H. John Homan Co., Inc. v. The United States

418 F.2d 522, 189 Ct. Cl. 500, 1969 U.S. Ct. Cl. LEXIS 85
CourtUnited States Court of Claims
DecidedNovember 14, 1969
Docket128-66
StatusPublished
Cited by11 cases

This text of 418 F.2d 522 (H. John Homan Co., Inc. v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
H. John Homan Co., Inc. v. The United States, 418 F.2d 522, 189 Ct. Cl. 500, 1969 U.S. Ct. Cl. LEXIS 85 (cc 1969).

Opinion

OPINION

PER CURIAM:

This case was referred to Trial Commissioner William E. Day with directions to make findings of fact and recommendation for conclusions of law under the order of reference and Rule 57(a) [since September 1, 1969, Rule 134(h)]. The commissioner has done so in an opinion and report filed on February 4, 1969. Exceptions to the commissioner’s opinion, findings and recommended conclusion of law were filed by defendant and plaintiff requested that the court adopt the commissioner’s findings, opinion and recommended conclusion of law except for a requested addition to one finding. * The case has been submitted to the court on oral argument of counsel and the briefs of the parties. Since the court agrees with the commissioner’s opinion, findings and recommended conclusion of law, with a modification in the amount of recovery, it hereby adopts the same, as modified, as the basis for its judgment in this case. Therefore, plaintiff is entitled to recover and judgment is entered for plaintiff in the sum of $59,-715.10.

Commissioner Day’s opinion, as modified by the court, is as follows:

This is a contract case. The plaintiff sues for breach of contract, charging that its performance of contract work was unreasonably delayed by the defendant, to plaintiff’s damage. At pretrial it was agreed that the only issue for trial was whether or not the defendant caused plaintiff to be unreasonably delayed in the performance of the contract work. The proof shows that the plaintiff is entitled to prevail on this issue and it is therefore entitled to a judgment for the damages it established. There is no question in this case relating to the application of the Wunderlich Act because the claims made are not redress-able under the contract, there being no suspension of work clause included in the contract provisions. United States v. Utah Constr. & Mining Co., 384 U.S. 394, 86 S.Ct. 1545, 16 L.Ed.2d 642 (1966). (1966).

The material facts have been set forth in detailed findings which will be summarized for consideration of the controlling legal principles.

In June 1964, the defendant, through the General Services Administration (hereafter called GSA) issued an invitation for bids at a fixed price for the extension and modernization of the United States Post Office at Mount Holly, New Jersey. Bid opening was conducted on June 16, 1964, and (at $269,841) the plaintiff’s was the lowest of the six bids received. The other bids ranged from $286,445 to $343,897, with the third low bid at $290,000. The government estimate for the work (made on August 12, 1964) was $248,800.

The specifications for the work on which bids had been sought and received, provided a definite sequence for the work, because it was understood that the post office was to continue its function of postal operations during performance of the work.

A few days after the bid opening, the GSA superiors of the officials who had issued the invitations for bid directed a change in the sequence of operations. Thereafter and before the award of a contract to the plaintiff, a conference was held between representatives of the *524 plaintiff and the GSA regional office to discuss the change in sequence of the work which had been directed by higher GSA authority. At this conference, the plaintiff agreed to perform the work, with the changed work sequence, at the bid price. Based upon such agreement, contract GS-02B-11, 826, dated August 12, 1964, was awarded to the plaintiff, with the change in work sequence denominated as Change Order No. 1. The contract price for the work was $269,841, with the work to be completed in 270 days from receipt of notice to proceed. Since the notice to proceed was received on August 24, 1964, the scheduled completion date was May 20,1965.

The contract work was substantially completed in 350 days, thus there was an overrun of 80 days beyond the scheduled completion date. There was a provision for liquidated damages of $50 per calendar day, but none were assessed or paid.

The contract as let provided for the modernization and revision of a 64' x 56' post office so as to extend it by 30' x 64', with a new mailing platform 40' x 24' and an extension of the parking and truck maneuvering area behind the structure from an area 40' x 70' to an area 60' x 144', as well as extensive interior and exterior modernizations and alterations.

The work got off to a bad start, due to the fact that the site survey was defective, in that the metes and bounds as shown on the site plan (one of the contract drawings) would not close.

The discrepancy in the survey was called to the attention of GSA representatives at a meeting on September 2, 1964. This was apparently prior to the time the defendant retained the Alfred Clauss firm as its supervising architect, two of whose representatives attended the meeting. On September 9, 1964, Chester Jones (one of the two), project engineer of the Clauses firm, was on the job for an inspection visit. He was told of the discrepancy in the site survey and of the impossibility of beginning the excavation for the extensive retaining wall until the discrepancy was corrected. Jones phoned the GSA construction engineer, Curotola, at his New York office, advising him of the discrepancy in the site survey. Jones was told to have the plaintiff proceed with demolition of the old swing room until the survey problem was resolved.

GSA formally solicited bids from various surveyors for a resurvey of the site plan and it was not until September 30, 1964, that a surveyor was hired by GSA to do the work. The survey was not completed until October 21, 1964. Until this was accomplished, it was not possible for the plaintiff to proceed with the excavation for the retaining wall, the erection of which (plus backfilling) was the key to an orderly beginning of the work for the reason, among others, that with the wall in place and backfilled, much needed ground space would have been provided for the storage of material and equipment needed for the work, as well as space for the parking and maneuvering of post office trucks moving mail in and out of the post office. With the retaining wall constructed and back-filled, there would have been a great deal more space for the use of trucks delivering and unloading of material and equipment as well as for general construction activities.

As shown in finding 4, there were 11 steps in the mandatory construction sequence covered by Change Order No. 1. The preamble stated that all construction work must be planned in conformance with the 11-step sequence and construction sequence drawings 27-3. It further provided that the work must further be coordinated with the construction engineer and custodian of the building to the end that normal seasonal functions of the post office would not be impaired by reason of the construction work. It further provided:

******

b. The following sequence steps are specific in nature and are to be used as a sequence of construction for the subject project:

(1) Construct all new retaining walls * * * around new maneuvering *525 area, backfill and grade and make suitable for vehicle usage.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Smith v. United States
40 Cont. Cas. Fed. 76,854 (Federal Claims, 1995)
C. Norman Peterson Co. v. Container Corp. of America
172 Cal. App. 3d 628 (California Court of Appeal, 1985)
Highland Construction Co. v. Union Pacific Railroad
683 P.2d 1042 (Utah Supreme Court, 1984)
Savoy Construction Co. v. United States
31 Cont. Cas. Fed. 71,109 (Court of Claims, 1983)
Lewis-Nicholson, Inc. v. United States
550 F.2d 26 (Court of Claims, 1977)
Huber, Hunt & Nichols, Inc. v. Moore
67 Cal. App. 3d 278 (California Court of Appeal, 1977)
S. L. Rowland Construction Co. v. Beall Pipe
540 P.2d 912 (Court of Appeals of Washington, 1975)
Seger v. United States
469 F.2d 292 (Court of Claims, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
418 F.2d 522, 189 Ct. Cl. 500, 1969 U.S. Ct. Cl. LEXIS 85, Counsel Stack Legal Research, https://law.counselstack.com/opinion/h-john-homan-co-inc-v-the-united-states-cc-1969.