Savoy Construction Co. v. United States

31 Cont. Cas. Fed. 71,109, 2 Cl. Ct. 338, 1983 U.S. Claims LEXIS 1760
CourtUnited States Court of Claims
DecidedApril 29, 1983
DocketNo. 579-81C
StatusPublished
Cited by2 cases

This text of 31 Cont. Cas. Fed. 71,109 (Savoy Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Savoy Construction Co. v. United States, 31 Cont. Cas. Fed. 71,109, 2 Cl. Ct. 338, 1983 U.S. Claims LEXIS 1760 (cc 1983).

Opinion

OPINION

MEROW, Judge:

This matter comes before the court on motions for summary judgment filed by the parties. Plaintiff seeks review and reversal of the portion of the decisions of the Armed Services Board of Contract Appeals (ASBCA) in Savoy Construction Co., Inc., ASBCA No. 21218, 80-1 BCA par. 14,392, recon. denied, 80-2 BCA par. 14,724, denying plaintiff’s claim for extended corporate overhead. Defendant seeks a determination that the cited ASBCA decisions are final under the review standards of 41 U.S.C. 321-322 (1976).

Background Facts

On August 2, 1973 the United States Army Corps of Engineers (Corps) contracted with plaintiff for the construction of the Harry Diamond Laboratories, Phase III, in Adelphi, Maryland, at a price of $17,094,500. The contract included a changes clause reading (in part):

3. CHANGES (1968 FEB)
* * * * ' * *
(d) If any change under this clause causes an increase or decrease in the contractor’s cost of, or the time required for, the performance of any part of the work under this contract, whether or not changed by any order, an equitable adjustment shall be made and the contract modified in writing accordingly.

The contract work was to be completed on or before November 15, 1975, 820 days after a notice to proceed with the work was issued by the Corps. The date of beneficial occupancy by the government was December 10, 1976, some 391 days after the originally scheduled completion date. Numerous contract changes were made by the Corps during construction. In 14 modifications the overall completion date was extended by 273 days. Before the ASBCA the parties stipulated, among other items, that “2. During performance of the contract the Respondent recognized 273 compensable days of time extensions for government caused delay of the work attributable to the modifications presently in dispute.”

Among the claims which plaintiff asserted before the ASBCA in connection with the extended performance period was one for “Extended Corporate Overhead.” Plaintiff’s complaint stated (in part):

As the delays resulting from the Government-ordered changes caused Appellant to incur additional costs associated with extended project supervision, Appellant also had to bear additional general corporate and administrative costs during the delays (“extended corporate overhead”). These costs are not included in the overhead costs of administering a particular change or in the general overhead cost of administering the contract. Extended corporate overhead reflects the costs of administering and supervising the contract as a whole during a period of time when Appellant assumed its overhead costs, e.g., the cost of its corporate staff, would be absorbed by additional direct cost dollars, e.g., other contracts. The [340]*340delays extended the period of time during which Appellant had to focus its resources on the performance of this project. As a result, Appellant was precluded from directing its resources to the performance of work relating to other contracts and from reducing excess staff whose efforts would not otherwise have been required by Appellant.

In presenting this extended corporate overhead claim to the ASBCA, plaintiff utilized a formula approach based upon the decision in Eichleay Gorp., ASBCA No. 5183, 60-2 BCA par. 2688, 61-1 BCA par. 2894. First, a ratio was developed between the billings plaintiff made on the Harry Diamond contract and total billings on all contracts during the same period. This ratio was then applied to the total corporate (home office) overhead for the period1 to obtain the portion thereof deemed allocable to the Harry Diamond contract. This allo-cable portion was then divided by the total days of contract performance to obtain a “Daily Extended corporate rate.” This daily rate times the stipulated 273 days of extended performance comprised the amount claimed.

In denying plaintiffs claim for extended corporate overhead, the board found no evidence that the contract modifications caused any increase in the ratio of plaintiff’s home office overhead to its direct costs. The board also found that during the time period involved plaintiff was performing a substantial amount of work under other contracts with no indication in the evidence that the modification caused any increase in the home office overhead rate applicable to this other work. The ASBCA noted that formulas similar to that proposed by plaintiff had been utilized in other appeals “where some entitlement for it has been determined.” But the ASBCA ruled that plaintiff had failed to establish the necessary predicate, “that the modification caused appellant’s other work to be burdened with an increased rate for its home office expenses.” Thus, the ASBCA concluded that plaintiff “has not established entitlement to any recovery for unabsorbed overhead, * * On plaintiff’s subsequent motion for reconsideration, the ASBCA noted that each modification included home office overhead through the use of rates expressed as a percentage of the additional direct costs added by the modifications and that, on the evidence of record, “[t]o award a daily amount in addition to overhead rates already allowed by respondent would constitute an over recovery.”

In its motion for summary judgment, plaintiff asserts that the ASBCA’s decision constitutes “an aberration from the long-established case law of this court * * 2 In response, defendant asserts that the ASBCA’s decision is supported by substantial evidence and is legally sound.

Discussion

The home office overhead involved in this litigation constitutes costs which are fixed in nature in that they do not generally change directly in relation to the volume or number of contracts performed or the ex[341]*341tent of the direct costs incurred in performing, such contracts. They are the costs which a company must continue to incur to remain in business, such as officers’ salaries, rent, taxes, etc. Obviously, to remain in business, a company must, on an overall basis, price its contracts so as to recover the direct costs incurred in performing its contracts plus an additional amount sufficient to cover the fixed costs it will continue to incur, even in the absence of contracts, plus a profit.

When a change is made to a government contract during its performance, the price must be equitably adjusted. The equitable adjustment required is simply a corrective measure utilized to keep a contractor whole when the government modifies a contract. Bruce Construction Corp. v. United States, 163 Ct.Cl. 97, 100, 324 F.2d 516, 518 (1963). The equitable adjustment must compensate the contractor for increased costs which are the direct and necessary result of the change. Paul Hardeman, Inc. v. United States, 186 Ct.Cl. 743, 752, 406 F.2d 1357, 1362-63 (1969) (Davis, J., concurring); Merritt-Chapman & Scott Corp. v. United States, 192 Ct.Cl. 848, 851, 429 F.2d 431, 432 (1970).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Capital Electric Company v. The United States
729 F.2d 743 (Federal Circuit, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
31 Cont. Cas. Fed. 71,109, 2 Cl. Ct. 338, 1983 U.S. Claims LEXIS 1760, Counsel Stack Legal Research, https://law.counselstack.com/opinion/savoy-construction-co-v-united-states-cc-1983.