Essex Electro Engineers, Inc. v. The United States

757 F.2d 247, 32 Cont. Cas. Fed. 73,263, 53 U.S.L.W. 2445, 1985 U.S. App. LEXIS 14719
CourtCourt of Appeals for the Federal Circuit
DecidedFebruary 25, 1985
DocketAppeal 84-941
StatusPublished
Cited by94 cases

This text of 757 F.2d 247 (Essex Electro Engineers, Inc. v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Essex Electro Engineers, Inc. v. The United States, 757 F.2d 247, 32 Cont. Cas. Fed. 73,263, 53 U.S.L.W. 2445, 1985 U.S. App. LEXIS 14719 (Fed. Cir. 1985).

Opinion

BALDWIN, Circuit Judge.

This is an appeal from a judgment of the United States Claims Court, Essex Electro Engineers, Inc. v. United States, 4 Cl.Ct. 463 (1984), denying appellant’s application for attorney fees and expenses under the Equal Access to Justice Act (EAJA), 28 U.S.C. § 2412 (1982). We hold that the Claims Court possesses jurisdiction to award attorney fees and expenses under the EAJA for cases commenced after October 1, 1982, and, on the merits, we affirm the denial of an award in this case.

Essex Electro Engineers, Inc. (Essex) applied for fees and expenses incurred in a bid protest suit in which Essex obtained a judgment declaring it to be a responsive bidder in a procurement conducted by the Federal Aviation Administration (FAA) and a permanent injunction barring award of the subject contract to any other bidder. Essex Electro Engineers, Inc. v. United States, 3 Cl.Ct. 277 (1983). The factual background is detailed in the lower court’s opinions, which we only summarize here.

Background

In August 1982, the FAA issued an invitation for bids (IFB) for the production of engine generator sets. The IFB specifications required that the engine run at a maximum synchronous speed of 1200 rpm. Forster Enterprises was the lowest bidder, Essex was the second lowest, and Introl Corporation was third lowest. Forster, in its bid, offered a Cummins engine which, according to its own accompanying descriptive material, did not meet the engine output requirement. Essex offered the same Cummins engine or an Allis-Chalmers engine. Although Essex provided no descriptive literature on the Cummins engine, it did supply two pages of a brochure applicable to a standard model Allis-Chalmers engine but which did not address engine output. The cover letter accompanying the Essex bid stated that, if there were any conflict between the general literature and the IFB specifications, the specifications would control. Introl offered a General Motors engine and supplied no descriptive literature. The FAA provisionally determined that Forster was the lowest responsive and responsible bidder.

Introl initiated a protest before the General Accounting Office (GAO) contending that it was the lowest responsive bidder on the basis that neither the Cummins engine nor the Allis-Chalmers engine met the IFB output requirements. The GAO determined that Forster’s bid was nonresponsive because Forster’s descriptive literature indicated that the Cummins engine would not meet the output requirement. The GAO also found Essex’s bid to be nonresponsive based on the Forster literature showing the Cummins engine unable to meet the output requirement, and on a complete brochure for the Allis-Chalmers engine obtained by the FAA which showed that the Allis-Chalmers engine normally operated at 1800 rpm and that modification would be needed to permit operation at the required 1200 rpm. The GAO refused to consider evidence submitted by Essex during the protest supporting compliance with the output requirement. Introl’s bid was deemed responsive based in part on descriptive literature submitted by Introl during the protest proceedings.

Relying on the GAO decision, the FAA awarded the contract to Introl. Forster unsuccessfully sought in the Claims Court to enjoin issuance of the contract to Introl. Essex then filed suit in the Claims Court asking for injunctive and declaratory relief restraining the FAA from awarding the contract to any bidder other than Essex.

*250 The government’s litigating position in the Claims Court consisted of three general arguments:

1) the agency action was rational;
2) the scope of judicial review of an agency’s pre-award procurement decision is very limited and both the agency’s and GAO’s determinations should be accorded strong deference; and
3) Essex was not treated unfairly.

The Claims Court concluded that the agency irrationally determined that Essex’s bid was ambiguous, the FAA and GAO irrationally refused to consider literature proffered by Essex showing compliance, and, therefore, that the agency procurement decision was irrational. The court also determined that the agency decision treated Essex unfairly insofar as literature favorable to Introl was considered but literature supporting Essex was not considered. Essex was awarded injunctive and declaratory relief. Upon determining that Essex was responsible, the FAA awarded Essex the contract.

