Metric Construction Co. v. United States

81 Fed. Cl. 804, 2008 U.S. Claims LEXIS 137, 2008 WL 2170692
United States Court of Federal Claims·Decided May 21, 2008·No. No. 04-635C·Published·Cited by 8 cases

Opinion

OPINION AND ORDER

LETTOW, Judge.

In this contract case, plaintiff Metric Construction Co., Inc. (“Metric”) seeks equitable adjustments and damages respecting two related construction contracts awarded to Metric by the U.S. Department of the Navy (“government” or “Navy”) for work on San Nicolas Island, California, one of the Channel Islands located approximately 70 miles off the coast of California. The contracts concerned roadways and a Navy airfield on the island. Metric’s claims primarily turn on the Navy’s post-contractual installation of facilities on the island that allegedly hindered Metric’s landing of construction materials, but they also involve alleged defective specifications for asphalt at two particular locations on the airfield runway, failure by the Navy to provide contractually promised special components for the runway, and a requirement that Metric clean-up and remove soils contaminated through no fault of Metric. Metric initially sought a total of $7,906,092.74 in damages, although that amount was later reduced by certain concessions made thereafter.

The court conducted a nine-day trial, first in Seattle, Washington, and then Washington, D.C., with an intervening site visit to the naval installations at Point Mugu, California and on San Nicolas Island.

FACTS1

A. San Nicolas Island

Relatively small and isolated, San Nicolas Island is notable for its restrictive geography, topography, and usage.2 The island is home to a Naval Air Weapons Station associated with the Navy Air Stations at Point Mugu and China Lake and is also used as a site to train naval aviators for landings on aircraft carriers. The Navy controls access to the island. Roughly seven miles long and three miles wide (over twenty square miles in area), the interior of the island is gently rolling, with steep cliffs and gullies descending to the ocean. See generally National Park Service Pamphlet, www.nps.gov/chis/ forkids/upload/sannicolas2006website.pdf (last visited May 20, 2008). Significant populations of seabirds nest in the cliffs; northern elephant seals, harbor seals, and California sea Hons populate the beaches. Id. (A contour map of the island is appended to this opinion.) The most prominent man-made feature is a runway over 10,000 feet in length with an arresting gear at each end to simulate landing conditions on a Navy carrier. Rainfall is sparse, and the island is covered with desert vegetation. Archeological sites derived from its preexisting native population dot the island. San Nicolas Island often faces high winds, and the surrounding ocean has strong currents and can have large ocean swells. No sheltered harbor or dock is present. All deliveries to the island must be made by either plane or ocean-going barge suited to land on one of two exposed beaches. After completion of the contracts at issue in this case, the government constructed a barge-landing pier on one of the beaches to improve access to the island for delivery of materials and supplies.

B. The Contracts

Metric’s work as a contractor on the island first began in 1992. Tr. 880:4-6 (Test, of Thomas P. Miller, President, Metric Construction).3 In August 1994, Metric was awarded Contract No. N62474-94-C-6807 (the “airfield contract”), entitled Repair Air[808]*808field Pavement at the Naval Air Weapons Station on San Nicolas Island, California. PX 2 (Airfield Solicitation, Offer, and Award). This contract called for Metric to make improvements and repairs to the Navy’s airfield runway on the island. In September 1998, Contract No. N68711-98-C-5553 (the “roadway contract”) was awarded to Metric, entitled Roadway and Storm Drainage Repair Effort at San Nicolas Island, California. DX 1008 (Roadway and Airfield Contract Provisions) at 353-60. The plans and specifications for both projects were prepared by the Navy, which administered the projects. PX 1 (Airfield Repair Plans); PX 2 (Airfield Solicitation, Offer, and Award); DX 1001 (Expert Report of Patti Jones, an expert retained by the government (Aug. 28, 2006)) (“Jones Report”) at 142-43 (Modification P00001 of Roadway Contract); DX 1008 (Roadway and Airfield Contract Provisions) at 353-60.

