Conrac Corp. v. United States

558 F.2d 994, 23 Cont. Cas. Fed. 81,510, 214 Ct. Cl. 561, 1977 U.S. Ct. Cl. LEXIS 72
CourtUnited States Court of Claims
DecidedJuly 8, 1977
DocketNo. 368-74
StatusPublished
Cited by11 cases

This text of 558 F.2d 994 (Conrac Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Conrac Corp. v. United States, 558 F.2d 994, 23 Cont. Cas. Fed. 81,510, 214 Ct. Cl. 561, 1977 U.S. Ct. Cl. LEXIS 72 (cc 1977).

Opinion

Bennett, Judge,

delivered the opinion of the court:

This appeal under the Wunderlich Act, 41 U.S.C. §§ 321, 322 (1970), before the court on defendant’s request for review of Trial Judge Francis C. Browne’s opinion filed June 28, 1976, raises two questions of interpretation of the so-called Truth in Negotiations Act, 10 U.S.C. § 2306(f) (1970) (hereinafter the Act). The Armed Services Board of Contract Appeals (the board) agreed with the contracting officer that the contract in issue was "overpriced,” due to insufficient cost information disclosure to the Government by the contractor, though it lowered the amount of the refund to the Government ordered by the contracting officer, concluding that $8,050 was due from the contractor.1 The trial judge reversed, finding that the contractor owed no part of that amount because its cost disclosure to the Government had been adequate, and, independently, because the sum determined by the board was too small to be made the subject of a mandatory refund under the Act and the contract. We cannot accept the trial judge’s [565]*565analysis, and we enter judgment for defendant, sustaining the ruling of the board.

Plaintiff is the successor in interest to Giannini Controls Corporation, the original party to the contract in issue. Its problems giving rise to this litigation can be traced back to July 1966, when the Navy apparently ran short of time in making a procurement. On July 26, 1966, Giannini received an urgent telephone call from a Navy procurement negotiator, asking it to ready a quotation "before the end of the week” for delivery of 29 air data computers. Giannini was the sole source supplier of these computers, known as the 560T27-1, which were used in the flight control system of the Navy’s C2-A aircraft. The contractor complied with the quotation request, the very next day offering the Navy a unit purchase price of approximately $20,000, even though a much longer period of time, from 4 to 6 weeks, would normally be allowed for assembly of the cost data and the resulting formulation of the asking price.

As required by the Act, Giannini also submitted to the Navy certain information it possessed on the cost of each of the some 500 component parts that comprised the 560T27-1 computer. Since Giannini’s prospective sale would culminate in a "negotiated prime contract” with a military department "where the price is expected to exceed $100,000,” the Act specifies that "[p]rior to award” of the contract the contractor must "submit cost or pricing data” and "certify that, to the best of his knowledge and belief, the cost or pricing data he submitted was accurate, complete and current * * *.”2 The only cost data Giannini [566]*566so submitted was a priced bill of materials (BOM) dated June 24, 1965, showing the item-by-item breakdown of estimated material costs for the components of a computer, the 560T1-2A, almost identical to that slated for procurement.3 Giannini did not disclose, nor did the Government’s negotiator know of the data on, the firm’s purchase history cards, which listed for each computer component the quantities and prices of previous purchases.

No attempt was made by Giannini to update the 1965 BOM given the Government, to reflect the firm’s component cost experience in the 11 months intervening the BOM and the 560T27-1 quotation. This was not undertaken simply because, as indicated earlier, up to 6 weeks would usually be needed to ascertain the most recent purchase costs, not then recorded on the purchase history cards, and compile all the cost data from the cards into an itemized materials cost estimate. The urgency of the prospective procurement did not allow for such delay. Therefore, the negotiators for Giannini and the Navy worked from the 1-year-old BOM, agreeing to make judgmental adjustments to account for the age of the cost information as well as the fact that the quantity of computers slated for procurement, 29, differed from the quantities for which costs were projected in the BOM, 6, 12, and 18. The Government’s negotiator pressed for a 4-percent reduction in the direct material cost proposed by Giannini (roughly $7,900 of the $20,000 unit price), to [567]*567compensate for the BOM’s age and quantity differences, but in the end compromised on a 2-percent reduction. On August 18, 1966, Giannini and the Navy agreed to a unit price of $18,900, amounting to a total contract price of $548,100. Also on that date, the contractor executed the certificate of cost information disclosure required by the Act and the (yet to be signed) contract’s Price Reduction for Defective Cost or Pricing Data clause implementing the statute. Although its purchase history cards then contained component cost data of more recent vintage than the 1965 BOM, including information current as of 6 weeks before negotiations began, Giannini submitted none to the Government.

