Skanska USA Civil Southeast, Inc.

CourtArmed Services Board of Contract Appeals
DecidedApril 3, 2025
Docket61220, 61347
StatusPublished

This text of Skanska USA Civil Southeast, Inc. (Skanska USA Civil Southeast, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Skanska USA Civil Southeast, Inc., (asbca 2025).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeals of - ) ) Skanska USA Civil Southeast, Inc. ) ASBCA Nos. 61220, 61347 ) Under Contract No. N40085-10-C-3006 )

APPEARANCE FOR THE APPELLANT: Arnie B. Mason, Esq. Williams Mullen PC Tysons, VA

APPEARANCES FOR THE GOVERNMENT: Allison McDade, Esq. Navy Chief Trial Attorney Elizabeth C. Tosh, Esq. Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE ARNETT

Skanska USA Civil Southeast, Inc. (Skanska or appellant) seeks compensation for claimed additional costs arising from the removal of interior timber bearing piles during the performance of a firm fixed-price contract with the Department of the Navy (the government or Navy) for the demolition of two existing piers (Piers 4 and 5) and construction of a new pier at the Norfolk Naval Shipyard (NNSY) in Portsmouth, VA. Skanska attributes its claimed additional costs to either defective specifications or a differing site condition (DSC) (app. br. at 4). In support of its defective specification argument, Skanska cites as a defect a note in the solicitation instructing bidders to assume that the timber piles were treated with creosote 1 (id. at 2-3). Skanska argues that it was legally impossible to fully extract the interior bearing piles within the dredge limits in the permit because the piles were not treated with creosote (id. at 5, 88-90). Next, Skanska asserts that the lack of creosote treatment constitutes either a Type I or Type II DSC (id. at 91-101). Finally, Skanska contends that the Navy’s characterization of the note as a “worst-case scenario” for bidders constitutes a constructive change (id. at 101-03).

For the reasons explained in detail below, we conclude that the evidence does not support finding a defective specification, a Type I or Type II DSC, or a constructive change because Skanska should have reasonably anticipated the conditions it encountered. Therefore, we deny the appeals.

1 Creosote is a type of tar produced from coal and commonly used to preserve timber (app. supp. R4, tab 69 at 24). FINDINGS OF FACT

The Project:

1. On May 26, 2010, the Navy solicited proposals for a firm fixed-price design- bid-build project (the Project) to demolish Piers 4 and 5 and construct a new replacement pier at the NNSY (R4, tab 1 at 1, 3 2). In addition, the successful offeror was required to dredge the area to a specified depth in compliance with a U.S. Army Corps of Engineers (USACE) permit (R4, tab 5 at 2; app. supp. R4, tab 16 at 4). Jutting into the Elizabeth River, Piers 4 and 5 were “closed face” piers supported by thousands of approximately 70-foot-long interior bearing piles buried in soil and enclosed with tongue and groove concrete sheet piles to hold the soil in place underneath each pier (app. resp. to gov’t Proposed Finding of Fact (PFOF) ¶¶ 9, 18, 87; tr. 2/76, 163).

2. Although the solicitation included a full design prepared by the designer of record, MN3M 3 (the DOR), the successful offeror was required to have a licensed engineer design the means, methods, and procedures for demolition of the existing piers (tr. 4/68-69; R4, tab 7 at 6-7). Lacking experience with pier demolition design (tr. 5/20-21), the DOR met with three prospective contractors, including Skanska, early in the design to solicit input on the Project and “how they might approach the pier demolition” (tr. 4/81-85, 5/66-68). Feedback included concern that the “demolition aspects of this project was (sic) going to be one of the more challenging aspects” (tr. 4/85). None inquired whether the existing timber piles were treated with creosote (tr. 4/83).

3. Prior to issuing the solicitation, the Navy conducted a site visit; however, attendees, including Skanska, were unable to see or inspect the interior bearing piles supporting the piers because the piles were under the piers and obscured behind concrete sheet piles (app. supp. R4, tab 15 at 3; app. resp. to gov’t PFOF ¶ 11; tr. 1/134-35).

4. Each offeror was required to submit a Technical Approach with a “narrative that describes the construction means and methods” for demolition of the existing piers, including “ensuring the existing concrete sheet pile walls remain in place while the interior fill and timber piles are removed from existing piers 4 and 5” (R4, tab 17 at 8). To prevent the soil under each pier from spilling into the water at this operational nuclear shipyard, the soil had to be removed and excavated while the

2 Documents in the Rule 4 file are numbered using letter prefixes and leading zeros. We have dropped the prefix and leading zeros in this decision for ease. 3 MN3M was a joint venture comprised of Moffat & Nichol and MMN Design Group (tr. 4/68). 2 concrete sheet pile walls forming the perimeter of each pier remained in place (id.; tr. 2/44, 49-50).

