Lockheed Aircraft Corporation, Lockheed-Georgia Company Division v. The United States

432 F.2d 801, 193 Ct. Cl. 86, 1970 U.S. Ct. Cl. LEXIS 51
CourtUnited States Court of Claims
DecidedOctober 16, 1970
Docket250-67
StatusPublished
Cited by15 cases

This text of 432 F.2d 801 (Lockheed Aircraft Corporation, Lockheed-Georgia Company Division v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lockheed Aircraft Corporation, Lockheed-Georgia Company Division v. The United States, 432 F.2d 801, 193 Ct. Cl. 86, 1970 U.S. Ct. Cl. LEXIS 51 (cc 1970).

Opinions

ON PLAINTIFF’S MOTION AND DEFENDANT’S CROSS-MOTION FOR SUMMARY JUDGMENT

DURFEE, Judge.

This case comes before the court for Wunderlich Act review (41 U.S.C. §§ 321, 322) of a decision of the Armed Services Board of Contract Appeals (hereinafter referred to as the ASBCA or the Board), in Lockheed Aircraft Corporation, Loekheed-Georgia Company Division, ASBCA No. 10453, 67-1 BCA, 6356, p. 29,439 (decided May 18, 1967). The court is called upon in this companion case to Cutler-Hammer, Inc. v. United States, 416 F.2d 1306, 189 Ct.Cl. 76 (1969), to further interpret the “Price Reduction for Defective Cost or Pricing Data” clause (“the Defective Pricing Clause”).

Plaintiff Lockheed had a $10,500,000 negotiated fixed-price contract with the Air Force to develop and produce an electronic Malfunction Detection and Recording System (MADREC). This was a system to be installed in B-52 aircraft. The Air Force had awarded a letter contract to plaintiff on May 4, 1962. One component of MADREC was the 813LQ recorder, and in anticipation of the award of the prime contract, plaintiff solicited a proposal from Midwestern Instruments, Inc. for the recorder.

Since Midwestern had not yet developed the 813LQ recorder, it submitted a price proposal of $14,078.17 per unit on February 13, 1962, based on the 812L [803]*803recorder which had been previously produced. Included in the price proposal were cost estimates for the anticipated difference between the 812L and the 813LQ models.

Following a series of negotiations and meetings, an audit and price analysis were performed by Lockheed on May 15, 1962. On June 1, 1962 there was a price reduction to $13,857 per unit, and on June 6 the unit price 'was further reduced to $13,681.50. This latter price was definitized into a subcontract entered into on June 6, 1962.

The June 6, 1962 subcontract price was included in plaintiff’s own price proposal, submitted to the Air Force in July 1962. In September 1962 an Air Force Audit and Price Analysis team visited Midwestern’s plant, where it examined records and made production studies. By this time, Midwestern had delivered about 30 recorders to plaintiff. A price reduction of $281 per unit was negotiated by the Air Force team with Midwestern, after which the Air Force team prepared an Audit Report and a Price Analysis Report, reflecting such reduction.

During February and March 1963, plaintiff and the Air Force were negotiating to make definite their contract. The letter contract was finally definitized on April 15, 1963, and made effective retroactive to May 4, 1962, the date of the original letter contract. The prices in the prime contract reflected the Midwestern prices as amended by the reduction negotiated with the Air Force.

In the early fall of 1963, the General Accounting Office (GAO) began a four-month audit of the contract. The audit revealed that the total unit price for purchase parts for the 813LQ recorder should have been $1,530 instead of $2,-070. Lockheed thereafter conducted its own three-day price survey of Midwestern’s accounts in April 1964, and found merit in GAO’s findings. The Air Force also conducted an audit. After communications between all the parties, the Contracting Officer on October 19, 1964 made a formal demand on Lockheed for a refund of $234,623 (the amount suggested by GAO) on the basis of Midwestern’s overstatement of material and labor costs.

