Allen-Howe Specialties Corp. v. U. S. Construction, Inc.

611 P.2d 705, 1980 Utah LEXIS 932
CourtUtah Supreme Court
DecidedApril 21, 1980
Docket16209
StatusPublished
Cited by8 cases

This text of 611 P.2d 705 (Allen-Howe Specialties Corp. v. U. S. Construction, Inc.) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Allen-Howe Specialties Corp. v. U. S. Construction, Inc., 611 P.2d 705, 1980 Utah LEXIS 932 (Utah 1980).

Opinion

MAUGHAN, Justice:

Plaintiff, a subcontractor, initiated this action, pleading in seven counts, to recover $75,010.42 for labor and materials expended in erecting a metal building to house a uranium extraction plant. The defendants, after extensive discovery, moved for summary judgment on the alternative grounds that certain contractual provisions precluded recovery or an accord and satisfaction had been effected. The trial court granted defendants summary judgment on five of the counts. Plaintiff dismissed one count and its claim against Kennecott Copper; liability on one count was admitted. Plaintiff appeals, contending it is entitled to a trial to establish its claim for an additional $64,108.77. The judgment of the trial court is affirmed. No costs awarded.

Wyoming Mineral Corporation (Wyoming), a subsidiary of Westinghouse Electric Corporation, leased a parcel of land from Kennecott Copper in Bingham Canyon, Utah, to build a uranium extraction facility. U. S. Construction, Inc. (U.S.C.) entered into a contract with Wyoming to complete the cement work and erect a building on the land; Wyoming assigned its interests in this contract to Jacobs Engineering Company (Jacobs), which acted as general contractor.

On April 11,1977, plaintiff entered into a subcontract with U.S.C. to erect a metal building for Wyoming, for the price of $53,-372.00. Plaintiff has been paid or tendered $64,193.65. (The count upon which liability was admitted was for $10,901.65, this sum included $10,623.25 which had been previously tendered and an additional $278.40, which had not been tendered because of a bookkeeping error.) Plaintiff claims an additional $64,108.77, by means of alternative counts, sounding in contract, breach of contract and quantum meruit against its con-tractee, U.S.C. Plaintiff has also asserted a claim against Jacobs for interference with the plaintiff’s performance of its subcontract.

In essence, plaintiff claims that the nature and scope of its work under its subcontract was substantially changed by site congestion and the delays and interference from process equipment and from other trades and crafts, which increased plaintiffs costs. Plaintiff contends it had to perform under conditions it had not anticipated at the time it executed the contract. *707 These conditions, according to plaintiff, compelled it to perform its work at 35% efficiency; it, therefore, charged 35% of its work to the contract and claimed an additional 65% as extra work beyond the scope of the contract. A portion of plaintiff’s claim involved the costs of transferring material from a stockpile located approximately 100 yards from the building site, and the work entailed in cleaning threads on the steel that had been improperly painted.

The defense is predicated on certain provisions contained in plaintiff’s subcontract, which incorporated the terms and provisions of the contract between U.S.C. and Wyoming. The subcontract provided no decrease or increase of the subcontract price shall be binding unless agreed upon in writing. The contract between Wyoming and U.S.C. required that if the contractor considered any order or direction a change in the work, although not so identified by the owner, the Contractor shall within five days after notice of such direction submit a written request for the issuance of a written change order. The failure to follow such a prescribed course is deemed an agreement such direction did not make any change in the work required by the contract.

Plaintiff was further bound by the following provision in the contract between Wyoming and U.S.C.:

“Acquaintance With Conditions And Requirements
“The Contractor, by its execution of the Construction Agreement, represents that he has visited or has had full opportunity to examine the site upon which the work is to be erected and the specifications, drawings, and other contract documents; that he has satisfied himself as to the requirements of the work and all conditions which may affect the work; that his entry into the contract has not been induced either wholly or in part by any promises, representations or statements on behalf of the Owner, his agents or representatives other than those set forth in the contract. The Contractor further represents that the price set forth in the Construction Agreement has been determined with due regard to all such conditions and requirements affecting the work, as well as the difficulties and delays incident to work of the nature contemplated hereby, and agrees that no claim for any increase in such price shall be made except as specifically provided in the contract.”

In addition to the contractual provisions, the discovery process revealed plaintiff’s knowledge of the very limited space at the building site. Prior to execution of the subcontract, plaintiff sought another contract on a separate phase of construction. Plaintiff submitted a document which stated:

“We further request because of the tight work area, we be the only steel erector on the job during our scheduled erection dates.”

Plaintiff’s president further conceded payment or tender had been made in every case where a claim for extra work had been submitted and negotiated in advance. The President of plaintiff further admitted the location was brought to his attention immediately after the steel arrived at the stockpile, and he had an opportunity to submit a claim for extra work for hauling the steel from the storage area and failed to do so. The President further conceded, shortly after the work commenced he conferred with a representative of U.S.C. concerning the processing of claims for extra work; he was informed extra work must be approved pri- or to commencing such work. Plaintiff’s claims for hauling the steel from the stockpile and for cleaning the steel, which was improperly painted, were submitted in the form of back charges for extra work sometime after its performance. Payment was refused on the ground there was no authorization as an extra from U.S.C. Plaintiff’s failure to comply with the contractual provisions precluded its claim for extra work.

A considerable portion of plaintiff’s claim involved alleged additional expenses incurred by reason of delays and inefficient scheduling, which caused simultaneous work by different crafts on the crowded work site.

*708 The subcontract provided:

“Section 6. In the event the Subcontractor’s performance of this Subcontract is delayed or interfered with by acts of the Owner, Contractor or other subcontractors, he may request an extension of the time for the performance of the same, as hereinafter provided, but shall not be entitled to any increase in the Subcontract price or to damages or additional compensation as a consequence of such delay except to the extent that Contractor is entitled to receive an increase in contract price from the Owner.”

The contract between Wyoming and U.S.C. provided:

“9. Simultaneous Work By Others
(a) The Owner shall have the right to perform or have performed in and about the construction site during the time when the Contractor is performing the work required by this contract, such other work as Owner may desire.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alpha Partners, Inc. v. Transamerica Investment Management, L.L.C.
2006 UT App 331 (Court of Appeals of Utah, 2006)
Estate Landscape v. MOUNTAIN STATES TEL.
793 P.2d 415 (Court of Appeals of Utah, 1990)
Cove View Excavating & Construction Co. v. Flynn
758 P.2d 474 (Court of Appeals of Utah, 1988)
Masonry Equipment & Supply v. Willco Associates, Inc.
755 P.2d 756 (Court of Appeals of Utah, 1988)
Pioneer Roofing Co. v. Mardian Construction Co.
733 P.2d 652 (Court of Appeals of Arizona, 1986)
Marton Remodeling v. Jensen
706 P.2d 607 (Utah Supreme Court, 1985)
Highland Construction Co. v. Union Pacific Railroad
683 P.2d 1042 (Utah Supreme Court, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
611 P.2d 705, 1980 Utah LEXIS 932, Counsel Stack Legal Research, https://law.counselstack.com/opinion/allen-howe-specialties-corp-v-u-s-construction-inc-utah-1980.