M-R-S Manufacturing Co. v. United States

492 F.2d 835, 203 Ct. Cl. 551, 1974 U.S. Ct. Cl. LEXIS 93
CourtUnited States Court of Claims
DecidedFebruary 20, 1974
DocketNo. 95-72
StatusPublished
Cited by14 cases

This text of 492 F.2d 835 (M-R-S Manufacturing Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
M-R-S Manufacturing Co. v. United States, 492 F.2d 835, 203 Ct. Cl. 551, 1974 U.S. Ct. Cl. LEXIS 93 (cc 1974).

Opinion

SkeltoN, Judge,

delivered the opinion of the court:

This contract action involves an appeal by the plaintiff, M-R-S Manufacturing Company, from a decision of the Armed Services Board of Contract Appeals (hereinafter referred to as the Board) in M-R-8 Manufacturing Company, ASBCA No. 14825, 71-1 BCA, ¶8821, at 40,998 (decided March 31,1971). The Board found that the plaintiff’s submission of defective cost or pricing data to the Government resulted in overstatements in the prices of two contracts between the parties. The data found to be defective involved labor costs for four manufactured parts and a duplication in a bill of materials. On cross motions for summary judgment, the parties ask this court to review the Board’s decision in accordance with the standards of the Wunderlich Act, 41 U.S.C. §§ 321, 322 (1970). Such a review presents the issues of whether or not the Board’s decision is supported by substantial evidence and is correct as a matter of law. Resolving these issues requires further interpretation of the Truth in Negotiations Act, 10 U.S.C. § 2306(f) (1970)1 and the now standard Price Reduction for Defective [555]*555Cost of Pricing Data clause2 (Defective Pricing Clause), added to Government contracts pursuant to that statute.

Factual Background

On January 23,1967, the Government issued to the plaintiff sole source request for proposal (EFP) No. DSA-700-67-E-5960 calling for certain heavy duty earth moving equipment. The return date of the EFP was February 2, 1967. Since the EFP allowed only a short period of time for response, the plaintiff’s proposal utilized cost figures which had been used in a previous procurement for identical equipment. The proposal included the applicable DD Forms 633 (Contract Pricing Proposals) which listed the proposed prices for the equipment. The first two columns of the forms showed a breakdown of the prices into individual cost elements. The third column, which allowed a reference to the source data used to form the proposal in the first two columns, contained no entries. The proposal included no supporting documentation.

On February 13, 1967, the Government requested the Defense Contract Audit Agency (DOAA) to perform an audit [556]*556to provide the information necessary for the development of a realistic negotiation objective. A DCAA auditor conducted an audit, or price proposal evaluation, between 'February 20, 1967, and March 1, 1967, at the plaintiff’s plant, and then submitted an audit report. The report contained nothing concerning the allegedly defective data involved in this action. After negotiations between the parties and plaintiff’s execution of a Certificate of Current Cost or Pricing Data,3 the Government awarded Contract DSA 700-67-C-C976 (Contract 0976) on March 30,1967.

On July 13, 1967, the Government issued sole source BFP No. DSA 700-68-R-0145 to M-IUS calling for more heavy duty equipment. This equipment was identical to the machinery involved in Contract C976. The plaintiff responded with a proposal which included the applicable DD Forms 638. The first two columns of the forms contained appropriate price information, but the third column contained nothing. A letter which accompanied the proposal read, in part, as follows:

Reference: Solicitation No. DSA-700-68-R-0145 We consider this proposal and Contract DSA-700-67C-C-976 inter-related, as in effect, this Proposal is essentially the option we expected to be exercised when we secured Contract No. DSA — 700-67-C-C-976.
Therefore, if your auditor’s figures on Contract DSA-700-67-C-C-976 are acceptable for this new procurement of identical items, you will find the attached DD Form 633 utilizes the EXACT Purchased and SubContract Parts costs, the EXACT Direct Material cost and the EXACT Direct Labor cost as AUDITED and NEGOTIATED on Contract No. DSA-700-67-CCC-976.

