Highland Construction Co. v. Union Pacific Railroad

683 P.2d 1042, 1984 Utah LEXIS 766
CourtUtah Supreme Court
DecidedFebruary 3, 1984
Docket17900
StatusPublished
Cited by23 cases

This text of 683 P.2d 1042 (Highland Construction Co. v. Union Pacific Railroad) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Highland Construction Co. v. Union Pacific Railroad, 683 P.2d 1042, 1984 Utah LEXIS 766 (Utah 1984).

Opinion

HOWE, Justice:

Plaintiff, Highland Construction Company, appeals from a directed verdict of no cause of action for failure to introduce any admissible evidence of the quantity of damages it allegedly had sustained under a construction contract. The appeal is taken against Dravo Corporation, Carbon County Coal Company and its general partners, Rocky Mountain Energy Company and Dravo Coal Company, hereinafter collectively referred to as Carbon; Lamb Engineering & Construction Company (Lamb); and Michael R. Lamb and James R. Lamb, as well as Industrial Indemnity Company. None of the other parties is before us on this appeal for reasons not relevant to our review.

Plaintiff was the successful bidder on concrete substructures and piping work to be installed in a coal handling facility under construction near Hanna, Wyoming. On March 26, 1979 Highland entered into a written subcontract with Lamb which was the general contractor for Carbon, owner of the facility. The bid price was $1,097,-325. Completion of the work under the subcontract was scheduled for August 15, 1979.

On July 9, 1979 Lamb partially terminated Highland’s work for its failure to comply with working schedules on four of the concrete foundations under construction. Highland was allowed to continue the remaining contract work, but was completely terminated on December 27, 1979, after three additional partial terminations by Lamb in August, September and October of that year.

Highland filed suit against Lamb, Carbon and Lamb’s surety, Industrial Indemnity Company, Richard R. Lamb and James R. Lamb, alleging breach of contract, breach of fiduciary duty, conspiracy, quantum me-ruit, tortious interference with contractual rights, business interference and economic duress, as well as punitive damage claims. Lamb counterclaimed for breach of contract and resulting damages for costs which it incurred in substituting work to be performed by Highland, and for losses due to winter work and business reputation damages. The case was tried before a jury. At the end of the liability phase of its case, Highland proffered evidence on a “total cost” theory and the opinion of its expert that Highland’s damages approximated its total expenditures on the job (which included a built-in profit), less the amount it had been paid by Lamb. No allocation of damages among the various defendants was made. Defendants objected to that proffer, the objection was sustained, and Highland rested without further proof of damages. Defendants then moved the court for a directed verdict which the court granted. Judgment was entered in favor of all defendants, no cause of action. The trial proceeded on Lamb’s counterclaim. The jury returned a verdict on special interrogatories against Highland, awarding damages in the sum of $242,660.25 as a result of Highland’s breach of contract.

Highland appeals, citing error by the trial court as follows:

*1045 1. Failure to allow Highland to proceed on total costs, quantum meruit, or “jury verdict” theories, and ruling that Highland was not entitled to loss of business or punitive damages.

2. Refusal to accept some of Highland’s jury instructions, and the submittal to the jury of a special verdict form favoring Lamb’s theories.

3. Ruling that there was no evidence of improper conduct on the part of Michael R. Lamb and James R. Lamb.

4. Exclusion of Highland’s expert witness testimony.

5. Award of costs to defendants Lamb and Carbon not contemplated by law.

I.

The record before us is voluminous and covers the entire liability phase of Highland’s case against Lamb which it presented at trial stretching over a period of two months. We have diligently reviewed the testimony adduced; however, space will not allow but the briefest reference to some of the crucial points. We will view the evidence in a light most favorable to the party against whom the verdict was directed, in order to determine whether Highland had established a prima facie case. Cruz v. Montoya, Utah, 660 P.2d 723 (1983) and cases cited therein; Lindsay v. Gibbons and Reed, 27 Utah 2d 419, 497 P.2d 28 (1972).

II.

Highland’s first assignment of error is the trial court’s refusal to admit evidence of damages based on total costs, quantum meruit, and “jury verdict” theories. After rejecting Highland’s proffer, the court made the following finding:

As to the defendant Lamb Engineering & Construction Company, there is no evidence before the court that its conduct, misconduct, actions, inactions and/or breach of contract caused any damage to any other party or parties to the above-entitled action.

