J. L. Simmons Company, Inc. v. The United States

412 F.2d 1360, 188 Ct. Cl. 684, 1969 U.S. Ct. Cl. LEXIS 45
CourtUnited States Court of Claims
DecidedJuly 16, 1969
Docket186-59
StatusPublished
Cited by87 cases

This text of 412 F.2d 1360 (J. L. Simmons Company, Inc. v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J. L. Simmons Company, Inc. v. The United States, 412 F.2d 1360, 188 Ct. Cl. 684, 1969 U.S. Ct. Cl. LEXIS 45 (cc 1969).

Opinion

PER CURIAM:

This case was referred to Trial Commissioner Louis Spector with directions to make recommendations for conclusions of law on plaintiff’s motion for partial summary judment and defendant’s cross motion for partial summary judgment under the order of reference and Rule 99(c). The commissioner has done so in an opinion and report filed on January 21, 1969, wherein such facts as are necessary to the opinion are set forth. Plaintiff requested the court to adopt the commissioner’s report with one exception and defendant requested the court to review the report in its entirety. Briefs were filed by the parties and the case was submitted to the court on oral argument of counsel. Since the court agrees with the commissioner’s opinion and recommended conclusion of law with certain changes and modifications, it hereby adopts the same, as hereinafter set forth, as the basis for its judgment in this case.

Therefore, it is concluded that with respect to claims covered by the Veterans’ Administration Contract Appeal Board’s decision of May 31, 1967, plaintiff’s motion for partial summary judgment is granted, defendant’s cross motion is denied, and plaintiff is entitled to recover and judgment is entered for plaintiff in the sum of $480,956.43. Plaintiff is also entitled to recover on Claim No. 3, Part A., the amount of recovery to be determined pursuant to Rules 47(c) and 64(e). Plaintiff is not entitled to recover on its claim for interest and as to that claim, the petition is dismissed. Plaintiff’s petition is also dismissed with respect to the claim for bond premiums, except to the extent that this claim may be relevant in further proceedings under Rules 47(c) and 64(e).

Commissioner Spector’s opinion, as modified by the court, is as follows:

To establish the present posture of this venerable case, and to know how best to proceed with it from here, one must perforce describe where it has been. Its travels rival those of Odysseus, and the Wunderlich Act 1 has represented to it obstacles as formidable as Scylla and Charybdis.

In United States v. Carlo Bianchi & Co., 2 the Supreme Court described the chronology of that case as constituting “delay at its worst,” and it sought by its ruling therein to ameliorate such delays in the future. Regretfully, Bianchi will have to step aside for a new champion.

On October 5, 1949, the plaintiff undertook to construct a hospital and related buildings and facilities for the Veterans’ Administration at Chicago, Illinois. ■ The contract price was $6,985,905, and the completion date September 18, 1951. Work was actually completed April 30, 1953. The events from which this litigation arose relate primarily to the *1362 pile foundation for the main hospital building.

The specifications, which were prepared by the defendant, are a classic example of “design” specifications, and not “performance” specifications. 3 In other words, in these specifications, the defendant set forth in precise detail the materials to be employed and the manner in which the work was to be performed, and plaintiff was not privileged to deviate therefrom, but was required to follow them as one would a road map. In contrast, typical “performance” type specifications set forth an objective or standard to be achieved, and the successful bidder is expected to exercise his ingenuity in achieving that objective or standard of performance, selecting the means and assuming a corresponding responsibility for that selection.

This opinion need not be burdened with the more than ample detail spread over an unusually extensive administrative and judicial record underlying the case. Suffice it to say that Section 2 of the contract specifications dealing with the pile foundation contained the most definite and precise requirements with respect to the piles to be installed. They were to be cast-in-place concrete type piles cased with a steel shell, and were to be one of three types. Plaintiff selected a pedestal-type pile, described in the specifications as follows:

2-6 (b) By driving a casing and removable core to the required penetration and bearing, removing core, placing at least 4% cubic feet of concrete in the casing, replacing the core, and driving the apparatus into the concrete to form a base, removing the core and inserting a shell which shall rest upon and be sealed by the concrete at the lower end, removing casing and filling shell with concrete.

