals, 1886)
Hoye v. . Pennsylvania R.R. Co.
83 N.E. 536 (New York Court of Appeals, 1908)
National Contracting Co. v. Hudson River Water Power Co.
118 A.D. 665 (Appellate Division of the Supreme Court of New York, 1907)
Phillips v. Schlang
139 A.D. 930 (Appellate Division of the Supreme Court of New York, 1910)

Cite This Page — Counsel Stack

Bluebook (online)
79 Misc. 160, 140 N.Y.S. 747, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mulcahy-gibson-inc-v-pacific-coast-casualty-co-nynyccityct-1913.