Universal Restoration, Inc. v. United States

35 Cont. Cas. Fed. 75,612, 16 Cl. Ct. 214, 1989 U.S. Claims LEXIS 9, 1989 WL 3690
CourtUnited States Court of Claims
DecidedJanuary 19, 1989
DocketNo. 77-84-C
StatusPublished
Cited by6 cases

This text of 35 Cont. Cas. Fed. 75,612 (Universal Restoration, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Universal Restoration, Inc. v. United States, 35 Cont. Cas. Fed. 75,612, 16 Cl. Ct. 214, 1989 U.S. Claims LEXIS 9, 1989 WL 3690 (cc 1989).

Opinion

OPINION AND ORDER

TURNER, Judge.

Universal Restoration, Inc., successful on the merits, has applied under the Equal Access to Justice Act (EAJA), 28 U.S.C. § 2412(d) (Supp. IV 1986), for attorney fees and other expenses incurred in its contract action against the United States. For reasons discussed below, it is concluded that Universal is not entitled to an EAJA award for its efforts in this case.

I

The suit for which Universal now seeks an EAJA award emerged from its contract with defendant for the repair and restoration of areas within the National War College at Fort McNair in Washington, D.C. The contract was awarded to plaintiff on May 31, 1974. Plaintiff satisfactorily completed performance under the contract on September 23, 1975. During the course of performance, five contract modifications were agreed to by the parties; these modifications greatly increased the scope of the work so that what had started as a modest $65,000 contract grew into one for over $1,000,000.

The parties’ dispute concerned the Truth In Negotiations Act (TINA), 10 U.S.C. § 2306(f) (1970). The government took the position that TINA applied to its modified contract with Universal, that Universal had violated TINA by failing to disclose pricing data pertinent to the contract modifications, and that this failure entitled the government to withhold payment of some monies Universal had billed under the contract. After an odyssey through several fora, Universal obtained judgment for $107,368, plus interest, on January 15, 1988.

Resolution of the issues raised by Universal’s application requires an under[216]*216standing of the procedural history of the underlying dispute. The Armed Services Board of Contract Appeals (ASBCA or Board) was the first forum to address this controversy. That body initially found for Universal in a 3-2 decision. Universal Restoration, Inc., 82-1 BCA If 15,762 (ASBCA 1982) [1982 WL 7091]. While the Board agreed with the government that TINA applied to the contract, as modified, and that Universal had violated TINA by failing to disclose pricing data, a majority of the panel found that the non-disclosure had no. effect on the contract price. Id. On reconsideration, the Board reversed itself, again in a 3-2 decision in which, curiously, the vote of the judge who replaced a judge from the original majority made the difference. Universal Restoration, Inc., 83-1 BCA ¶ 16,265 (ASBCA 1983) [1983 WL 8440]. After its motion to vacate the reconsidered decision was denied, Universal Restoration, Inc., 84-1 BCA 1116,918 (ASBCA 1983) [1983 WL 13387], Universal appealed to this court under the Wunderlich Act, 41 U.S.C. §§ 321 et seq., 322 (1982). This court (White, S.J.) affirmed the Board’s actions. Universal Restoration, Inc. v. United States, 8 Cl.Ct. 510 (1985). On appeal, the Federal Circuit reversed. Universal Restoration, Inc. v. United States, 798 F.2d 1400 (Fed.Cir.1986). The cause was remanded to the ASBCA for proceedings consistent with the Federal Circuit’s decision; there, the Board denied the government’s motion for reconsideration and granted summary judgment for Universal. Universal Restoration, Inc., 88-1 BCA ¶ 20,394 (ASBCA 1987) [1987 WL 46076].

II

In its application for EAJA monies, Universal asserts that the position of the United States was not “substantially justified.” 28 U.S.C. § 2412(d)(1)(A). While conceding that defendant prevailed at some points in the process, Universal urges that these short-lived successes are not sufficient to show that defendant’s position was reasonable, since the decisions which defendant won “were overwhelmingly contrary to the evidence.” (Plaintiff’s Reply at 3). Further, plaintiff urges that then-existing case law was firmly contrary to defendant’s position. Finally, plaintiff asserts that even if defendant’s litigating position were otherwise reasonable, its post-remand motion to the Board for reconsideration was not. Universal seeks an award totalling $53,505.

In its Opposition, the government concedes that Universal is a “prevailing party” within the meaning of EAJA but questions the degree of success truly obtained since Universal advanced a number of contentions which the Federal Circuit, as well as the other fora, either rejected or chose not to address. Defendant urges, further, that even where Universal prevailed, it is not entitled to a fee award because the position of the government was “substantially justified” in light of then-existing case law. Finally, defendant contends that even if Universal could otherwise establish EAJA entitlement, it may not, as a matter of law, recover fees or expenses for its efforts before the Board related to a contract which predated the Contract Disputes Act of 1978, 41 U.S.C. §§ 601-13.

Ill

The EAJA provides:

[A] court shall award to a prevailing party other than the United States fees and other expenses ... incurred by that party in any civil action ... brought by or against the United States ... unless the court finds that the position of the United States was substantially justified or that special circumstances would make an award unjust.

28 U.S.C. § 2412(d)(1)(A). In the case at bar, the parties do not dispute that Universal is a “prevailing party” within the meaning of the act. Nor does the government allege the presence of “special circumstances [that] would make an award unjust.” Id. Instead, resolution of this matter hinges upon whether defendant’s position was “substantially justified.”

The Supreme Court recently defined “substantially justified” in the EAJA context as

[217]*217‘justified in substance or in the main,' that is, justified to a degree that could satisfy a reasonable person [, which] is no different from the ‘reasonable basis both in law and fact’ formulation [heretofore] adopted by [many of the circuits].

Pierce v. Underwood, — U.S. -, 108 S.Ct. 2541, 2550, 101 L.Ed.2d 490 (1988). The burden of demonstrating substantial justification rests with the government. Gavette v. Office of Personnel Management, 808 F.2d 1456,1465-6 (Fed.Cir.1986), quoting H.R. REP. 1418, 96th Cong. 2d Sess. 18, reprinted in 1980 U.S. CODE CONG. & ADMIN. NEWS 4984, 4997. Justification for the government’s position must be measured against the law as it existed when the government was litigating the case, not against new law enunciated at the conclusion of the case. Kay Manufacturing Co. v. United States, 699 F.2d 1376,1379 (Fed.Cir.1983); accord, Devine v. Sutermeister, 733 F.2d 892, 895 (Fed.Cir.1984); Essex Electro Engineers, Inc. v. United States, 4 Cl.Ct. 463, 465-6 (1984), affirmed,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sikorsky Aircraft Corporation v. United States 09-844c &
110 Fed. Cl. 210 (Federal Claims, 2013)
Raytheon Co. v. United States
105 Fed. Cl. 236 (Federal Claims, 2012)
West Bay Builders, Inc. v. United States
85 Fed. Cl. 1 (Federal Claims, 2008)
Corrigan v. United States
70 Fed. Cl. 665 (Federal Claims, 2006)
Orion International Technologies v. United States
66 Fed. Cl. 569 (Federal Claims, 2005)
Biener GmbH v. United States
35 Cont. Cas. Fed. 75,701 (Court of Claims, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
35 Cont. Cas. Fed. 75,612, 16 Cl. Ct. 214, 1989 U.S. Claims LEXIS 9, 1989 WL 3690, Counsel Stack Legal Research, https://law.counselstack.com/opinion/universal-restoration-inc-v-united-states-cc-1989.