Alloy Surfaces Company, Inc.

CourtArmed Services Board of Contract Appeals
DecidedApril 9, 2020
DocketASBCA No. 59625
StatusPublished

This text of Alloy Surfaces Company, Inc. (Alloy Surfaces Company, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Alloy Surfaces Company, Inc., (asbca 2020).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Alloy Surfaces Company, Inc. ) ASBCA No. 59625 ) Under Contract No. W15QKN-04-D-1002-0014 )

APPEARANCES FOR THE APPELLANT: David Z. Bodenheimer, Esq. Jason M. Crawford, Esq. Jason C. Lynch, Esq. Crowell & Moring LLP Washington, DC

APPEARANCES FOR THE GOVERNMENT: Scott N. Flesch, Esq. Army Chief Trial Attorney Harry M. Parent III, Esq. Robert B. Neill, Esq. Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE WOODROW

This appeal involves a dispute as to the pricing of a delivery order (DO) for the manufacture of M211 infrared countermeasure decoy flares. Appellant Alloy Surfaces Company, Inc. (Alloy or appellant) held an Indefinite Quantity/Indefinite Delivery (IDIQ) contract with the United States Army (Army or government) for the procurement of M211 Infrared Countermeasure Decoys, which are fired from helicopters to avoid heat-seeking rounds. The Army awarded the contract in January 2004. In April 2006, the government requested a proposal for a substantial quantity of additional M211s to be procured under DO 0014 (DO 14).

During 2006, appellant was in the process of automating certain manufacturing processes and bringing two additional plants on-line. By early September 2006, Alloy completed DO 13, utilizing its automated manufacturing processes at its original plant.

Appellant submitted its proposal for DO 14 in April 2006. Its proposal did not contain any material and labor usage data related to DO 13; rather, it contained similar data from earlier jobs which were produced without the automated processes utilized in DO 13. In August 2006, the government and appellant began negotiations on the proposal which ultimately led to Modification No. P00025 and DO 14.

The government contends that it relied on defective material and usage rates when it negotiated the price for DO 14 and that it agreed to a higher price than it would have if it had access to the DO 13 data. On July 24, 2014, the contracting officer (CO) issued a Contracting Officer’s Final Decision (COFD) asserting that appellant provided defective cost or pricing data to the Army during the negotiation leading to the award of DO 14. The Army seeks $15,920,212 plus interest. This appeal followed. Both entitlement and quantum are before us.

We hold that job cost sheets prepared by Alloy during the production of DO 13 were management tools that contained both factual and judgmental information, but did not possess the requisite degree of certainty necessary for providing certified cost data to the government. In particular, at the time of price agreement on September 25, 2006, the reports were not sufficiently certain to be certified as “cost and pricing data” pursuant to the Truth in Negotiations Act, 10 U.S.C. § 2306a.

Finally, we hold that the Army fully was aware of the effect of automation on the pricing for the flares, but chose instead to rely on manufacturing data from earlier, non-automated jobs. As the Army acknowledged during its negotiations, the pricing of the non-automated jobs best reflected a compromise between the increased efficiency of automation and the inefficiency of increasing production. We conclude that having the data from DO 13 would not have shed light on the anticipated inefficiencies of qualifying new plants, installing new equipment, and hiring new workers, and, ultimately, would not have changed the price the government negotiated with Alloy. We sustain the appeal.

FINDINGS OF FACT

I. Prior Contract History

1. On July 7, 1999, the Army awarded Contract No. DAAE30-99-C-1084 (the 1999 contract) to Alloy for the production of a quantity of 6,800 M211 decoy flares (R4, tab 60 at 3; answer at 38).

2. The Army issued Modification No. P00041 under the 1999 contract with an effective date of March 28, 2003 (answer at 3). Modification No. P00041 is also known as Job No. 1516 (R4, tab 80 at 8; tr. 1/84-85).

3. In August 2005, Alloy completed delivery of 120,553 M211 decoy flares under Modification No. P00041 (Job 1516) (R4, tab 80 at 8).

