Michael W. Wynne, Secretary of the Air Force v. United Technologies Corporation

463 F.3d 1261, 2006 U.S. App. LEXIS 21924, 2006 WL 2466286
CourtCourt of Appeals for the Federal Circuit
DecidedAugust 28, 2006
Docket05-1393
StatusPublished
Cited by6 cases

This text of 463 F.3d 1261 (Michael W. Wynne, Secretary of the Air Force v. United Technologies Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Michael W. Wynne, Secretary of the Air Force v. United Technologies Corporation, 463 F.3d 1261, 2006 U.S. App. LEXIS 21924, 2006 WL 2466286 (Fed. Cir. 2006).

Opinion

CLEVENGER, Senior Circuit Judge.

The Secretary of the Air Force (Air Force) appeals from the reconsideration decision of the Armed Services Board of Contract Appeals (Board) denying the Air Force’s claim for a contract price reduction for a six-year, multi-billion dollar contract with United Technologies Corporation, Pratt & Whitney (UTech). See In re United Techs. Corp., ASBCA Nos. 51410, 53089, 53349, 05-1 BCA ¶ 32,860 (Jan. 19, 2005) (Reconsideration Decision). The Air Force claims that UTech furnished defective cost or pricing data in connection with both its initial price proposal and its Best and Final Offer (BAFO) for the contract, such that the Air Force was entitled to a contract price reduction under the Truth in Negotiations Act (TINA), 10 U.S.C. § 2306(f) (1983). 1 Because we agree with the Board that the Air Force did not establish that it relied upon the defective cost or pricing data to its detriment, we affirm.

I

TINA requires that when a government contract is expected to exceed a certain value, a contractor must submit “cost or pricing data ... [and] certify that, to the best of his knowledge and belief, the cost or pricing data he submitted was accurate, complete and current ....” 10 U.S.C. § 2306(f)(1). In addition, TINA requires that a contract price be “adjusted to exclude any significant sums by which it may be determined ... that such price was increased because the contractor ... furnished cost or pricing data which ... was inaccurate, incomplete, or noncurrent.” § 2306(f)(2). In other words, the government will be awarded a contract price adjustment when the government proves that a contractor furnished defective cost or pricing data and “the [government relied on the overstated costs to its detriment.” Singer Co., Librascope Div. v. United States, 217 Ct.Cl. 225, 576 F.2d 905, 914 (1978). 2 When it is determined *1263 that a contractor furnished defective data, there is a rebuttable presumption that the defective data resulted in “an overstated negotiated contract price .... for it is reasonable to assume that the government negotiators relied upon the data supplied by the contractor and that this data affected the negotiations.” Sylvania Elec. Pros., Inc. v. United States, 202 Ct.Cl. 16, 479 F.2d 1342, 1349 (1973). However, if that presumption of causation is rebutted, the government can only prevail upon proof that it relied upon the defective data to its detriment in agreeing to the contract price.

In the instant case, the Air Force sought a contract price reduction in the amount of roughly $300 million, claiming that UTech furnished defective cost or pricing data in connection with both the initial price proposal, which was made on August 17, 1983, and the BAFO, which was made on December 5, 1983. In an initial decision, the Board determined that although certain of the Air Force claims did not constitute defective cost or pricing data, UTech had made a number of undisclosed mistakes which did constitute defective cost or pricing data. Appeals of United Techs. Corp., ASBCA Nos. 51410, 53089, 53349, 04-1 BCA ¶ 32,556 (Feb. 27, 2004) (Initial Decision ). The Board further determined that the Air Force had relied on this defective data to its detriment. However, the Board found that although the defective data had caused an increase in the contract price in some instances, it had caused a decrease in the contract price in other instances and that the contract price reductions to which the Air Force was entitled were exceeded by the offsets to which UTech was entitled. Consequently, the Board found that the Air Force did not prove “that it is entitled to an affirmative recovery due to appellant’s defective cost or pricing data.” Id., slip op. at 39.

Upon reconsideration, UTech challenged the Board’s Initial Decision, arguing that the Board’s reliance analysis improperly focused on the Air Force’s audit of the data submitted with the initial price proposal. Reconsideration Decision, slip op. at 2-3. UTech argued that the Air Force did not accept UTech’s initial price proposal, dated August 17, 1983. Rather, the Air Force accepted UTech’s BAFO, dated December 5, 1983, for the base year of the contract, Fiscal Year 1985 (FY 85), and accepted revised versions of that offer for the subsequent years of the contract, Fiscal Years 1986 —1990 (FYs 86-90). Because each of the Air Force’s claims were based upon its acceptance of the BAFO and subsequent revised offers, UTech argued that the Board’s “inquiry as to causation should properly focus on whether the [Air Force] relied on the defective BAFO cost or pricing data to award the contract and to determine that the offered prices were fair and reasonable.” Id., slip op. at 2.

The Board agreed with UTech, finding that it had misplaced its analysis in the Initial Decision, and that under the correct analysis the Air Force’s claims failed. The Board found that the Air Force was entitled to a presumption that “the natural and probable consequence of defective cost or pricing data is to cause an overstated price.” Id. slip op. at 3. However, the Board found that UTech had rebutted this presumption by demonstrating that the Air Force did not rely upon the allegedly defective cost or pricing data in agreeing to any contract price and that the Air Force had failed to meet its burden of proof, as the claimant, of showing that the defective cost or pricing data caused an increase in the contract price.

With respect to the contract price for FY 85, which was based upon the BAFO, *1264 the Board found as a matter of fact that “neither the Defense Contract Audit Agency (DCAA), the [Air Force] price analyst, the contracting officer (CO) nor the cost panel reviewed the BAFO cost or pricing data prior to award.” Id. The Board found that the language in the Record of Acquisition Action (RAA) and attachments, which allegedly showed reliance on the defective cost or pricing data, was “seriously undercut by the concession of the RAA author ... that he did not recall reviewing any of appellant’s BAFO cost or pricing data.” Id. The Board also found that the RAA did not discuss any specific BAFO cost or pricing data relied upon by the Air Force price analyst or the cost panel. In addition, the Board found that the Air Force failed to provide evidence indicating that the BAFO data was reviewed by any government person prior to award. Although the Air Force price analyst and the CO testified that they relied on the fact that the BAFO data furnished by appellant were current, accurate, and complete, the Board found that “this testimony — given roughly 1Y years after the fact — was lacking in specificity and was unpersuasive.” Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

AAI Corporation, d/b/a Textron Systems, Unmanned Systems
Armed Services Board of Contract Appeals, 2022
Alloy Surfaces Company, Inc.
Armed Services Board of Contract Appeals, 2020
BAE Systems Tactical Vehicle Systems LP
Armed Services Board of Contract Appeals, 2016
United States v. United Technologies Corp.
782 F.3d 718 (Sixth Circuit, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
463 F.3d 1261, 2006 U.S. App. LEXIS 21924, 2006 WL 2466286, Counsel Stack Legal Research, https://law.counselstack.com/opinion/michael-w-wynne-secretary-of-the-air-force-v-united-technologies-cafc-2006.