Associated Lathing & Plastering Co. v. Louis C. Dunn, Inc.

286 P.2d 825, 135 Cal. App. 2d 40, 1955 Cal. App. LEXIS 1326
CourtCalifornia Court of Appeal
DecidedAugust 15, 1955
DocketCiv. 16455
StatusPublished
Cited by31 cases

This text of 286 P.2d 825 (Associated Lathing & Plastering Co. v. Louis C. Dunn, Inc.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Associated Lathing & Plastering Co. v. Louis C. Dunn, Inc., 286 P.2d 825, 135 Cal. App. 2d 40, 1955 Cal. App. LEXIS 1326 (Cal. Ct. App. 1955).

Opinion

PETERS, P. J.

Plaintiff, Associated Lathing and Plastering Company, brought this action against defendant, Louis C. Dunn, Inc., for breach of contract. Defendant denied that it had breached the contract, and by cross-complaint charged plaintiff with a breach, and sought damages for it. The trial court found that plaintiff in fact had breached the contract, and awarded defendant on its cross-complaint the sum of $1,678. Plaintiff and cross-defendant appeals.

Respondent, who was the general and the cement contractor for the construction of a hospital, solicited bids for the lathing and plastering work. Appellant, about the middle of April, 1952, was notified that it was the successful bidder. On May 1, 1952, respondent prepared the subcontract, and Mr. De-Angelis, president of appellant was notified to come to respondent’s office to sign it. Mr. DeAngelis failed to do so. On May 22,1952, respondent mailed the contract to appellant. The appellant made certain modifications, and the contract as modified was finally signed by both parties late in June of 1952.

Not only in securing appellant’s signature on the contract, but in other ways respondent had difficulty in securing appellant’s cooperation. On May 8, 1952, respondent, by *43 letter, requested from appellant certain priority materials information required by the federal government, requesting an immediate reply so that appellant could be issued a job priority rating. Receiving no reply over a period of time, an officer of respondent telephoned to appellant at least six times unsuccessfully seeking the information. The requested information was not received until October 22, 1952, in a letter dated October 20, 1952, but postmarked 7:30 p. m., October 21st. These dates are important, because, as will later appear, respondent terminated the contract during the day of October 21, 1952.

On September 10, 1952, respondent by letter requested appellant to send it, not later than September 15th, certain price information on the cost of some changes contemplated by the architects. This information was not furnished to respondent prior to the date respondent terminated the contract, October 21, 1952.

The dispute that finally led to the termination of the contract was over the installation of certain wire hangers from which the suspended ceilings were to be hung. On October 14, 1952, respondent notified appellant to install these hangers so as not to delay the pouring of the concrete, scheduled for October 21, 1952. On October 17, 1952, appellant, by letter, took the position that, under the contract, these hangers were to be installed by the cement contractor. On October 20th an officer of respondent phoned DeAngelis, and the two had an argument over whose duty it was to install the hangers. DeAngelis promised to give a definite answer the next day. He did not do so, and, on October 21, 1952, the officer of respondent phoned DeAngelis and requested an answer. DeAngelis stated that appellant would not install the hangers because that was the duty of the concrete contractor. De-Angelis then talked to the president of respondent who asked DeAngelis if he was going to install the hangers. When DeAngelis stated that appellant would not do so, the president of respondent stated: “All right, if that is your attitude, or if that is the way it is, your contract is hereby cancelled.”

The refusal of DeAngelis was apparently not absolute. He testified that he told the officers of respondent that even though it was not his job he was willing to install the hangers if the parties could discuss later whether appellant would be entitled to extra compensation for the work. With some qualifications, this conversation is admitted by respondent.

*44 On the same date as the oral termination, October 21, 1952, respondent sent appellant a registered letter, stating, in part:

“. . . Since the start of the job we have had no cooperation from your office. We have tried in vain to obtain the following information.
“1. Priority data.
‘ ‘ 2. Prices on change orders as listed in letter of September 10, 1952.
“Recently we informed you to start your work on the hanging wires, but have been informed that you do not intend to do the work. We are, therefore, giving you notice that your contract has been broken and is now void. We are making arrangements to have this work performed by others. ’ ’

Two days later, on October 23, 1952, appellant wrote to respondent, in part, as follows:

“Realizing that an authoritative ruling on this disputed question cannot be had immediately, we propose that you furnish us with a letter permitting us to do this work without prejudice to our rights to recover, in addition to the contract price, the reasonable value of the labor and materials required to take care of the disputed work.
“By so doing, you, of course, would not waive the right to make the same contention that you now make and we would not waive our rights under the contract . . .
“If you will . . . agree ... we will proceed forthwith with the disputed work.”