Two months after the decision, Essex applied for attorney fees and expenses under the EAJA. The government opposed the application contending that the Claims Court lacks jurisdiction to award attorney fees or expenses under 28 U.S.C. § 2412(a) and (d) because that court is not a “court of the United States” as defined in 28 U.S.C. § 451, and that in any event, an award would be inappropriate because the litigating position of the United States was substantially justified.

The Claims Court decided that it had jurisdiction, relying on prior decisions of that court. On the merits, the court denied the application on the ground that although the government had failed in its argument that the agency action was rational, the government’s “argument to accord the agency latitude in its procurement decision was not an unreasonable position.” As an alternative ground for the denial, the court found that exigent circumstances made an award of fees and expenses against the government unjust.

Appellant Essex’s arguments on appeal include: the government’s position in defending the agency procurement decision was unreasonable because the agency committed a per se violation of the applicable regulations; the government failed to sustain its burden of proving substantial justification especially since the Claims Court found the agency decision irrational; the Claims Court decision improperly bars an award under the EAJA in suits brought for injunctive relief; and the court erred in deciding that an award of fees, under the circumstances, would be unjust.

The government argues that the Claims Court lacks jurisdiction to award EAJA fees in cases commenced in that court after October 1, 1982, and with respect to the merits, argues that its litigating position was substantially justified.

We deal with jurisdiction first.

OPINION

A. Jurisdiction

In Ellis v. United States, 711 F.2d 1571 (Fed.Cir.1983), we held that the Claims Court had jurisdiction to award fees under the EAJA in a transitional case begun before the Court of Claims, which was subsequently carried over by statute to the Claims Court, and then decided by that court after October 1,1982. Ellis left open the jurisdictional question for actions commenced on or after October 1, 1982. Id. at 1574 n. 3.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Meyer Group, Ltd. v. United States
129 Fed. Cl. 579 (Federal Claims, 2016)
Johnson v. McDonald
28 Vet. App. 136 (Veterans Claims, 2016)
Freddie Butts v. Robert A. McDonald
28 Vet. App. 74 (Veterans Claims, 2016)
Prochazka v. United States
116 Fed. Cl. 444 (Federal Claims, 2014)
Dellew Corp. v. United States
108 Fed. Cl. 357 (Federal Claims, 2012)
Sierra Nevada Corp. v. United States
107 Fed. Cl. 735 (Federal Claims, 2012)
Patrick v. Dept. Of Veterans Affairs
668 F.3d 1325 (Federal Circuit, 2011)
Global Computer Enterprises, Inc. v. United States
88 Fed. Cl. 350 (Federal Claims, 2009)
Gear Wizzard, Inc. v. United States
87 Fed. Cl. 218 (Federal Claims, 2009)
Totolo/King v. United States
87 Fed. Cl. 680 (Federal Claims, 2009)
RhinoCorps Ltd. v. United States
87 Fed. Cl. 673 (Federal Claims, 2009)
Dyonyx, L.P. v. United States
83 Fed. Cl. 460 (Federal Claims, 2008)
Metric Construction Co. v. United States
83 Fed. Cl. 446 (Federal Claims, 2008)
Former Employees of BMC Software, Inc. v. United States Secretary of Labor
519 F. Supp. 2d 1291 (Court of International Trade, 2007)
Erinys Iraq Ltd. v. United States
78 Fed. Cl. 518 (Federal Claims, 2007)
Ryan v. United States
75 Fed. Cl. 769 (Federal Claims, 2007)
Textron, Inc. v. United States
74 Fed. Cl. 277 (Federal Claims, 2006)
Independence Park Apartments v. United States
61 Fed. Cl. 692 (Federal Claims, 2004)
Federal Management Systems, Inc. v. United States
61 Fed. Cl. 364 (Federal Claims, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
757 F.2d 247, 32 Cont. Cas. Fed. 73,263, 53 U.S.L.W. 2445, 1985 U.S. App. LEXIS 14719, Counsel Stack Legal Research, https://law.counselstack.com/opinion/essex-electro-engineers-inc-v-the-united-states-cafc-1985.