The demand for a refund from Lockheed was made pursuant to the following provision in the definitized price contract :

PART XVIII — PRICE REDUCTION FOR DEFECTIVE COST OR PRICING DATA (NOV. 1962)
(a) If the Contracting Officer determines that any price, including profit or fee, negotiated in connection with this contract was increased by any significant sums because the Contractor, or any subcontractor in connection with a subcontract covered by (c) below, furnished incomplete or inaccurate cost or pricing data or data not current as certified in the Contractor’s Certificate of Current Cost or Pricing Data, then such price shall be reduced accordingly and the contract shall be modified in writing to reflect such adjustment.
******

The foregoing contract clause was made inapplicable to subcontracts which were “definitized prior to contractor’s receipt of a fully executed copy of this document except to the extent the subcontractor was previously subject to the requirements of such clauses by the terms of the subcontract.” Midwestern’s contract was definitized before Lockheed’s ; nonetheless, the subcontract contained its own version of the Defective Pricing Clause, which was substantively the same as the clause in the prime contract.

Lockheed appealed the demand of the Contracting Officer to the ASBCA. The Board upheld the Contracting Officer’s decision with respect to the material cost, and therefore denied the appeal in that regard. The Board held, however, that the Contracting Officer’s decision that direct labor costs had been overstated was incorrect, and sustained the appeal to that extent. Finally, Midwestern tried to offset royalties and development costs [804]*804that it had overlooked and excluded from its estimated proposal. The Board held that since these two cost items were only “remotely related” to the “material costs” in issue, there could be no offset, since “the equitable reduction permitted under the clause is intended to cover solely the cost items concerning which the pricing data was defective. To permit unrelated offsets would be tantamount to repricing the entire contract, which is not within the contemplation of the clause.” 67-1 BCA at p. 29,450.

Plaintiff is now appealing the decision of the Board regarding the “material cost” overstatements and the disallowance of offsets. Both sides are moving for summary judgment.

We feel it is important to note, at this juncture, that this case is the product of a demand made by the Government upon Lockheed, as a result of alleged overstatements in price made by its subcontractor, Midwestern. Although this is a case of first impression, insofar as the issue of subcontractor overstatements are concerned, this court has had occasion previously to consider P.L. 87-653,1 the Defective Pricing Statute, and the clause adopted pursuant to it, in Cutler-Hammer, Inc., supra. In that case we held, in part, that the prime contractor was under an obligation to furnish information concerning costs. We stated:

Public Law 87-653 was intended to apply to situations where the data supplied was incomplete, inaccurate, or noncurrent. It was aimed at cases where costs were known, but information about them was withheld. The statute (and the contract clause which is utilized pursuant to the statute) speaks in terms of “Defective Pricing.” If a cost is known when the 'contract price is being negotiated, it must be furnished accurately, completely, and on a current-price basis. If the contractor purchases components from a subcontractor, these costs are also subject to the Defective Pricing Clause. 416 F.2d at 1311, 189 Ct.Cl. at 84.

The court is now faced with the question as to added responsibility of a prime contractor for overpricing by its subcontractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States Ex Rel. Sanders v. Allison Engine Co.
364 F. Supp. 2d 699 (S.D. Ohio, 2003)
United States v. United Technologies, Corp.
51 F. Supp. 2d 167 (D. Connecticut, 1999)
Motorola, Inc. v. Togo D. West, Secretary of the Army
125 F.3d 1470 (Federal Circuit, 1997)
Sundstrand Corp. v. Commissioner
98 T.C. No. 36 (U.S. Tax Court, 1992)
Universal Restoration, Inc. v. United States
35 Cont. Cas. Fed. 75,612 (Court of Claims, 1989)
Singer Co. v. United States
576 F.2d 905 (Court of Claims, 1978)
Conrac Corp. v. United States
558 F.2d 994 (Court of Claims, 1977)
M-R-S Manufacturing Co. v. United States
492 F.2d 835 (Court of Claims, 1974)
Lockheed Aircraft Corp. v. United States
485 F.2d 584 (Court of Claims, 1973)
Sylvania Electric Products, Inc. v. United States
479 F.2d 1342 (Court of Claims, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
432 F.2d 801, 193 Ct. Cl. 86, 1970 U.S. Ct. Cl. LEXIS 51, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lockheed-aircraft-corporation-lockheed-georgia-company-division-v-the-cc-1970.