On October 22, 1952, respondent had entered into a contract with the lathing contractor who had submitted the second lowest bid, which contract provided for a price $1,678 higher than appellant’s contract. Accordingly, on October 25, 1952, respondent’s attorneys answered appellant’s letter of October 23, 1952, by stating that, because appellant had repeatedly breached its contract, it had caused respondent to incur substantial damages because of the delay, and had caused additional expense in that respondent, to avoid further damage, had been compelled to make other arrangements at increased cost for the lathing and plastering work. The letter notified appellant that respondent intended to hold appellant strictly accountable for these damages.

DeAngelis testified that the cost of installing the hangers would be about $3,500. The total lathing subcontract was for nearly $140,000.

Appellant thereupon brought this action for breach of *45 contract and respondent cross-complained for its damages caused by the alleged breach by appellant. The trial court, in substance, found that under the contract the obligation of installing the hangers was that of appellant; that appellant had failed to install the hangers, and had repudiated its contract; that appellant had repeatedly neglected, failed and refused to comply with its duty as a subcontractor to cooperate with the general contractor, a duty found to exist by custom and usage in this area; that respondent as a result of these breaches by appellant was compelled to enter into a contract with another plasterer at a higher price to respondent’s damage in the sum of $1,678.

The first question presented is whether the subcontract imposed on appellant the obligation to install the challenged hangers. The trial court permitted parol testimony on this issue and based thereon, and on the terms of the contract, ruled that the obligation was that of appellant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Busby Family, LLC v. Zervos CA4/3
California Court of Appeal, 2022
Singleton v. Friedberg CA4/1
California Court of Appeal, 2020
Schellinger Brothers v. Cotter
2 Cal. App. 5th 984 (California Court of Appeal, 2016)
Thee Aguila v. ERDM CA2/5
California Court of Appeal, 2016
Galeb Paving v. D.L. Falk Construction CA1/2
California Court of Appeal, 2014
530 Hewitt Subsidiary v. P.G.C.A. Holdings CA2/8
California Court of Appeal, 2014
Tutor-Saliba-Perini J v. v. LA Co. MTA CA2/7
California Court of Appeal, 2014
Unicom Systems, Inc. v. Farmers Group, Inc.
405 F. App'x 152 (Ninth Circuit, 2010)
Denver D. Darling, Inc. v. Controlled Environments Construction, Inc.
108 Cal. Rptr. 2d 213 (California Court of Appeal, 2001)
Hayter Trucking, Inc. v. Shell Western E & P, Inc.
18 Cal. App. 4th 1 (California Court of Appeal, 1993)
Superior Motels, Inc. v. Rinn Motor Hotels, Inc.
195 Cal. App. 3d 1032 (California Court of Appeal, 1987)
Kelsey v. Nagy
410 N.E.2d 1333 (Indiana Court of Appeals, 1980)
Easton Theaters v. WELLS FARGO, ETC.
401 A.2d 1333 (Superior Court of Pennsylvania, 1979)
Easton Theatres, Inc. v. Wells Fargo Land & Mortgage Co.
401 A.2d 1333 (Superior Court of Pennsylvania, 1979)
Weeshoff Construction Co. v. Los Angeles County Flood Control District
88 Cal. App. 3d 579 (California Court of Appeal, 1979)
Penn Security Life Insurance v. Rising
62 Cal. App. 3d 302 (California Court of Appeal, 1976)
Pennel v. Pond Union School District
29 Cal. App. 3d 832 (California Court of Appeal, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
286 P.2d 825, 135 Cal. App. 2d 40, 1955 Cal. App. LEXIS 1326, Counsel Stack Legal Research, https://law.counselstack.com/opinion/associated-lathing-plastering-co-v-louis-c-dunn-inc-calctapp-1955.