Milwaukee Building Co. v. Wetzel

270 P. 382, 93 Cal. App. 775, 1928 Cal. App. LEXIS 804
CourtCalifornia Court of Appeal
DecidedSeptember 7, 1928
DocketDocket No. 3388.
StatusPublished
Cited by4 cases

This text of 270 P. 382 (Milwaukee Building Co. v. Wetzel) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Milwaukee Building Co. v. Wetzel, 270 P. 382, 93 Cal. App. 775, 1928 Cal. App. LEXIS 804 (Cal. Ct. App. 1928).

Opinion

HART, J.

A petition for a rehearing was granted herein solely for the purpose of enabling us to give further consideration to the question whether the damages awarded by the judgment were, as counsel for the defendant vigorously contend is true, in excess in a material measure of the damages to which the evidence showed the plaintiff was entitled in consequence of the damage it actually sustained through defendant’s breach of his contract. After a more scrutinizing examination of the evidence addressed to that question than was given to it in our original investigation of the record, we have satisfied ourselves that counsel for the defendant are right in the statement in their petition that the evidence does disclose that the plans and specifications upon which the Bayer-Rothgeb Company successfully submitted its bid after the defendant abandoned his contract with the plaintiff for doing the work and furnishing' the materials called for by the said contract contained certain items which were not a part of the plans and specifications upon which the defendant submitted his bid and which increased the cost of the work and the materials over the cost thereof under the latter’s contract.

We adhere to the conclusion announced in the opinion originally filed herein as to the making of the contract between the plaintiff and the defendant and the refusal by the latter to perform the terms thereof, as alleged in the complaint. The judgment, however, must be modified in accord with our modified conclusion that the aggregate sum thereby allowed the Bayer-Rothgeb Company as damages for defendant’s breach of his contract is materially in excess of what the evidence shows it is entitled to. A more specific consideration of the evidence upon which the modification is predicated will be found in the body of the opinion. The following is the opinion heretofore filed herein, modified in accord with the foregoing considerations :

This is an action by the plaintiff to recover from the defendant damages for the alleged breach of a certain contract.

*778 Judgment passed for the plaintiff in the sum of $3,131, the amount prayed for in the complaint. The defendant moved for a new trial, the same being denied. This appeal is from the judgment upon a bill of exceptions.

The plaintiff, a corporation organized and existing in pursuance of the laws of California, prior to and at the time of the commencement of this action, was and is engaged in the business of general contractor for the erection and construction of buildings, with its principal place of business in the city of Los Angeles.

The defendant, Kurt 0. Wetzel, prior to and at the time of the commencement of this action, was doing business in said city under the fictitious firm name of K. 0. Wetzel & Co.

At some time prior to and at the time of the commencement of this action the plaintiff was, “and still is, engaged, as the general contractor, in the erection, building and construction of that certain building ... at No. 806 South Broadway, in the City of Los Angeles, commonly known as the Carleton F. Burke building, according to plans and specifications provided” in the contract for the erection and construction of the same. “Said plans and specifications provided for the furnishing and construction of . . . certain store fronts and iron doors to store and iron front, iron doors and iron grille on the wood doors to the building lobby and iron elevator doors for two passenger elevators and other iron work to be furnished in and about said premises.” On October 31, 1922, the defendant entered into a written agreement with plaintiff to furnish said iron or metal and to perform all work, labor, and materials necessary therefor, for the sum of $4,752, and further in said contract agreed to complete said work on or before the eighth day of February, 1923.

The complaint, from which the foregoing statement is taken, alleges that the defendant breached said contract by failing and refusing to comply with the terms thereof; that, in order to complete said building in compliance with the terms of its contract, the plaintiff “was forced to and did secure from other persons and firms engaged in the same line of business, to wit, in the furnishing of iron and metal work and doing labor with regard thereto, such as required by the plans and specifications to be followed by this *779 plaintiff, bids and estimates of the best price at which they would furnish the materials and do and perform the labor necessary to install the same as per the original agreement with the defendant; . . . that the lowest bid or estimate for said materials and work was the sum of $7,883.00; . . . that plaintiff has by its contract duly made become indebted in said sum for the iron and metal work which was to have been furnished by defendant under his said contract aforesaid.” It is alleged that by reason of the defendant’s failure to comply with and perform his said contract, the plaintiff has been damaged “in a sum equal to the difference between the sum of $7,883.00 and the sum of $4,752.00,” the first named sum being the amount which plaintiff was compelled to pay for the material and the work because of the defendant’s breach of his contract with plaintiff to furnish said material and work' and the last-named sum the amount defendant agreed to furnish said material and work for, the difference between said sums being the sum of $3,131. It is further shown by the complaint that the contract of plaintiff to erect said building provided that for its noncompletion within the time specified therein the plaintiff shall be penalized in the sum of $100 for every day until completed.

The defendant’s answer first specifically denies the material averments of the complaint and then sets up a special defense. The brief of counsel for the plaintiff correctly epitomizes the averments of said special defense, and we will, therefore, adopt the same herein, as follows:

“As a second and separate defense defendant alleged substantially that he had received requests for the submission of a bid for certain work, designated as Item No. 1 and Item No. 2, said request being accompanied by certain plans and specifications. That defendant submitted bids therefor, but that neither of said bids was ever accepted. The plaintiff delivered to defendant a certain ‘purchase order’ calling for defendant to ‘furnish and install complete ornamental wrought iron and cast iron front entrance and doors, except the lobby door and frame, which are omitted as per our plans and specifications and your bid 10/31/22, $2952.’ That said work order called for other and different work and material. That defendant returned said work order and requested that it be changed to conform to request for *780 bid, but that plaintiff refused to change said purchase order. That defendant was ready, willing and able to perform work called for in bid, and plans and specifications submitted to him at time of making, but plaintiff refused to allow him to so complete the contract. That as to Item No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Associated Lathing & Plastering Co. v. Louis C. Dunn, Inc.
286 P.2d 825 (California Court of Appeal, 1955)
Northwestern Sheet & Iron Works v. County of Sioux
36 N.W.2d 605 (North Dakota Supreme Court, 1949)
Alexander v. Walling
288 P. 138 (California Court of Appeal, 1930)

Cite This Page — Counsel Stack

Bluebook (online)
270 P. 382, 93 Cal. App. 775, 1928 Cal. App. LEXIS 804, Counsel Stack Legal Research, https://law.counselstack.com/opinion/milwaukee-building-co-v-wetzel-calctapp-1928.