The negotiated computer sale contract was executed on September 19 and proceeded to completion. The contractor experienced no further difficulties on its account until 1970, when it was selected for audit. As a result of two audits conducted that year, and a failure to resolve differences held by the contractor and the Navy over the information that the audits disclosed, the contracting officer for the computer sale contract issued a final decision on December 8, 1970, determining that the contract had been "overpriced” by $14,158 and that a refund was due the Government in that amount. The overpricing was said to stem from the excess of the 1965 BOM costs over the lower costs shown to exist on purchase history cards at the time of the price negotiations, for 15 high dollar value computer components. Giannini was thus implicitly held to have violated the requirements of the Act and the implementing contract clause, for failure to furnish the purchase history cards to the Government’s negotiator. The contractor timely appealed to the board, which disagreed in part with the contracting officer and lowered the refund amount to $8,050.4 The board sustained the use of the purchase history cards available to the contractor at the outset of the negotiations, but not disclosed to the [568]*568Government, to justify a refund for failure to furnish accurate, complete, and current cost data. The board opined that "the natural and probable consequence of the nondisclosure is that the price as negotiated was overstated * * However, the board absolved the contractor of any alleged wrongdoing in its failure to provide the Government with cost data more current than that in the contractor’s possession on the date of certification, August 18, 1966.

Plaintiff attacks the board’s decision on two grounds. First, it disputes the relevance and reasonable availability, and therefore the legal requirement, of disclosing the purchase history cards as they existed when negotiations commenced. On the point of relevance, plaintiff cites Lockheed Aircraft Corp. v. United States, 193 Ct. Cl. 86, 432 F. 2d 801 (1970), for the proposition that the Act’s disclosure requirements are not met by the furnishing of data in undigested form, meaning the purchase history cards rather than an updated BOM. In Lockheed, raw purchase history data in a Kardex file was furnished to the Government’s negotiators.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Loretta J. Owen v. Defense Logistics Agency
16 F.3d 421 (Federal Circuit, 1993)
Fruin-Colnon Corporation v. The United States
912 F.2d 1426 (Federal Circuit, 1990)
William F. Klingensmith, Inc. v. United States
731 F.2d 805 (Federal Circuit, 1984)
Savoy Construction Co. v. United States
31 Cont. Cas. Fed. 71,109 (Court of Claims, 1983)
Regan Construction Co. v. United States
30 Cont. Cas. Fed. 70,306 (Court of Claims, 1982)
Precision Piping, Inc. v. United States
29 Cont. Cas. Fed. 82,292 (Court of Claims, 1982)
Piasecki Aircraft Corp. Island Road v. United States
667 F.2d 50 (Court of Claims, 1981)
Campeau Tool & Die Co.
650 F.2d 287 (Court of Claims, 1980)
Grumman Aerospace Corp. v. United States
587 F.2d 498 (Court of Claims, 1978)
American Electric Contracting Corp. v. United States
579 F.2d 602 (Court of Claims, 1978)
Singer Co. v. United States
576 F.2d 905 (Court of Claims, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
558 F.2d 994, 23 Cont. Cas. Fed. 81,510, 214 Ct. Cl. 561, 1977 U.S. Ct. Cl. LEXIS 72, Counsel Stack Legal Research, https://law.counselstack.com/opinion/conrac-corp-v-united-states-cc-1977.