Weeshoff Construction Co. v. Los Angeles County Flood Control District

88 Cal. App. 3d 579, 152 Cal. Rptr. 19, 1979 Cal. App. LEXIS 1315
CourtCalifornia Court of Appeal
DecidedJanuary 2, 1979
DocketCiv. 52771
StatusPublished
Cited by13 cases

This text of 88 Cal. App. 3d 579 (Weeshoff Construction Co. v. Los Angeles County Flood Control District) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Weeshoff Construction Co. v. Los Angeles County Flood Control District, 88 Cal. App. 3d 579, 152 Cal. Rptr. 19, 1979 Cal. App. LEXIS 1315 (Cal. Ct. App. 1979).

Opinion

Opinion

HASTINGS, J.

This appeal by the Los Angeles County Flood Control District arises out of a judgment granting damages to Weeshoff Construction Company in the amount of $31,781 for extra work performed during the execution of a construction contract.

The district now appeals the judgment, contending damages were improperly awarded. It claims: (a) there was no change in the original contract which required additional compensation for the plaintiff; (b) even if contractual change did occur, the district’s failure to issue a written change order in accordance with the contract’s “Change in Work” provision protected it from the court’s finding that a change order had been issued; and even if a change had been ordered, plaintiff’s failure to *583 comply with the “Extra Work” clause relieved the district of an obligation to pay plaintiff for costs incurred; and (c) even if a change order was issued and plaintiff was entitled to extra compensation, this compensation was improperly calculated by the court.

On or about May 9, 1972, the district advertised for bids for the construction and installation of a storm drain project in Pico Rivera. The district provided the project plans and specifications and administered the final contract. A portion of the project involved construction on Whittier Blvd., a state highway. The state required and the contract specified that during construction on Whittier Blvd. three traffic lanes were to be maintained during morning and evening commuting hours. The contract also included a state requirement prohibiting the use of temporary resurfacing on state highways.

While preparing a bid for this project, plaintiff’s president Gerard Weeshoff concluded that the requirement to keep three traffic lanes open would not be feasible in some areas of Whittier Blvd. unless parts of the district’s plans were altered. He considered submitting a letter concerning this problem with his bid, but was informed by a district engineer that he would be disqualified if he did so. He bid the job assuming that, after the contract was awarded, either the three-lane requirement would be reduced to cover only two lanes, or that the specifications would be changed such that by moving the project a few feet, three lanes could be adequately maintained. Mr. Weeshoff testified that his bid included costs for keeping three traffic lanes open, but only if specifications were altered as indicated. Because of the contract’s prohibition against using temporary resurfacing on state highways, he did not include in his bid a cost for using temporary pavement on Whittier Blvd.

Plaintiff was low bidder on the project and was awarded the contract on or about June 20, 1972. Shortly after entering the contract, in July 1972, plaintiff proposed to the district that the construction line on Whittier Blvd. be moved four to five feet and that a ninety-six-inch pipe be substituted for the reinforced concrete box conduit. He believed these alterations would enable him to safely maintain three traffic lanes during commuting hours. On August 2, after several meetings during which plaintiff’s request was denied, plaintiff resubmitted his proposal in a letter to the district. The district again refused his request, this time by a letter dated August 9, 1972,

*584 In February 1973, plaintiff began construction of a sewer crossing on Whittier Blvd. Mr. Thomas Russi, senior construction specialist and senior site inspector for the project, testified that shortly after plaintiff began this sewer construction, plaintiff requested permission from the district to use temporaiy pavement at the intersection of Whittier and Rosemead in order to expedite construction. Having obtained the state’s agreement, the district allowed the contractor to place temporaiy pavement on the condition that permanent reserves be moved in within five days. According to plaintiff, he did not request but was ordered by the district to use temporaiy pavement at this intersection. Plaintiff felt this was due to newly expressed state requirements for temporaiy resurfacing in this area. Plaintiff did introduce as evidence a January 17, 1973, entiy from the diary of Mr. Russi which stated, “M. J. Clark gave me [a] letter [from the State Engineer’s Office] authorizing the use of temporaiy pavement at certain areas on Whittier Boulevard, gave same to Mr. Miller.” In a letter dated February 20, 1973, plaintiff requested that the district issue a written change order which would authorize compensation. for the extra cost of laying the temporaiy pavement. No change order was issued and no extra payment was authorized.

