Frank T. Hickey, Inc. v. Los Angeles Jewish Community Council

276 P.2d 52, 128 Cal. App. 2d 676, 1954 Cal. App. LEXIS 1520
CourtCalifornia Court of Appeal
DecidedNovember 12, 1954
DocketCiv. 20216
StatusPublished
Cited by31 cases

This text of 276 P.2d 52 (Frank T. Hickey, Inc. v. Los Angeles Jewish Community Council) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Frank T. Hickey, Inc. v. Los Angeles Jewish Community Council, 276 P.2d 52, 128 Cal. App. 2d 676, 1954 Cal. App. LEXIS 1520 (Cal. Ct. App. 1954).

Opinion

VALLÉE, J.

Appeal by defendants from a judgment in favor of plaintiff for money and for a decree of foreclosure of a mechanic’s lien. The dispute involves charges made by plaintiff for claimed extra labor, material, and equipment furnished under a subcontract with defendant Contracting Engineers Company for the construction of a building for defendant Los Angeles Jewish Community Council.

On May 2, 1950, defendant Contracting Engineers Company, a partnership, as general contractor, and defendant Los Angeles Jewish Community Council, a corporation, as owner, entered into a contract for the construction of the Jewish Community Council Building on the corner of Vermont and Clinton Avenues, in Los Angeles. The building was to consist of two wings, one on Vermont and one on Clinton, with a rotunda connecting the two. On May 15, 1950, plaintiff, a corporation, and the general contractor entered into a subcontract whereby plaintiff agreed for $31,200 to: (1) remove trees, except those designated by the architect; (2) remove foundations from temporary buildings and old concrete residences; (3) demolish and remove walls, walks, and paving from the site; (4) excavate by machine for the building, including footings; (5) excavate and grade to *680 one-tenth foot, plus or minus, for parking area (the parties agree this meant 10 inches); and (6) stockpile material for backfill and haul remainder away. The subcontract provided: “Unit Price for Machine Excavation $.90 per cu. yd. Unit Price for Machine Back Fill $.45 [per cu. yd.].” The parties contemplated and plaintiff computed its bid for the job on the basis that the dirt needed for the backfills would be excavated from the site, that more dirt would be excavated than would be needed for the backfills, and that the excess would have to be hauled away.

The subcontract provided: “No modification of the contract price shall be made and no work of lesser value than that called for in the plans and specifications shall be accepted, except upon written change order signed by one of the partners of the contractor.” It also stated that the subcontractor waived any and all claims on the general contractor for damages for any act, omission or delay caused by the contractor, the owner, or any other subcontractor, and undertook the work subject to all conditions as they then existed or may arise. The plans and specifications were incorporated by reference into the subcontract. The prime contract provided for completion of construction in 11 months. Plaintiff commenced work on May 22, 1950, but because of delays— not due to its fault—it was unable to complete the job until November 30, 1951, 18 months later.

Nine temporary buildings were located on the premises and walks connected them. Plaintiff was not told by what particular date the buildings would be removed. They remained on the premises during the greater part of the time that construction was going on. Community Council used the property during the entire period and continued the operation of its business as a community center without interruption ; only when it was able to move into the new building were seven of the older buildings and the walks demolished.

On October 31, 1951, plaintiff billed the general contractor (Invoice 9475) for $1,350—removing 900 cubic yards from the site at the rate of $.90 a cubic yard plus $.60 a cubic yard for extra distance the dirt had to be hauled—claimed to be extras. On November 30, 1951, plaintiff billed the general contractor (Invoice 9489) for $2,700—hauling 3,000 cubic yards to the site between July 31 and September 13, 1950, at $.45 a cubic yard, $1,350, and removing an equal amount from the site in November 1951, at $.45 a cubic yard, $1,350— claimed to be extras. On December 4, 1951, plaintiff billed *681 the general contractor (by letter) for five items of extras totaling $3,422.69—(1) increase in labor, $95.15; (2) increase in dump truck rentals, $919.39; (3) increase in shovel and truck crane rental rates, $313.15; (4) additional cost of tree removal, $295; (5) additional charge for removing the 3,000 cubic yards of material set forth in Invoice 9489 because of extra distance to disposal area, $.60 a cubic yard, $1,800.

On December 26, 1951, the general contractor recorded his notice of completion. On January 23, 1952, plaintiff filed a mechanic’s lien for $8,841.50. On February 1, 1952, the general contractor tendered plaintiff a cheek for $1,310.53 1 in full satisfaction, which was refused by plaintiff and returned.