Highland contends that the court should have allowed evidence that Highland’s total costs incurred for its partial construction of the concrete structures and piping work were $2,317,172.66, and that after a credit of $413,763.04 paid by Lamb, Highland was entitled to $1,903,409.62. Highland’s bid to Lamb was $1,097,325.

It is true that some degree of uncertainty in the evidence of damages will not relieve a defendant from recompensing a wronged plaintiff. Bastian v. King, Utah, 661 P.2d 953 (1983) and cases cited therein. However, it is also a general rule of long standing that a plaintiff must show damages by evidence of facts and not by mere conclusions, and that the items of damage must be established by substantial evidence and not by conjecture. Bunnell v. Bills, 13 Utah 2d 83, 90, 368 P.2d 597 (1962); Bingham C. & L. Co. v. Board of Ed., 61 Utah 149, 159, 211 P. 981 (1922). And, whether general or special, damages must be traceable to the wrongs complained of. Ranch Homes, Inc. v. Greater Park City Corp., Utah, 592 P.2d 620 (1979).

Highland contends that as a result of the nature of work to be performed it was impossible for it to trace ascertainable and quantifiable damages to the misconduct and/or breach of the various defendants. Therefore, the court below should have let the total costs come in under one of the three theories set out above, and allowed the jury to calculate the amount due as well as allocate percentages among the various defendants.

1. In support of its total cost theory, Highland refers us to several cases which allowed recovery to the plaintiff under that method. All of them are distinguishable. Two major differences pervade all of them: the contractor was either free from fault (or his fault was insignificant) and suit was brought against a single defendant who was blameworthy in causing the contractor’s cost overrun. In Thorn Const. Co., Inc. v. Utah Dept. of Transp., Utah, 598 P.2d 365 (1979), the court found for the contractor because a specific false *1046 representation was made by the defendant’s engineer’s aide that borrow could be used from a certain pit more than 1.7 miles closer to the construction area than the pit the contractor finally had to use. The court allowed the excess cost for hauling the borrow.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Penunuri v. Sundance Partners, Ltd.
2017 UT 54 (Utah Supreme Court, 2017)
Penunuri v. Sundance Partners
2017 UT 54 (Utah Supreme Court, 2017)
Express Recovery Services Inc. v. Reuling
2015 UT App 299 (Court of Appeals of Utah, 2015)
Richards v. Brown
2009 UT App 315 (Court of Appeals of Utah, 2009)
Traco Steel Erectors, Inc. v. Comtrol, Inc.
2007 UT App 407 (Court of Appeals of Utah, 2007)
Depew v. Sullivan
2003 UT App 152 (Court of Appeals of Utah, 2003)
Wood v. Utah Farm Bureau Insurance Co.
2001 UT App 35 (Court of Appeals of Utah, 2001)
Coleman Ex Rel. Schefski v. Stevens
2000 UT 98 (Utah Supreme Court, 2000)
Young v. State
2000 UT 91 (Utah Supreme Court, 2000)
Bd. of Com'rs, Utah State Bar v. Petersen
937 P.2d 1263 (Utah Supreme Court, 1997)
Savage Industries, Inc. v. American Pulverizer Co.
103 F.3d 145 (Tenth Circuit, 1996)
Anderson v. Sharp
899 P.2d 1245 (Court of Appeals of Utah, 1995)
Ong International (U.S.A.) Inc. v. 11th Avenue Corp.
850 P.2d 447 (Utah Supreme Court, 1993)
Canyon Country Store v. Bracey
781 P.2d 414 (Utah Supreme Court, 1989)
C.S. v. Nielson
767 P.2d 504 (Utah Supreme Court, 1988)
Bergener v. Dravo Corp.
740 P.2d 818 (Utah Supreme Court, 1987)
Jacobs v. Farmland Mutual Insurance Co.
377 N.W.2d 441 (Supreme Court of Minnesota, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
683 P.2d 1042, 1984 Utah LEXIS 766, Counsel Stack Legal Research, https://law.counselstack.com/opinion/highland-construction-co-v-union-pacific-railroad-utah-1984.