United States Ex Rel. Campbell v. Lockheed Martin Corp.

282 F. Supp. 2d 1324, 2003 U.S. Dist. LEXIS 21103, 2003 WL 22128833
CourtDistrict Court, M.D. Florida
DecidedAugust 5, 2003
Docket6:95CV549-ORL-28DAB
StatusPublished
Cited by18 cases

This text of 282 F. Supp. 2d 1324 (United States Ex Rel. Campbell v. Lockheed Martin Corp.) is published on Counsel Stack Legal Research, covering District Court, M.D. Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Ex Rel. Campbell v. Lockheed Martin Corp., 282 F. Supp. 2d 1324, 2003 U.S. Dist. LEXIS 21103, 2003 WL 22128833 (M.D. Fla. 2003).

Opinion

ORDER

ANTOON, District Judge.

In this action the United States (“the United States” or “the Government”) and its relator, Albert Campbell, seek to recover damages from Defendant Lockheed Martin under the False Claims Act (“the FCA”) (31 U.S.C. § 3729) and the Truth in Negotiations Act (“TINA”) (10 U.S.C. § 2306a). Plaintiffs contend that Lockheed Martin withheld “cost or pricing data” from the United States Air Force in connection with contracts for the manufacture by Lockheed of LANTIRN pods, despite being obligated to disclose such data under TINA. Additionally, Plaintiffs assert that Lockheed Martin double-billed the Government and submitted false invoices to the Government in connection with several LANTIRN contracts.

This cause is currently before the Court on several motions for summary judgment submitted by the parties: the United States’ Motion for Partial Summary Judgment (Doc. 369) (“Motion I”); Defendants’ Motion for Summary Judgment on Counts *1327 II-VII of the Government’s Complaint (Doc. 374) (“Motion II”); and Defendants’ Motion for Summary Judgment on FMS Issues (Doc. 376) (“Motion III”). 1 The Court heard oral argument on these motions on July 1, 2003 (see Doc. 470) and now issues the following rulings thereon.

I. Background

A. Factual Background 2

Defendant Lockheed Martin (“Lockheed”) was formed in 1994 via a merger of Martin Marietta Corporation and Lockheed Corporation. 3 Lockheed is the only manufacturer of LANTIRN (“Low Altitude Navigation and Targeting Infrared for Night”) pods, which are targeting and navigation pods used on military aircraft, including F-15s and F-16s. Relator Albert Campbell was formerly employed by Lockheed as Cost Control Chief of the LAN-TIRN program.

Since the 1980s, the United States Government has entered into several contracts with Lockheed for the production of LAN-TIRN pods. The LANTIRN pods are manufactured at Lockheed facilities in Orlando, Florida, and Ocala, Florida. In late 1993, the final assembly and test subtasks of the manufacturing process were moved from Orlando to Ocala; this move caused an interruption in production and a “learning loss” that are important to some of the issues in this case.

The first production contract for the LANTIRN system, known as the “USAF contract,” was entered into in 1984. Another LANTIRN contract entered into by the Government and Lockheed involved the ultimate sale of LANTIRN pods to Saudi Arabia, Greece, and Bahrain and is referred to by the parties and herein as the “SGB contract.” The SGB contract is a sole-source, negotiated contract 4 that was entered into in 1993-1994.

The SGB contract and other contracts that involve the resale of LANTIRN pods (or other defense material) to foreign governments are referred to as “FMS contracts” because they involve “Foreign Military Sales” under the Arms Export Control Act (“AECA”), 22 U.S.C. § 2751 et seq. Under that statute, the President and, by designation, the Department of Defense, may sell arms to friendly foreign governments either from stocks of arms or through procurement from American contractors. In procured Foreign Military Sales, the United States Government contracts with a foreign government, and then the United States Government contracts separately with the contractor. The contractor sells the items to the United States Government, which then resells to the foreign government.

