Berkeley Cement, Inc. v. Regents of the Univ. of Cal.

CourtCalifornia Court of Appeal
DecidedJanuary 7, 2019
DocketF073455
StatusPublished

This text of Berkeley Cement, Inc. v. Regents of the Univ. of Cal. (Berkeley Cement, Inc. v. Regents of the Univ. of Cal.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Berkeley Cement, Inc. v. Regents of the Univ. of Cal., (Cal. Ct. App. 2019).

Opinion

Filed 1/7/19

CERTIFIED FOR PARTIAL PUBLICATION *

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

FIFTH APPELLATE DISTRICT

BERKELEY CEMENT, INC., F073455, F073586 Plaintiff, Cross-defendant and Appellant, (Super. Ct. No. CV002452) v.

REGENTS OF THE UNIVERSITY OF OPINION CALIFORNIA,

Defendant, Cross-complainant and Respondent.

APPEAL from a judgment of the Superior Court of Merced County. Ronald W. Hansen, Judge. Hampton Firm and Kyle A. Hampton for Plaintiff, Cross-defendant and Appellant. Ralls Gruber & Niece, John W. Ralls, W. Samuel Niece and Anita W. Chu for Defendant, Cross-complainant and Respondent. -ooOoo- Plaintiff Berkeley Cement, Inc. (Berkeley) appeals from the judgment entered against it after a jury trial in this dispute over construction of a building on the Merced campus of the University of California. Berkeley contends the jury’s findings on the

* Pursuant to California Rules of Court, rules 8.1105(b) and 8.1110, this opinion is certified for publication with the exception of parts I, II, III, IV and V(A). complaint and on the cross-complaint were fatally inconsistent; the trial court incorrectly instructed the jury that a particular specification in the parties’ contract was a performance specification, rather than a design specification, based on an incorrect interpretation of the contract; the trial court improperly cut off plaintiff’s cross- examination of a key witness before it was complete; the trial court improperly excluded relevant evidence on the issue of damages after holding a hearing on its admissibility; and the trial court erred in including expert witness fees and mediation fees in its award of costs to defendant. We conclude the expert witness fees were improperly included in the award of costs, but no other error in the judgment has been demonstrated. We modify the judgment to exclude the award of expert fees and affirm. FACTUAL AND PROCEDURAL BACKGROUND Defendant Regents of the University of California (University) requested bids for construction of a social sciences and management building (SSMB) on University’s Merced campus. Berkeley submitted the low bid for the structural concrete work and was granted the contract. To create an attractive, energy efficient, and long-lasting structure, the plans and specifications called for a cast-in-place concrete building. Because the building was designed with architecturally exposed concrete, that is, areas exposed to view where the concrete itself was the finished surface of the building, the design specifications required a high quality concrete finish. They required the use of self-consolidating concrete in the architecturally exposed elements. They specified the aggregate (rock) to be used in the concrete in order to achieve a consistent color, and set a standard requiring minimization of the “bug holes” (voids in the concrete surface created by air pockets) in the architectural concrete. When self-consolidating concrete was used to construct walls and columns, the construction required erection of formwork into which the concrete was poured. The contract documents required Berkeley to prepare mock-ups prior to pouring the walls and columns in place, to “permit verification of workmanship and visual qualities of the final

2. completed installation.” The architectural finish of the concrete was affected by the concrete mix, the formwork, and the placement of the concrete in the formwork. Problems arose, delaying Berkeley’s performance. The aggregate specified in the contract documents was not immediately available, and Berkeley used a substitute, which was later approved by University. Mock-ups were rejected by University; the concrete in the mock-ups exhibited bug holes excessive in quantity and size, rock pockets, discoloration, striations or “tiger striping,” and honeycombing. Berkeley also experienced formwork “blowouts,” where the formwork broke and the wall had to be redone. There was evidence the formwork Berkeley rented from its initial supplier was not designed for the pressures exerted by the self-consolidating concrete, which were higher than those exerted on formwork by conventional concrete. Because of these and other difficulties, the concrete work fell behind schedule. Eventually, Berkeley engaged a subcontractor to provide and install formwork, in lieu of the rented and self-installed formwork it used initially. Additionally, University permitted Berkeley to complete the project using flowable conventional concrete, with which Berkeley was more familiar, instead of the self-consolidating concrete called for in the contract. Construction of the building was completed, and University paid Berkeley the full contract price for its work. Berkeley submitted a Claim for Equitable Adjustment against University, seeking compensation for work it performed, which it claimed was extra work outside the contract. University denied the claim. Berkeley filed this action, alleging causes of action for breach of contract, breach of the implied covenant of good faith and fair dealing, and breach of the implied covenant of the correctness of the plans and specifications. It sought to recover compensation for alleged extra work and delays in construction, which it blamed on defective specifications for the concrete mix and University’s alleged interference with Berkeley’s performance by improperly rejecting its proposed concrete mix design, shop drawings, and mockups. University cross-