Both contracts required Metric to ship materials, equipment, and machinery to the island by ocean-going barge. DX 1008 (Roadway and Airfield Contract Provisions) at 102. The roadway and airfield contracts adopted Section 01600, Special Clauses Applying Only to Work on San Nicolas Island (“Special Clauses”), to govern procedures for landing materials and operations, including special provisions for use of the beaches and for environmental protection. See DX 1008 (Roadway and Airfield Contract Provisions) at 356. The contract explicitly provided that “the delivery of materials to San Nicolas Island is often the critical activity (longest duration)” affecting performance. Id. § 1011.1.5.1.2, at 43. The materials required for the airfield and roadway contracts included considerable amounts of aggregate, cement, asphalt, sand, gravel, and other construction materials that had to be moved to the island. Metric also had to install construction facilities such as an asphalt plant on the island. DX 1008 (Roadway and Airfield Contract Provisions) at 151-52.

For deliveries of materials and equipment to the island, the contracts designated two barge landing sites: Sissy Cove and Daytona Beach. DX 1008 (Roadway and Airfield Contract Provisions) at 104-05. Because landings had to be made on one of these two exposed beaches, adverse weather conditions could prevent deliveries for periods of time. See DX 1008 (Roadway and Airfield Contract Provisions) at 104; Tr. 76:1 to 79:17 (Test, of George Kostelny, former Metric Superintendent of San Nicolas Island projects) (stating that Metric used a weather consultant to forecast surf and winds but that occasionally unexpected conditions made it difficult or impossible for the barge to land even when the weather was expected to be favorable). Because of the challenges of landing barges at the beach-landing sites, the Special Clauses addressed aborted or impossible barge landings:

If the Contractor’s attempt to land his barge is not successful due to weather and/or high surf conditions—or—if data [are] available which proves that barge landing is impossible, then sufficient justification may exist for a no cost time extension.

DX 1008 (Roadway and Airfield Contract Provisions) at 104 (emphasis added). The number of successful landings varied from year to year based upon the conditions encountered. Tr. 912:6-21 (Miller). Because of the island’s distance from the California coast, approximately a full day was required to complete a trip to the island from either Point Mugu, Point Hueneme (the Navy’s chief Seabee base located near Point Mugu), or Terminal Island, where materials were loaded for delivery. Tr. 511:4 to 518:3, 761:8 to 763:1 (Test, of Elon Holmes, a project manager for Metric). The contracts also provided that the Navy had priority over Metric in using the beach-landing sites. DX 1008 (Roadway and Airfield Contract Provisions) at 104; Tr. 79:25 to 80:8 (Kostelny).

C. Beach Landings

When Metric submitted its bids for the projects, it based its costs on use of an oceangoing barge that it purchased in 1994 which was too large to land at Sissy Cove but had landed successfully at Daytona Beach during prior projects by Metric at San Nicolas Island. Tr.

Free access — add to your briefcase to read the full text and ask questions with AI

Metric Construction Co. v. United States, 81 Fed. Cl. 804, 2008 U.S. Claims LEXIS 137, 2008 WL 2170692 (uscfc 2008).

81 Fed. Cl. 804 (Metric Construction Co. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Al Ghanim Combined Group W.L.L.
Armed Services Board of Contract Appeals, 2026
KUNJ Construction Corporation
Armed Services Board of Contract Appeals, 2024
Magnus Pacific Corporation v. United States
133 Fed. Cl. 640 (Federal Claims, 2017)
Zafer Taahhut Insaat Ve Ticaret A.S. v. United States
833 F.3d 1356 (Federal Circuit, 2016)
Sikorsky Aircraft Corp. v. United States
102 Fed. Cl. 38 (Federal Claims, 2011)
Jay Cashman, Inc. v. United States
88 Fed. Cl. 297 (Federal Claims, 2009)
Scott Timber, Inc. v. United States
86 Fed. Cl. 102 (Federal Claims, 2009)
Ramah Navajo School Board, Inc. v. United States
83 Fed. Cl. 786 (Federal Claims, 2008)