The proposal was later followed by additional DD Forms 633. No support data accompanied the forms, but a third set forwarded on August 16,1967, listed in the third column a reference to “cost records” in explanation of the prices quoted in the first two columns.

[557]*557The Government officials decided not to request audit assistance with respect to the plaintiff’s proposal because direct costs had been verified by the audit in connection with Contract C976, and indirect costs had been examined in another audit performed in connection with a May 22, 1967, proposal by M-E-S for production of similar, but larger, equipment. During final negotiations on August 16,1967, the direct costs accepted by the Government were the same figures submitted in support of the proposal which resulted in Contract C976. Negotiated indirect costs were based on the audit performed in connection with the May 22,1967, proposal for larger equipment. The plaintiff neither offered nor submitted any other cost data, and the Government requested no such data. The plaintiff executed a Certificate of Current Cost or Pricing Data on August 17, 1967, and received an award of Contract DSA 700-68-C-8006 (Contract 8006) on August 25, 1967.

Understanding the issues in this case requires a rather detailed explanation of the plaintiff’s accounting system and the nature of the February audit by the Government. The plaintiff maintained a Kardex-file accounting system for manufactured parts. After fabricating a part, the plaintiff recorded manufacturing costs for the production run on a production card with a production order number as its means of identification. The production card contained the name of the part, the part number, the date the production run commenced, the completion date, the number of units manufactured, and a breakdown of costs. The cost breakdown included entries for the unit and total costs of materials, labor, and burden for the particular run. After each production run was completed, the sum of the costs for materials, labor, and burden was posted on a unit and total basis to an inventory card. The inventory 'card contained the part name, the part number, and a list of every production run on that part. For each production run, the card listed the production order number, the date of completion, and the costs on a total and unit basis.

As can be seen, plaintiff’s Kardex file contained two relevant types of cards for manufactured parts. Although the inventory cards showed cost variations among production runs, they did not show precise labor and material costs for [558]*558manufactured parts on particular production runs. These precise costs could be obtained by consulting the individual production card pertaining to ta particular production run. This was done by determining the production order number from the inventory card and then going to the individual production card bearing that production order number.

When the auditor who conducted the first price evaluation in February 1967, went to the plaintiff’s plant, he carried the plaintiff’s proposal and DD Forms 633. After submitting the proposal, plaintiff had prepared additional cost data consisting of a priced bill of materials. This bill of materials, which listed manufactured parts by part name and number, was given to the auditor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States Ex Rel. Sanders v. Allison Engine Co.
364 F. Supp. 2d 699 (S.D. Ohio, 2003)
United States Ex Rel. Campbell v. Lockheed Martin Corp.
282 F. Supp. 2d 1324 (M.D. Florida, 2003)
American National Bank & Trust Co. v. United States
36 Cont. Cas. Fed. 75,871 (Court of Claims, 1990)
Unisys Corporation v. United States
888 F.2d 841 (Federal Circuit, 1990)
Universal Restoration, Inc. v. United States
35 Cont. Cas. Fed. 75,612 (Court of Claims, 1989)
F. Alderete General Contractors Inc. v. United States
31 Cont. Cas. Fed. 72,054 (Court of Claims, 1984)
Paul E. Lehman, Inc. v. United States
673 F.2d 352 (Court of Claims, 1982)
Singer Co. v. United States
576 F.2d 905 (Court of Claims, 1978)
Conrac Corp. v. United States
558 F.2d 994 (Court of Claims, 1977)
Grumman Aerospace Corp. v. United States
549 F.2d 767 (Court of Claims, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
492 F.2d 835, 203 Ct. Cl. 551, 1974 U.S. Ct. Cl. LEXIS 93, Counsel Stack Legal Research, https://law.counselstack.com/opinion/m-r-s-manufacturing-co-v-united-states-cc-1974.