3. complained against Berkeley for breach of contract, alleging the architectural concrete finish of the building did not meet the contract standards for uniformity of color and lack of bug holes, and Berkeley did not perform within the contract time, causing University to incur additional expenses. After a lengthy jury trial, the jury found University did not breach the contract or either of the implied covenants; on the cross-complaint, it found Berkeley breached the contract, but University was not harmed by the breach. Berkeley’s motion for judgment notwithstanding the verdict or for a new trial was denied. The trial court awarded costs to University. Berkeley appeals, challenging the judgment against it on its complaint and certain costs awarded. 1 DISCUSSION I. Inconsistent Verdict Berkeley contends the findings of the jury contained in the special verdict are fatally inconsistent, requiring a new trial. A fact finder may not make inconsistent factual determinations based on the same evidence. (Oxford v. Foster Wheeler LLC (2009) 177 Cal.App.4th 700, 707 (Oxford).) “ ‘An inconsistent verdict may arise from an inconsistency between or among answers within a special verdict [citation] or irreconcilable findings. [Citation.] Where there is an inconsistency between or among answers within a special verdict, both or all the questions are equally against the law. [Citation.] The appellate court is not permitted to choose between inconsistent answers.’ ” (Id. at p. 716.) “ ‘The proper remedy for an inconsistent special verdict is a new trial.’ ” (Trejo v. Johnson & Johnson (2017) 13 Cal.App.5th 110, 124.) “The standard of review for inconsistency in a special verdict is de novo.” (Ibid.)

1 The two appeals have been consolidated.

4. When “the jury’s findings are so inconsistent that they are incapable of being reconciled and it is impossible to tell how a material issue is determined, the decision is ‘against law,’ ” justifying a new trial. (Oxford, supra, 177 Cal.App.4th at p. 716.) If the verdict is not hopelessly ambiguous or fatally inconsistent, the court may interpret the verdict, considering its language and anything in the proceeding that serves to show with some certainty what the jury intended. The court may consider the pleadings, the evidence, the admissions of the parties, the instructions, and the forms of verdict submitted. (Zagami, Inc. v. James A. Crone, Inc.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Spearin
248 U.S. 132 (Supreme Court, 1918)
Blake Construction Company, Inc. v. The United States
987 F.2d 743 (Federal Circuit, 1993)
Jones v. Farmers Ins. Exchange CA2/3
221 Cal. App. 4th 986 (California Court of Appeal, 2013)
Bole v. Bole
172 P.2d 936 (California Court of Appeal, 1946)
In Re Marriage of Connolly
591 P.2d 911 (California Supreme Court, 1979)
Bristow v. Ferguson
121 Cal. App. 3d 823 (California Court of Appeal, 1981)
West v. Duncan
205 Cal. App. 2d 140 (California Court of Appeal, 1962)
FOOTHILL-DE ANZA COMMUNITY COLLEGE DISTRICT v. Emerich
69 Cal. Rptr. 3d 678 (California Court of Appeal, 2007)
Anthony v. City of Los Angeles
166 Cal. App. 4th 1011 (California Court of Appeal, 2008)
Shaw v. Hughes Aircraft Co.
100 Cal. Rptr. 2d 446 (California Court of Appeal, 2000)
Gibson v. Bobroff
49 Cal. App. 4th 1202 (California Court of Appeal, 1996)
Seever v. Copley Press, Inc.
47 Cal. Rptr. 3d 206 (California Court of Appeal, 2006)
In Re Marriage of Carlsson
163 Cal. App. 4th 281 (California Court of Appeal, 2008)
Ladas v. California State Automobile Ass'n
19 Cal. App. 4th 761 (California Court of Appeal, 1993)
Baker-Hoey v. Lockheed Martin Corp.
3 Cal. Rptr. 3d 593 (California Court of Appeal, 2003)
Oxford v. Foster Wheeler LLC
177 Cal. App. 4th 700 (California Court of Appeal, 2009)
Zagami, Inc. v. James A. Crone, Inc.
74 Cal. Rptr. 3d 235 (California Court of Appeal, 2008)
Ripley v. Pappadopoulos
23 Cal. App. 4th 1616 (California Court of Appeal, 1994)
Jeld-Wen, Inc. v. Superior Court
53 Cal. Rptr. 3d 115 (California Court of Appeal, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
Berkeley Cement, Inc. v. Regents of the Univ. of Cal., Counsel Stack Legal Research, https://law.counselstack.com/opinion/berkeley-cement-inc-v-regents-of-the-univ-of-cal-calctapp-2019.