In April 1973, plaintiff had begun work on a portion of Whittier Blvd. west of Rosemead Blvd. At this point, problems arose concerning the maintenance of three traffic lanes during commuting hours. Plaintiff had maintained these lanes by means of a hard sand compact, but this material did not satisfy the district. On April 19, 1973, plaintiff was given a written memo stating he had failed to maintain three traffic lanes and directing him to restore these lanes as required by contract. Plaintiff responded that he had restored the lanes in accordance with contract specifications, but the district declared the sand to be an inadequate material for safe traffic lane restoration. (Mr. Russi testified that during this period, the contractor had experienced a cave-in and the district felt that although sand was a sufficient material to support some traffic, it wás not suitable for heavy traffic.) When plaintiff inquired of the district how he should restore the lanes, the district refused to give specific responses, but continued to order plaintiff to “fix” his lane restoration.

At about the same date, plaintiff received a letter from the district, dated April 20, which restated its position with regard to plaintiff’s alleged failure to comply with contract terms because of inadequate traffic lane maintenance; it also stated: “If by April 22, 1973, you have not restored the street surface sufficiently to provide for the traffic *585 requirements, the District will commence such restoration operations, the cost of which shall be borne by you. In addition, should you continue operations causing noncompliance with the specifications or should you fail to immediately proceed with the work in a satisfactoxy manner and in compliance with the specifications, the District will request that the Board of Supervisors serve notice upon you and your surety demanding compliance as provided in the specifications, Subsection 6-4, ‘Default by Contractor.’ ” On April 22, the district placed approximately 18 tons of temporary resurfacing material on Whittier Blvd., and on January 11, 1974, the district informed plaintiff that a sum of $758.65 was being deducted from his final payment to compensate the district for this act. Thereafter, plaintiff restored traffic lanes on Whittier Blvd. by means of temporary pavement. Plaintiff testifed that because of the strong position taken by the district, he felt temporary restoration was required in order to avoid forced termination of the project, withholding of payment, and a possible claim for breach of contract and damages.

On May 10, 1973, in a request similar to that submitted in July and August of 1972, plaintiff again submitted a written request to the district for authorization to alter the specifications for work on Whittier Blvd.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Swan Engineering v. Tuscan Ridge Associates CA3
California Court of Appeal, 2025
Silbermann v. Shangri-La Construction CA2/7
California Court of Appeal, 2020
G. Voskanian Construction, Inc. v. Alhambra Unified School District
204 Cal. App. 4th 981 (California Court of Appeal, 2012)
P&D Consultants, Inc. v. City of Carlsbad
190 Cal. App. 4th 1332 (California Court of Appeal, 2010)
Schram Construction, Inc. v. Regents of University of California
187 Cal. App. 4th 1040 (California Court of Appeal, 2010)
Ariza v. Autonation, Inc.
317 F. App'x 662 (Ninth Circuit, 2009)
Aceves v. Autonation, Inc.
317 F. App'x 665 (Ninth Circuit, 2009)
KATSURA v. City of San Buenaventura
65 Cal. Rptr. 3d 762 (California Court of Appeal, 2007)
Miller v. United States (In Re Miller)
253 B.R. 455 (N.D. California, 2000)
Roth v. Department of Veterans Affairs
110 Cal. App. 3d 622 (California Court of Appeal, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
88 Cal. App. 3d 579, 152 Cal. Rptr. 19, 1979 Cal. App. LEXIS 1315, Counsel Stack Legal Research, https://law.counselstack.com/opinion/weeshoff-construction-co-v-los-angeles-county-flood-control-district-calctapp-1979.