II. The Base Contract

4. On January 23, 2004, the Army awarded Indefinite Quantity/Indefinite Delivery (IDIQ) Contract No. W15QKN-04-D-1002 (the 2004 contract) to Alloy for the procurement of 700,000 M211 Infrared Countermeasure Decoys (decoys, flares,

2 M211s, or M211 decoys), with a maximum value of $25,914,000 (R4, tab 1 at 3, 10, tab 74 at 5-6). Subsequent contract modifications progressively increased the maximum ceiling price to $200,548,507.00 (R4, tab 74 at 3).

5. Infrared countermeasure flares, or decoys, are devices used to protect helicopters from heat-seeking missiles. The M211 decoy consists of a metal case that’s nominally an inch square and eight inches long, filled with between 2,500 and 3,000 thin metal foils that have a special coating on them that reacts in the air to perform their countermeasure work to decoy heat-seeking missiles. (Tr. 1/179).

6. The 2004 contract incorporated Federal Acquisition Regulation (FAR) clauses 52.215-10, PRICE REDUCTION FOR DEFECTIVE COST OR PRICING DATA (OCT 1997), and 52.215-11, PRICE REDUCTION FOR DEFECTIVE COST OR PRICING DATA – MODIFICATIONS (OCT 1997) (R4, tab 1 at 35). According to FAR § 15.407-l(b)(l), “[t]he clauses give the Government the right to a price adjustment for defects in certified cost or pricing data submitted by the contractor, a prospective subcontractor, or an actual subcontractor.” FAR § 15.407-1(b)(1).

A. Previous Delivery Orders for M211 Decoy Flares

7. Prior to the award of DO 14 at issue in this appeal, the Army issued other delivery orders to Alloy for M211 decoy flares under the 2004 contract (answer ¶ 8). These delivery orders included:

• Delivery Order 1 on February 5, 2004 (R4, tab 2). • Delivery Order 6 on June 17, 2005 (R4, tab 25). • Delivery Order 7 on October 10, 2005 (R4, tab 30). • Delivery Order 8 on November 23, 2005 (R4, tab 34). • Delivery Order 11 on January 26, 2006 (R4, tab 44). • Delivery Order 13 on May 16, 2006 (R4, tab 52).

8. Alloy assigned job numbers relating to the work under both Modification No. P00041 (1999 contract) and the above delivery orders (2004 contract at issue):

Army Contract Reference Alloy Job No.

Modification No. P00041 Job No. 1516

Delivery Order 1 Job No. 1528

3 Delivery Order 6 Job No. 1573-1 Job No. 1573-2 Delivery Order 7 Job No. 1596

Delivery Order 8 Job No. 1601

Delivery Order 11 Job No. 1611

Delivery Order 13 Job No. 1626

(Compl. ¶ 8)

9. Army CO Sandra LaBell signed and awarded DO Nos. 6, 7, 8, 11, and 13 (R4, tabs 25, 30, 34, 44, and 52).

10. The Army knew that DO Nos. 6, 7, 8, 11, and 13 had been produced in Plant 1. In its cost proposal for DO 14, Alloy stated that it would add substantial amounts of equipment, including expanding Plant 2, starting production at Plant 3, and hiring 234 new employees. (Tr. 1/178; R4, tab 50 at 3; app. supp. R4, tab 2; tr. 1/61-62)

1. Delivery Order 13 Introduces More Efficient Manufacturing Processes

11. On May 16, 2006, the government placed DO 13 against the contract (R4, tab 52).

12. DO 13 called for the fabrication, test, and delivery of 33,379 M211 decoys in two lots, with a portion to be used for lot testing (R4, tab 52 at 5, tab 96 at 7).

13. DO 13 was produced in Plant 1, but, unlike previous delivery orders, Alloy manufactured DO 13 using all-new automated processes (tr. 2/180; R4, tab 96 at 8-9). The Army was aware that DO 13 was produced in Plant 1 (tr. 3/45-46).

14.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Universal Restoration, Inc. v. The United States
798 F.2d 1400 (Federal Circuit, 1986)
Walling v. Armbruster
51 F. Supp. 166 (W.D. Arkansas, 1943)
Sylvania Electric Products, Inc. v. United States
479 F.2d 1342 (Court of Claims, 1973)
Singer Co. v. United States
576 F.2d 905 (Court of Claims, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
Alloy Surfaces Company, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/alloy-surfaces-company-inc-asbca-2020.