In negotiating the SGB contract, the Government and Lockheed first entered *1328 into a letter contract on July 12, 1993; this contract was modified on September 13, 1993. The modification authorized Lockheed to spend no more than $272 million to perform the contract and also authorized Lockheed to begin performance even before agreement was reached on a final price. On November 12, 1993, Lockheed submitted a proposal to “definitize” the SGB contract. The parties conducted fact-finding in November and December 1993, and after this factfinding Lockheed submitted an updated proposal on February 21,1994.

Because of cash-flow problems with one of the purchasing foreign countries, Lockheed was asked to restructure its SGB contract proposal, and in compliance with that request Lockheed submitted a restructured proposal on June 16, 1994. A final update to the proposal followed on August 3, 1994. The parties engaged in further face-to-face negotiations at Wright Patterson Air Force in Ohio in late August 1994 and agreed to a contract price of $450,748,730 for 67 target pods and 72 navigation pods.

The parties established a certification date of September 22, 1994, and Lockheed certified that as of that date all “cost or pricing data” submitted in support of Lockheed’s proposal was “current, accurate, and complete.” The date of final contract “definitization” was October 25, 1994.

Normally, Lockheed estimated future performance of its production line, or “touch labor,” based on actual historical performance of such workers. Lockheed kept data on how long it took workers to perform tasks, and typically that data would show an increase in efficiency over time. However, as noted earlier, during the time that the SGB contract was being negotiated, Lockheed was planning to move, and ultimately did move, the location of some of its LANTIRN manufacturing tasks from Orlando to Ocala. Because of this expected location shift, Lockheed informed the Air Force that in preparing its proposal Lockheed could not use its normal labor cost-estimate method based on performance history but instead would use a theoretical construct known as “the Anderlohr method” to estimate its labor costs for the SGB contract.

“The Anderlohr method” is a way of estimating the “lost learning” that occurs when there is a line break or other disruption in manufacturing such as the move of some tasks from Orlando to Ocala. Under this method, although more than 600 LANTIRN pods had been produced (on prior contracts from late 1989 until late 1993) at the time of the SGB negotiations, Lockheed’s estimate was that final assembly tasks would be performed with the efficiency of the 85th pod rather than the 600th pod; Lockheed thus “proposed to start the learning curve for SGB at that point and assume” that efficiency on the SGB contract “would come down the learning curve at the same rate which had been experienced in the past.” (Doc. 370 ¶ 15). Although Lockheed’s normal estimation procedures — based on performance history — were used for other portions of LAN-TIRN production, for the “old Ocala scope” work for which there was likely to be a loss-of-learning effect from the line break, the Anderlohr method was used.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Marsteller v. Tilton
N.D. Alabama, 2021
Lockheed Martin Corp. v. Hegar
550 S.W.3d 855 (Court of Appeals of Texas, 2018)
In re Engle Cases
45 F. Supp. 3d 1351 (M.D. Florida, 2014)
Starling v. R.J. Reynolds Tobacco Co.
845 F. Supp. 2d 1215 (M.D. Florida, 2011)
L-3 Communications Corp. v. United States
99 Fed. Cl. 283 (Federal Claims, 2011)
Crassociates, Inc. v. United States
95 Fed. Cl. 357 (Federal Claims, 2010)
United States Ex Rel. Deering v. Physiotherapy Associates, Inc.
601 F. Supp. 2d 368 (D. Massachusetts, 2009)
United States v. Allison Engine Company, Inc.
471 F.3d 610 (Sixth Circuit, 2006)
United States Ex Rel. Sanders v. Allison Engine Co.
471 F.3d 610 (Sixth Circuit, 2006)
United States Ex Rel. DRC, Inc. v. Custer Battles, LLC
376 F. Supp. 2d 617 (E.D. Virginia, 2005)
In re Cardiac Devices Qui Tam Litigation
221 F.R.D. 318 (D. Connecticut, 2004)
Simmons v. United States
225 F.R.D. 688 (N.D. Georgia, 2004)
United States Ex Rel. Hayes v. CMC Electronics Inc.
297 F. Supp. 2d 734 (D. New Jersey, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
282 F. Supp. 2d 1324, 2003 U.S. Dist. LEXIS 21103, 2003 WL 22128833, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-campbell-v-lockheed-martin-corp-flmd-2003.