On April 21, 1952, plaintiff brought this suit for $8,841.50 and foreclosure of its mechanic’s lien.

Defendants denied that plaintiff had performed labor and furnished equipment as extras in any sum greater than $890.12, which had been paid. They alleged plaintiff did not, before performing the items of alleged extra work, secure a written order signed by the Community Council, bearing the approval of the architect and the acceptance endorsement of the general contractor, as required by the specifications.

Defendants also pleaded a counterclaim alleging that the following work was not performed and materials and equipment were not furnished by plaintiff as required by the subcontract: (1) the removal of all top soil from the building site and its storage in separate piles, $300; (2) the failure to strip the existing surface for the parking area to a depth of 10 inches, $2,600; (3) the removal of approximately 25 lineal feet of the retaining wall at the southwest corner of the property, $250; (4) removal from the site of approximately 2,171 cubic yards of excavated materials, $976; (5) failure to do “all general excavating and finish the excavation for all . . . curbs, concrete walks, drives,” $104.

The court found that plaintiff performed all of the work to be performed under the subcontract with the exception of (4) and (5) and allowed as an offset $600 and $104, respectively. The court also found that each item of extras was authorized, requested, and accepted by defendants and that *682 the requirement of a written order for each item of extra work was complied with in each instance by defendants orally ordering each item of extra work and by accepting each item of work upon its completion, and that the reasonable value of the extras was $7,472.69. Judgment was for plaintiff for the full amount of its claim, $8,841.50,* 1 2 345together with interest from January 5, 1952, of $696.30, plus $2.40 for verifying and recording the lien, less the setoff of $704, or $8,836.20; and decreed foreclosure of the lien. Defendants appeal from the judgment with the exception of the award of $704 on their counterclaim.

Defendants contend the court erroneously found that plaintiff was entitled to $7,472.69 as the reasonable value of the so-called extras. They assert: (1) they did not order any of the claimed extras, nor did they accept any of them; (2) the claimed extras were called for by the contract; (3) increased costs are not extras; (4) plaintiff is not entitled to damages by reason of any delays in construction; (5) the amount found due for the alleged extras is erroneous; (6) the court erred in limiting their recovery on the counterclaim.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tutor-Saliba-Perini J v. v. LA Co. MTA CA2/7
California Court of Appeal, 2014
Ghilotti Brothers v. Monahan Pacific CA1/3
California Court of Appeal, 2013
Convolve, Inc. v. Compaq Computer Corp.
527 F. App'x 910 (Federal Circuit, 2013)
G. Voskanian Construction, Inc. v. Alhambra Unified School District
204 Cal. App. 4th 981 (California Court of Appeal, 2012)
Bohm v. Horsley Co. (In Re Groggel)
333 B.R. 261 (W.D. Pennsylvania, 2005)
Biren v. Equality Emergency Medical Group, Inc.
125 Cal. Rptr. 2d 325 (California Court of Appeal, 2002)
Amelco Electric v. City of Thousand Oaks
98 Cal. Rptr. 2d 159 (California Court of Appeal, 2000)
Havens Steel Co. v. Randolph Engineering Co.
613 F. Supp. 514 (W.D. Missouri, 1985)
Allen-Howe Specialties Corp. v. U. S. Construction, Inc.
611 P.2d 705 (Utah Supreme Court, 1980)
Weeshoff Construction Co. v. Los Angeles County Flood Control District
88 Cal. App. 3d 579 (California Court of Appeal, 1979)
Huber, Hunt & Nichols, Inc. v. Moore
67 Cal. App. 3d 278 (California Court of Appeal, 1977)
Carolina Mechanical Contractors, Inc. v. Yeargin Construction Co.
198 S.E.2d 224 (Supreme Court of South Carolina, 1973)
Trinity Builders, Inc. v. Schaff
199 N.W.2d 914 (North Dakota Supreme Court, 1972)
Cure v. City of Jefferson
380 S.W.2d 305 (Supreme Court of Missouri, 1964)
Hawley v. Orange County Flood Control District
211 Cal. App. 2d 708 (California Court of Appeal, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
276 P.2d 52, 128 Cal. App. 2d 676, 1954 Cal. App. LEXIS 1520, Counsel Stack Legal Research, https://law.counselstack.com/opinion/frank-t-hickey-inc-v-los-angeles-jewish-community-council-calctapp-1954.