Wynne, Secretary of the Air Force v. United Technologies Corp.

CourtCourt of Appeals for the Federal Circuit
DecidedAugust 28, 2006
Docket2005-1393
StatusPublished

This text of Wynne, Secretary of the Air Force v. United Technologies Corp. (Wynne, Secretary of the Air Force v. United Technologies Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wynne, Secretary of the Air Force v. United Technologies Corp., (Fed. Cir. 2006).

Opinion

United States Court of Appeals for the Federal Circuit

05-1393

MICHAEL W. WYNNE, Secretary of the Air Force,

Appellant,

v.

UNITED TECHNOLOGIES CORPORATION,

Appellee.

James W. Poirier, Attorney, Commercial Litigation Branch, Civil Division, United States Department of Justice, of Washington, DC, argued for appellant. With him on the brief were Peter D. Keisler, Assistant Attorney General, David M. Cohen, Director, and Donald E. Kinner, Assistant Director. Of counsel on the brief was Bryan R. O’Boyle, Senior Trial Attorney, Air Force Legal Services Agency, of Arlington, Virginia. Of counsel was Robert P. Balcerek, AFMCLO/JAB, of Wright Patterson Air Force Base, Ohio.

W. Stanfield Johnson, Crowell & Moring LLP, of Washington, DC, argued for appellee. With him on the brief was David Z. Bodenheimer.

Appealed from: United States Armed Services Board of Contract Appeals

Administrative Judge Jack Delman United States Court of Appeals for the Federal Circuit

___________________________

DECIDED: August 28, 2006 ___________________________

Before NEWMAN, Circuit Judge, CLEVENGER, Senior Circuit Judge, and SCHALL, Circuit Judge.

CLEVENGER, Senior Circuit Judge.

The Secretary of the Air Force (Air Force) appeals from the reconsideration

decision of the Armed Services Board of Contract Appeals (Board) denying the Air

Force's claim for a contract price reduction for a six-year, multi-billion dollar contract

with United Technologies Corporation, Pratt & Whitney (UTech). See In re United

Techs. Corp., ASBCA Nos. 51410, 53089, 53349, 05-1 BCA ¶ 32,860 (Jan. 19, 2005)

(Reconsideration Decision). The Air Force claims that UTech furnished defective cost

or pricing data in connection with both its initial price proposal and its Best and Final

Offer (BAFO) for the contract, such that the Air Force was entitled to a contract price reduction under the Truth in Negotiations Act (TINA), 10 U.S.C. § 2306(f) (1983).1

Because we agree with the Board that the Air Force did not establish that it relied upon

the defective cost or pricing data to its detriment, we affirm.

I

TINA requires that when a government contract is expected to exceed a certain

value, a contractor must submit "cost or pricing data . . . [and] certify that, to the best of

his knowledge and belief, the cost or pricing data he submitted was accurate, complete

and current . . . ." 10 U.S.C. § 2306(f)(1). In addition, TINA requires that a contract

price be "adjusted to exclude any significant sums by which it may be determined . . .

that such price was increased because the contractor . . . furnished cost or pricing data

which . . . was inaccurate, incomplete, or noncurrent." § 2306(f)(2). In other words, the

government will be awarded a contract price adjustment when the government proves

that a contractor furnished defective cost or pricing data and "the [g]overnment relied on

the overstated costs to its detriment." Singer Co., Librascope Div. v. United States,

576 F.2d 905, 914 (Ct. Cl. 1978).2 When it is determined that a contractor furnished

defective data, there is a rebuttable presumption that the defective data resulted in "an

overstated negotiated contract price . . . . for it is reasonable to assume that the

1 TINA has undergone revision and recodification since 1984, as discussed infra. Therefore, unless otherwise indicated, we will refer to the version of TINA effective in 1983, when UTech offered the initial price proposal and the BAFO.

2 In Singer, our predecessor court assessed a TINA claim under the 1970 version of the act. 576 F.2d at 908. That version of TINA is identical to the 1983 version of the act in all ways material to this case. See 10 U.S.C. § 2306(f)(1) (1970) ("A prime contractor . . . shall be required to submit cost or pricing data . . . and shall be required to certify that, to the best of his knowledge and belief, the cost or pricing data he submitted was accurate, complete and current . . . .").

05-1393 2 government negotiators relied upon the data supplied by the contractor and that this

data affected the negotiations." Sylvania Elec. Pros., Inc. v. United States, 479 F.2d

1342, 1349 (Ct. Cl. 1973). However, if that presumption of causation is rebutted, the

government can only prevail upon proof that it relied upon the defective data to its

detriment in agreeing to the contract price.

In the instant case, the Air Force sought a contract price reduction in the amount

of roughly $300 million, claiming that UTech furnished defective cost or pricing data in

connection with both the initial price proposal, which was made on August 17, 1983,

and the BAFO, which was made on December 5, 1983. In an initial decision, the Board

determined that although certain of the Air Force claims did not constitute defective cost

or pricing data, UTech had made a number of undisclosed mistakes which did constitute

defective cost or pricing data. Appeals of United Techs. Corp., ASBCA Nos. 51410,

53089, 53349, 04-1 BCA ¶ 32,556 (Feb. 27, 2004) (Initial Decision). The Board further

determined that the Air Force had relied on this defective data to its detriment.

However, the Board found that although the defective data had caused an increase in

the contract price in some instances, it had caused a decrease in the contract price in

other instances and that the contract price reductions to which the Air Force was

entitled were exceeded by the offsets to which UTech was entitled. Consequently, the

Board found that the Air Force did not prove "that it is entitled to an affirmative recovery

due to appellant's defective cost or pricing data." Id., slip op. at 39.

Upon reconsideration, UTech challenged the Board's Initial Decision, arguing that

the Board's reliance analysis improperly focused on the Air Force's audit of the data

submitted with the initial price proposal. Reconsideration Decision, slip op. at 2-3.

05-1393 3 UTech argued that the Air Force did not accept UTech's initial price proposal, dated

August 17, 1983. Rather, the Air Force accepted UTech's BAFO, dated December 5,

1983, for the base year of the contract, Fiscal Year 1985 (FY 85), and accepted revised

versions of that offer for the subsequent years of the contract, Fiscal Years 1986 - 1990

(FYs 86-90). Because each of the Air Force's claims were based upon its acceptance

of the BAFO and subsequent revised offers, UTech argued that the Board's "inquiry as

to causation should properly focus on whether the [Air Force] relied on the defective

BAFO cost or pricing data to award the contract and to determine that the offered prices

were fair and reasonable." Id., slip op. at 2.

The Board agreed with UTech, finding that it had misplaced its analysis in the

Initial Decision, and that under the correct analysis the Air Force's claims failed. The

Board found that the Air Force was entitled to a presumption that "the natural and

probable consequence of defective cost or pricing data is to cause an overstated price."

Id. slip op. at 3.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Wynne, Secretary of the Air Force v. United Technologies Corp., Counsel Stack Legal Research, https://law.counselstack.com/opinion/wynne-secretary-of-the-air-force-v-united-technolo-cafc-2006.