Sylvania Electric Products, Inc. v. United States

479 F.2d 1342, 24 A.L.R. Fed. 304, 202 Ct. Cl. 16, 1973 U.S. Ct. Cl. LEXIS 243
CourtUnited States Court of Claims
DecidedJune 20, 1973
DocketNo. 378-70
StatusPublished
Cited by21 cases

This text of 479 F.2d 1342 (Sylvania Electric Products, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sylvania Electric Products, Inc. v. United States, 479 F.2d 1342, 24 A.L.R. Fed. 304, 202 Ct. Cl. 16, 1973 U.S. Ct. Cl. LEXIS 243 (cc 1973).

Opinion

Kunzig, Judge,

delivered the opinion of the court:

This is a contract action wherein this court, toy cross motions for summary judgment, has been 'asked to review a decision of the Armed Services Board of Contract Appeals (the Board)1 in accordance with the standards of the Wunderlich Act, 41 U.S.C. §§ 321,322 (1910).

In issue is whether the Board’s decision that the Government is entitled to a price reduction of $239,913.75 pursuant to the Defective Pricing Clause of the contract2 is supported by substantial evidence and is correct as a matter of law.

[19]*19We affirm the Board’s excellent decision in favor of the Government. We hold the conclusions of the Board withstand a Wunderlich Review:

I. Plie plaintiff-contractor failed to disclose accurate, complete and current cost and pricing data.

II. The data not disclosed involved significant sums.

III. The Government relied upon the inaccurate data thus establishing a causal relationship between the incorrect data and the final negotiated contract price.

These conclusions of the Board involve mixed questions of law and fact. We do not deem it necessary to attempt to distinguish the two, since final disposition of this case does not require such delineation.

On April 30, 1964, plaintiff-contractor responded to a previously issued Request for Proposal (RFP) for the production of the electronic’s portion of two special receiving sets. Plaintiff quoted a firm fixed price of $6,385,325. On October 2, 1964, the last day of the negotiations, plaintiff [20]*20executed the required Certificate of Cost and Pricing Data. It provided:

[19]*19“(4) Prior to the pricing of any contract change or modification to a subcontract covered by (3) above, for which the price adjustment is expected to exceed $100,000, or such lesser amount as may be prescribed by the head of the agency.
“Any prime contract or change or modification thereto under which such certificate is required shall contain a provision that the price to the Government, including profit or fee, shall be adjusted to exclude any significant sums by which it may be determined by the head of the agency that such price was increased because the contractor or any subcontractor required to furnish such a certificate, furnished cost or pricing data which, as of a date agreed upon between the parties (which date shall be as close to the date of agreement on the negotiated price as is practicable), was inaccurate, incomplete, or noncurrent: Provided, That the requirements of this subsection need not be applied to contracts or subcontracts where the price negotiated is based on adequate price competition, established catalog or market prices of commercial items sold in substantial quantities to the general public, prices set by law or regulation or, in exceptional cases where the head of the agency determines that the requirements of this subsection may be waived and states in writing his reasons for such determination.
“For the purpose of evaluating the accuracy, completeness, and currency of cost or pricing data required to be submitted by this subsection, any authorized representative of the head of the agency who is an employee of the United States Government shall have the right, until the expiration of three years after final payment under the contract or subcontract, to examine all books, records, documents, and other data of the contractor or subcontractor related to the negotiation, pricing, or performance of the contract or subcontract.”
[20]*20(i) complete cost and pricing data, current as of 130 April 1964, has been considered in preparing Syl-vania Proposal 300-PB.-03 and submitted to the Contracting Officer or his representative;
(ii) all significant changes in the above data which occurred since the aforementioned date through 2 October 1964 have been similarly submitted; and no more recent significant change in such data was known to the undersigned at the time of executing this certificate ; etc.
(iii) all data submitted are accurate.

Final price negotiations were held between September 28, 1964 and October 2,1964, based upon plaintiff’s submissions. At the outset, the parties were approximately $3,000,000 apart. After many changes in their respective positions, they differed by only about $600,000. It was mutually agreed to split the difference, which resulted in a final contract price of $4,614,000.

In 1966, as a result of events not relevant to this case, the General Accounting Office (GA'O) opened an inquiry into plaintiff’s compliance with the Truth in Negotiations Act. The GAO found that the contract price of $4,614,000 had been increased by significant sums because plaintiff had failed to disclose to the Government accurate, complete and current cost and pricing data. The GAO report further found that proper disclosure before final price negotiations would have revealed plaintiff’s use of incorrect quantities in computing the cost of some parts and components, and the use of noncurrent price quotations in computing the cost of others. On the basis of these findings, the GAO recommended that the Government seek a downward adjustment of $254,000 in the contract price. Accordingly, on August 28, 1968, the Air Force contracting officer ordered the contract price reduced by $254,304. This figure represented defective pricing under the Truth in Negotiations Act as follows:

[21]*21a. GPI Receivers (duplication)-$104,752
b. Cable (939) (lower quotations)- 12,165
c. Cable (216) (307) (lower quotations)- 10,173
d. Adapters and Connectors (duplication)- 35,927
e. Goniometers (lower quotations)- 17,500
f. Power Supply Units (lower quotations)- 18,820
g. (Rack Hardware (lower quotations)- 15,636
Total_ 214,973

To this amount, 6% for general and administrative expense and 11.6% for profit, were added, giving a total of $254,304.

On appeal to the Board, the contracting officer’s decision was upheld to the extent of $239,913.75.3 Plaintiff subsequently sued for this figure, filing a petition in this court on November 3, 1970 and seeking a review of the Board’s decision pursuant to the standards of the Wunderlich Act, 41 U.S.C. §§ 321, 322 (1970).

The instant contract contained a Defective Pricing Clause identical in content to ASPE, § 7.104r-29 in effect at the time of the contract and promulgated pursuant to the Truth in Negotiations Act. The clause reads in pertinent part:

(a) If The Contracting Officer determines that any price, including profit or fee, negotiated in connection with this contract was increased lay any significant sums because the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alloy Surfaces Company, Inc.
Armed Services Board of Contract Appeals, 2020
United States v. United Technologies Corp.
782 F.3d 718 (Sixth Circuit, 2015)
United States Ex Rel. Sanders v. Allison Engine Co.
364 F. Supp. 2d 699 (S.D. Ohio, 2003)
United States Ex Rel. Campbell v. Lockheed Martin Corp.
282 F. Supp. 2d 1324 (M.D. Florida, 2003)
United States v. United Technologies, Corp.
51 F. Supp. 2d 167 (D. Connecticut, 1999)
In re Bicoastal Corp.
37 Cont. Cas. Fed. 76,075 (M.D. Florida, 1991)
Unisys Corporation v. United States
888 F.2d 841 (Federal Circuit, 1990)
Universal Restoration, Inc. v. United States
35 Cont. Cas. Fed. 75,612 (Court of Claims, 1989)
Universal Restoration, Inc. v. The United States
798 F.2d 1400 (Federal Circuit, 1986)
Singer Co. v. United States
576 F.2d 905 (Court of Claims, 1978)
Conrac Corp. v. United States
558 F.2d 994 (Court of Claims, 1977)
M-R-S Manufacturing Co. v. United States
492 F.2d 835 (Court of Claims, 1974)
Lockheed Aircraft Corp. v. United States
485 F.2d 584 (Court of Claims, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
479 F.2d 1342, 24 A.L.R. Fed. 304, 202 Ct. Cl. 16, 1973 U.S. Ct. Cl. LEXIS 243, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sylvania-electric-products-inc-v-united-states-cc-1973.