Metric Construction Co. v. United States

80 Fed. Cl. 178, 2008 U.S. Claims LEXIS 5, 2008 WL 90087
CourtUnited States Court of Federal Claims
DecidedJanuary 7, 2008
DocketNo. 04-954 C
StatusPublished
Cited by3 cases

This text of 80 Fed. Cl. 178 (Metric Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Metric Construction Co. v. United States, 80 Fed. Cl. 178, 2008 U.S. Claims LEXIS 5, 2008 WL 90087 (uscfc 2008).

Opinion

OPINION

BUSH, Judge.

Metric Construction Company, Inc. (Metric) seeks $2,100,340, plus interest, court costs and attorneys fees, for costs it incurred during the construction of a building for the United States Army Corps of Engineers (Corps).2

[180]*180BACKGROUND

In 1999, Metric was awarded Contract No. DACA05-99-C-0030 (contract) to construct the Deployable Medical Systems Warehouse (warehouse) at Hill Air Force Base in Utah. Compl. at 2. When the warehouse roof developed serious leaks, the Corps required Metric to install a new roof. Metric’s claims before this court stem largely from the costs Metric incurred repairing water damage from the roof leaks, replacing damaged property in the warehouse and installing the second roof. On March 30, 2004, Metric submitted a certified claim for $2,173,091.85 to the Corps for these costs, but never received a final decision from the contracting officer.

Jurisdiction over Metric’s claims is undisputed and exists pursuant to 41 U.S.C. § 609(a)(1) (2000). Metric pled three theories of entitlement to relief in this court: breach of contract, constructive change/extra work, and breach of implied warranty. Compl. at 5-6. These claims survived defendant’s motion for summary judgment, primarily because of factual disputes related to the Corps’ design of structural steel underlying the roof and the issue of whether the Corps’ design specifications and communications with Metric misrepresented information critical to proper roof installation. See Metric Constr. Co. v. United States, 73 Fed.Cl. 611, 614-17 (2006).

Trial was held in Seattle, Washington in March 2007. The court has before it the trial transcript (Tr.), trial exhibits (DX and TX), and the parties’ post-trial briefs (PL’s Br., Def.’s Br., and PL’s Reply). This matter is now ripe for decision.

DISCUSSION

I. Issues Being Tried

Metric now relies on a relatively straightforward theory of entitlement to an equitable adjustment to the contract for costs it incurred related to roof leaks at the warehouse. Metric alleges that the Corps’ specifications for the steel underlying the roof were defective, and that Metric relied on those specifications. Metric also alleges that the defective specifications, and related communication by the Corps, were misrepresentations upon which Metric relied to its detriment.

Although defendant has a different theory of the case, alleging that Metric chose a roof system incompatible with the Corps’ building design, in the court’s view the most important analysis here, after trial, is whether plaintiff has met its burden to prove the elements of its entitlement theory. To the extent that defendant’s framing of the legal issues central to this dispute fails to persuade the court, the court must review the evidence supplied by both parties to see whether it supports or rebuts plaintiffs arguments. Earlier in this litigation, the court rejected defendant’s argument that, as a matter of law, Metric’s claims must be dismissed because Metric failed to produce a workable roof in response to a performance specification, holding that plaintiffs theory of entitlement was plausible, if proved by evidence at trial.3 See Metric Construction, 73 Fed.Cl. at 615 (noting that defendant’s “argument does not directly refute Metric’s contention that the Corps’ plans and specifications were misleading and erroneous and that the information contained therein impaired Metric’s ability to choose the correct roof product for the building when it was carrying actual loads”).

Once again, the court is not persuaded by defendant’s arguments, or the evidence offered at trial, that this dispute turns on the fact that Metric was allowed to choose the roofing system which would work on top of [181]*181the steel structure designed by the Corps. There is no dispute that the roof of the warehouse was a performance specification. See Metric, 73 Fed.Cl. at 615. But all of the relevant testimony at trial confirmed that the structural steel framework to which the roofing system was attached was a design specification. See Tr. at 586 (Mr. Griffes); 605 (Mr. Miller); 659-60 (Mr. Willard); see also Conner Bros. Constr. Co. v. United States, 65 Fed.Cl. 657, 685 (2005) (stating that “detailed measurements, tolerances, materials, and elaborate instructions as to how to perform the contract are of a design nature”) (citation omitted). Because the steel framework was designed by the Corps and Metric was allowed no deviations from the Corps’ design, the steel framework design specification carries with it certain responsibilities on the part of the government. See Summit Timber Co. v. United States, 230 Ct.Cl. 434, 677 F.2d 852, 857 (1982) (noting that in some cases “the government is liable for damage attributable to misstatements of fact (in a contract or specifications) which are representations made to the contractor”) (citations and internal quotations omitted). Because Metric’s entire case is now based on alleged defects in, or misrepresentations regarding, the design of the structural steel members underlying the roofing system, defendant’s argument regarding Metric’s responsibility to install an appropriate roofing system in response to the Corps’ performance specification is inapposite to the issues being tried in this case.4

Instead, the court must review the evidence proffered by the parties to see whether the specifications concerning the steel members underlying the warehouse roof were defective, and were relied upon by Metric in its roofing installation. The court must also determine whether the specifications and/or communication from the Corps misrepresented the steel framework of the warehouse, and whether Metric relied upon this misrepresentation and incurred costs as a result. Finally, the court must determine what portion of the stipulated amount of Metric’s incurred costs related to roof leaks was proved to be related to Metric’s reliance on either the steel specifications or communication from the Corps. But first, some review of the evidence concerning the warehouse’s design and construction is warranted.

II. Building and Roof Construction

A. Relevant Evidence

Both parties called witnesses with personal knowledge of Metric’s performance of the contract. Testifying for plaintiff were: Mr. Thomas Phillip Miller, president of Metric; Mr. Mark Green, who was part-owner of Professional Raingutter Service, Inc., Metric’s roofing subcontractor; and Mr. Stuart Burnell, who works for Hainline & Associates, Inc., the construction management company which directed the work on the warehouse after disputes arose between Metric and the Corps. Testifying for defendant was Mr. Tim H. Willard, a project engineer for the Corps involved with the warehouse construction project.

In addition, both parties provided expert testimony. Testifying for plaintiff were: Mr. Burnell, an expert in construction estimating, who functioned both as an expert and percipient witness; Mr. Daryl Unrue, a roofing and waterproofing consultant; and Mr. Charles Griffes, a structural engineer. Testifying for defendant were: Mr. Richard S. Koziol, a roofing expert; and Mr. Raymond H.R. Tide, a structural engineer.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
80 Fed. Cl. 178, 2008 U.S. Claims LEXIS 5, 2008 WL 90087, Counsel Stack Legal Research, https://law.counselstack.com/opinion/metric-construction-co-v-united-states-uscfc-2008.