Furthermore, bidders were advised that defendant’s design for this site was based on a working load of 40 tons per pile for the main hospital building, and 30 tons per pile for other buildings and structures. The specifications further provided that one pile of each type was to be tested prior to the commencement of pile driving operations. A 40-ton pile was to be loaded with 80 tons, and a 30-ton pile with 60 tons, following which certain limitations upon settlement were imposed before the tests could be considered satisfactory.

As originally prepared by the defendant, the specifications required preexca-vation, or coring, to penetrate materials overlying a sand and gravel stratum at which level the piles were designed to encounter the necessary resistance to produce bearing capacity. Preeoring is required by a designer to avoid excessive movement of piles during installation resulting from displacement of earth, it being a well-established truth that two objects cannot occupy the same space at the same time. Excessive displacement occurs when there is too high a concentration of piles in too small an area. However, by an amendment to the invitation for bids prior to bid opening, the defendant specifically eliminated this specification provision for preexcavation or coring, thereby indicating that the designer did not contemplate displacement problems at this particular site. This was further indicated by the fact that the pedestal-type concrete pile employed is not one that can be reseated and re-driven, should movement later occur.

The contract further set forth with complete specificity the pile driving equipment to be employed, and the procedures for their use, and these were approved in advance. Required bearing for 40-ton piles would be indicated when the penetration under the last 32 blows of a hammer, delivering 15,000 foot pounds of energy, did not exceed 6 inches, and the penetration under the last seven blows did not exceed 1 inch.

The specifications required that a completed pile was not to be out of plumb more than Y% inch per foot, and the *1363 movement of pile groups, or clusters, was not to exceed 1 inch for groups of six or less, 1% inches for groups of seven to 10, and 2 inches for groups of 11 or more piles. After all pile shells in a particular group were in place, and had been inspected and approved by defendant, plaintiff was to fill them with concrete, as above described.

In summary, these were specifications of the type which have traditionally been held to carry with them the implied warranty by the party preparing them that if followed, a satisfactory result will pertain. 4

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Skanska USA Civil Southeast, Inc.
Armed Services Board of Contract Appeals, 2025
Philips Lighting North American Corporation
Armed Services Board of Contract Appeals, 2024
Hamp's Construction LLC
Armed Services Board of Contract Appeals, 2024
L.S. Black-Loeffel Civil Constructors JV
Armed Services Board of Contract Appeals, 2023
Sheffield Korte Joint Venture
Armed Services Board of Contract Appeals, 2023
ECC International, LLC
Armed Services Board of Contract Appeals, 2020
Meridian Engineering Company v. United States
122 Fed. Cl. 381 (Federal Claims, 2015)
Idaho Power Co. v. United States
105 Fed. Cl. 141 (Federal Claims, 2012)
Fireman's Fund Insurance v. United States
92 Fed. Cl. 598 (Federal Claims, 2010)
LB&B Associates Inc. v. United States
91 Fed. Cl. 142 (Federal Claims, 2010)
Metric Construction Co. v. United States
81 Fed. Cl. 804 (Federal Claims, 2008)
Caddell Construction Co. v. United States
78 Fed. Cl. 406 (Federal Claims, 2007)
Travelers Casualty & Surety of America v. United States
74 Fed. Cl. 75 (Federal Claims, 2006)
Daewoo Engineering & Construction Co. v. United States
73 Fed. Cl. 547 (Federal Claims, 2006)
Clearwater Constructors, Inc. v. United States
71 Fed. Cl. 25 (Federal Claims, 2006)
Orlosky Inc. v. United States
68 Fed. Cl. 296 (Federal Claims, 2005)
Conner Brothers Construction Co. v. United States
65 Fed. Cl. 657 (Federal Claims, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
412 F.2d 1360, 188 Ct. Cl. 684, 1969 U.S. Ct. Cl. LEXIS 45, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-l-simmons-company-inc-v-the-united-states-cc-1969.