5. There were three types of timber piles to be removed during demolition: (1) interior bearing piles buried almost completely in soil beneath each pier and driven into the riverbed; (2) batter/brace piles 4 which were interior bearing piles driven at an angle; and (3) fender piles which were in the water and driven into the riverbed around the exterior perimeter of each pier to prevent damage from ships (tr. 2/35; app. resp. to gov’t PFOF ¶¶ 25-26). The interior bearing piles are the subject of this litigation.

6. On July 29, 2010, Skanska submitted its Technical Proposal (the Proposal) highlighting its prior experience with projects at NNSY, including the Crane Rail Interconnect and Oil Waste/Waste Oil Collection System (Crane Rail Project) (ex. A-1 at 4192-04). The Proposal depicted the conditions under the piers as “muck” and reflected Mean Low Water 5 (MLW) at or above the tops of the interior piles (id. at 4261). It stated, “The Skanska Engineer has developed a detailed sequence of construction and methodology for the demolition of Pier 4 and 5” (id. at 4245-48, 4268). Skanska’s thirteen-step sequence included Step 8, which focused on removing the existing planks, decking, timber caps and timber piles (id. at 4246). It stated, “Existing interior supporting timber piles will be removed by either a crane located on top of the relieving platform, a barge or derrick crane in the same manner as previously described for the timber piles, cut by chain saw and/or a shear mounted on an excavator, and loaded to a barge” (id. at 4246-47) (emphasis added). Step 8 references a prior section of the Proposal regarding fender piles which provided for removal by “either of” the following methods “depending on the initial resistance and condition of the piles:” 1) “chocking the pile by direct line pull by the crane” or 2) using a vibratory hammer with an extractor attachment 6 (id. at 4242). Further, it stated,

For piles that are not visible and/or broken off at on (sic) near the mud line will be located, inspected by divers, and again referenced to the reference drawings. Divers will assist by attaching lines to piles that are below the water line but above the mud line for removal under method one. In cases where piles can not be removed by this method, a diver will assist with guiding a ‘Randall Straw’ pipe . . . pile over the existing piling. The pipe pile will then be vibrated down around the pile to break the pile free. The

4 Batter/brace piles were only installed on Pier 4 (gov’t br. at 8; app. PFOF ¶ 76). 5 MLW is the average water level at low tide (tidesandcurrents.noaa.gov/glossary). 6 Testimony clarified that Skanska planned to use both the vibratory hammer with the crane “in combination” to extract the interior bearing piles embedded in soil (tr. 1/176-77). 3 pipe pile and timber pipe are then extracted together. Once the piles are removed from the water, air will be introduced into the pipe pile which will allow the timber pile to be extracted from the pipe pile.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

International Data Products Corp. v. United States
492 F.3d 1317 (Federal Circuit, 2007)
J. L. Simmons Company, Inc. v. The United States
412 F.2d 1360 (Court of Claims, 1969)
Blake Construction Company, Inc. v. The United States
987 F.2d 743 (Federal Circuit, 1993)
Neal & Company, Inc. v. United States
121 F.3d 683 (Federal Circuit, 1997)
Comtrol, Inc. v. United States
294 F.3d 1357 (Federal Circuit, 2002)
bell/heery v. United States
739 F.3d 1324 (Federal Circuit, 2014)
Miller Elevator Co. v. United States
39 Cont. Cas. Fed. 76,635 (Federal Claims, 1994)
Neal & Co. v. United States
41 Cont. Cas. Fed. 77,003 (Federal Claims, 1996)
Oak Adec, Inc. v. United States
37 Cont. Cas. Fed. 76,220 (Court of Claims, 1991)
Flippin Materials Co. v. United States
312 F.2d 408 (Court of Claims, 1963)
Perini Corp. v. United States
381 F.2d 403 (Court of Claims, 1967)
Foster Wheeler Corp. v. United States
513 F.2d 588 (Court of Claims, 1975)
Jennie-O Foods, Inc. v. United States
580 F.2d 400 (Court of Claims, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
Skanska USA Civil Southeast, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/skanska-usa-civil-southeast-inc-asbca-2025.