Blake Construction Company, Inc. v. The United States

987 F.2d 743, 1993 WL 45083
CourtCourt of Appeals for the Federal Circuit
DecidedApril 13, 1993
Docket92-5092
StatusPublished
Cited by57 cases

This text of 987 F.2d 743 (Blake Construction Company, Inc. v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blake Construction Company, Inc. v. The United States, 987 F.2d 743, 1993 WL 45083 (Fed. Cir. 1993).

Opinion

MAYER, Circuit Judge.

The United States appeals the judgment of the United States Court of Federal Claims, * 25 Cl.Ct. 177 (1992), awarding an equitable adjustment to Blake Construction Company, on behalf of its subcontractor Steiny and Company, Inc., for additional costs incurred under its contract with the Department of the Navy. We reverse.

BACKGROUND

Blake Construction Company contracted with the Department of the Navy to construct replacement medical facilities at the San Diego Naval Regional Medical Center. The contract called for the construction of four new structures, including a mechanical equipment building, a warehouse, an auxiliary building, and a nursing tower. A corridor of approximately 1,000 feet ran most of the length of the ground floors of the buildings and was designed to enable people, supplies and utilities to move between the buildings. It is the manner in which the contract required electrical conduits to be installed along this corridor as part of an electrical feeder system that gives rise to the controversy before us.

Specifications governing the installation of the electrical feeder system were prepared by a joint venture architect and engineering firm and were made available to bidders. Power coming into the hospital from outside high voltage lines was to be reduced to a variety of lower voltages by transformer units and then distributed throughout the buildings via a branching series of ever smaller lines conveyed by electrical conduits. The series of drawings pertaining to the installation of the electrical conduits within and between the buildings depicted the conduits as installed overhead along the west side of the corridor, hanging either exposed from utility racks, or hidden from view by a dropped ceiling. These drawings also included notes describing the drawings as “diagrammatic.” On some drawings the notes stated: “All feeder details & sections are diagrammatic. Contractor shall relocate any/all conduits as per existing conditions to coordinate with all other trades.” On other drawings the notes similarly stated: “All feeder locations are diagrammatic. Contractor shall relocate feeders as per existing conditions and shall coordinate with other trades.”

After Blake was awarded the contract, and before any construction of the buildings had commenced, its electrical subcontractor Steiny and Company, Inc. began installation of the electrical feeder system in an underground concrete duct bank along the planned path of the corridor. When the Navy challenged this installation method, Steiny asserted that the contract’s “diagrammatic” notes permitted the contractor to relocate the electrical conduits so as to avoid conflict with other trades, such as mechanical and plumbing, which were to be installed, in the corridor. The Navy issued a stop work order informing Blake that the underground duct bank did not comply with the contract specifications, and directed that the conduits be installed over *745 head within the corridor as depicted in the drawings. Blake notified the Navy that it considered this directive to be a constructive change to the contract for which it was entitled to more money. When the Navy reissued its directive, Steiny removed the underground bank under protest.

After the corridor was constructed and ready to receive utilities, a conflict arose between Steiny and the mechanical subcontractor over the location of their respective trades. To alleviate the interference, Steiny agreed to move to the east side of the corridor. In one thirty foot section, the electrical conduits had to be placed outside the corridor, and in another they were located outside the planned route of the feeders. Both changes were approved by the Navy. In addition, Steiny generally had to weave the conduits between and around the other utilities in the corridor.

Blake submitted a claim on behalf of Steiny for an equitable adjustment to cover the costs of relocating the underground duct bank to the overhead placement. The contracting officer denied Blake’s claim and this action in the Claims Court followed. After a trial, the Claims Court held that Blake was entitled to recover $1,679,-260 plus interest, representing the cost incurred pursuant to the Navy’s directive to install the conduits overhead in the congested corridor. The government appeals.

DISCUSSION

The central question in this case is whether the contract gave Blake discretion to choose an underground location for installing the electrical feeder system. The point of disagreement is the meaning of the notes indicating that the drawings were “diagrammatic” and requiring the contractor to relocate in order to coordinate with other trades. The word “diagrammatic” is not defined by the contract.

Blake urges that resolution of this case turns on the characterization of the specifications as either “design” or “performance.” The difference between performance specifications and design specifications is well established. Performance specifications “set forth an objective or standard to be achieved, and the successful bidder is expected to exercise his ingenuity in achieving that objective or standard of performance, selecting the means and assuming a corresponding responsibility for that selection.” J.L. Simmons Co. v. United States, 188 Ct.Cl. 684, 412 F.2d 1360, 1362 (Ct.Cl.1969). Design specifications, on the other hand, describe in precise detail the materials to be employed and the manner in which the work is to be performed. The contractor has no discretion to deviate from the specifications, but is “required to follow them as one would a road map.” Id. “Detailed design specifications contain an implied warranty that if they are followed, an acceptable result will be produced.” Stuyvesant Dredging Co. v. United States, 834 F.2d 1576, 1582 (Fed.Cir.1987) (citing United States v. Spearin, 248 U.S. 132, 39 S.Ct. 59, 63 L.Ed. 166 (1918)).

Blake argues that the specifications in question are performance specifications which describe one objective — that the electrical feeder system be installed in a manner which avoids conflict with the other trades. It offers these arguments in support of its contention. First, because the diagrammatic notes explicitly required Blake to avoid interference with the other trades, without detailing the exact manner in which this was to be accomplished, the contract gave Blake the discretion to employ the means it deemed best to achieve this goal, including underground installation. Second, because the electrical feeder system could not be installed exactly as depicted by the Navy’s drawings, and some alterations were necessary to avoid conflict with other trades, the specifications must by definition be “performance” because they did not provide the “road map” characteristically associated with a design specification. Because the specifications are “performance,” and because an underground installation was the best way to avoid conflict with other trades in the corridor, Blake concludes that the Navy’s directive ordering it to install the conduits overhead constituted a constructive change in the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Meltech Corporation, Inc.
Armed Services Board of Contract Appeals, 2026
Skanska USA Civil Southeast, Inc.
Armed Services Board of Contract Appeals, 2025
L.S. Black-Loeffel Civil Constructors JV
Armed Services Board of Contract Appeals, 2023
Sheffield Korte Joint Venture
Armed Services Board of Contract Appeals, 2023
Vigor Works, LLC
Armed Services Board of Contract Appeals, 2023
D&J Machinery, Inc.
Armed Services Board of Contract Appeals, 2022
Brantley Construction Services, LLC
Armed Services Board of Contract Appeals, 2021
ECC International, LLC
Armed Services Board of Contract Appeals, 2020
Meridian Engineering Company v. United States
885 F.3d 1351 (Federal Circuit, 2018)
weston/bean Joint Venture v. United States
123 Fed. Cl. 341 (Federal Claims, 2015)
Fireman's Fund Insurance v. United States
92 Fed. Cl. 598 (Federal Claims, 2010)
LB&B Associates Inc. v. United States
91 Fed. Cl. 142 (Federal Claims, 2010)
M. Maropakis Carpentry, Inc. v. United States
84 Fed. Cl. 182 (Federal Claims, 2008)
Metric Construction Co. v. United States
81 Fed. Cl. 804 (Federal Claims, 2008)
Caddell Construction Co. v. United States
78 Fed. Cl. 406 (Federal Claims, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
987 F.2d 743, 1993 WL 45083, Counsel Stack Legal Research, https://law.counselstack.com/opinion/blake-construction-company-inc-v-the-united-states-cafc-1993.